Sprint Pulse

Engineering Pulse — Org Adservio ADS Q4 W40 - 05-09 Oct

Aggregated sprint ADS Q4 W40 - 05-09 Oct • deduplicated roll-up across included teams

This org roll-up aggregates deduplicated frozen issue facts across 4 team snapshots. Count metrics link to snapshot-exact JQL result pages. Jira IDs in the report link to live Jira issues.

Download DOCX

Executive summary

Yellow. The sprint closed 48/86 visible items. The org roll-up absorbed noise reasonably well — 14/22 added items were closed — but predictability on committed work was only 52.2% (35/67), and bugs made up 45.8% of completed items. The main drag was execution system quality, not readiness: 12/32 carryovers had been marked Ready at planning time.

Top-line metrics

MetricValueHow to read it
Committed completion52.2% (35/67)Planned items marked Done ÷ all planned committed items
Committed carryover47.8% (32/67)Planned committed carryovers ÷ all planned committed items
Finish predictability53.7% (29/54)Finish-intent planned items done ÷ all finish-intent planned items
Progress predictability58.3% (7/12)Progress items that behaved as intended by carrying
Added-during-sprint load25.6% (22/86)Added items ÷ all visible items
Added work closure14/22All added items marked Done
Reactive load (bug share)45.8% (22/48)Completed bugs ÷ all completed work
Planning quality35.8% (24/67)Committed items marked Ready ÷ all committed items
Workflow-truth mismatches12Items marked Done in review while workflow status remained non-final

Engineering readout

Across included teams, the sprint did not fail; it traded predictability for responsiveness. 14/22 added items were closed, but that responsiveness came with 45.8% bug share and diluted committed completion.

The miss pattern is concentrated: 11 partial-completion carryovers, 5 dependency-driven misses, and 13 committed items that never really started.

Most misses were not caused by poor readiness. 12 of the 32 carryovers had been marked Ready, so the stronger hypothesis is breakdown, sequencing, and capacity protection rather than simple scoping immaturity.

Delivered work mix

TypePlannedAddedStretchUnclearTotal doneDone %
Story9000918.8%
Task88001633.3%
Bug166002245.8%

Committed work: plan vs execution

SignalValueWhy it matters
Committed items67Explicit promise set
Committed done35Closed as promised
Committed carry over32Unfinished promise
Committed items marked Ready24Planning-quality input
Carryovers marked Ready12Ready did not guarantee finish
Carryovers not started13Execution focus gap
Carryovers started but unfinished16Work moved, but did not close

Carryover pattern

Jira itemOwnerStatusWhy it carried
ADS-3757 — Story — [Site] - Actualizare website AdservioPetronel PavelIn ProgressPartial completion
ADS-7354 — Story — [Abonamente] - Gestionare recurență pachete anualeEdgar AlexaIn ProgressDependency delay
ADS-7803 — Task — [FE/BE/MOB/UNI] - TitulaturaIvan IoanaReady for testingDependency delay
ADS-7817 — Story — [SIIIR] - Import cadre didacticeMarian AndreiIn ProgressPartial completion
ADS-8164 — Story — [Burse] - US6 - RapoarteIonut CiolanIn ProgressLate start / sequencing
ADS-8260 — Bug — [Prod][AWS][Web] Global-message modal fails on missing CMC metadata, including teacher-tab HTTP 500Marian AndreiTo DoNot started
ADS-8567 — Story — NOMENCLATOR - Refactor structura clasaAndrei DraganIn ProgressPartial completion
ADS-8679 — Story — Refactor student, situatie scolarastefan.achimIn ProgressPartial completion
ADS-8733 — Bug — [Prod][Billing] Custom Invoice workload exposes premature PostgreSQL client release and slow pending-charge aggregationEdgar AlexaTo DoNot started
ADS-8757 — Story — [Billing] - Migrat tot codul pe NestGeorge MurgociIn ProgressPartial completion
ADS-8763 — Task — [Asachi][BE] Import studenti pentru anul universitar 2026-2027andrei.alexandruIn ProgressDependency delay
ADS-8769 — Improvement — [Abonamente][Admin][Statistici] - UpdatesEdgar AlexaIn ProgressPartial completion
ADS-8798 — Task — [MOB][FE] - Front end optimizations for mobile appDragoș IvanIn ProgressPartial completion
ADS-8804 — Bug — [Asachi] - Student duplicat in catalog de restantieri la descarcareandrei.alexandruTo DoNot started
ADS-8810 — Bug — [Asachi] - Eroare alocare restantieristefan.achimIn ProgressDependency delay
ADS-8866 — Bug — [Asachi] - Problema echivalariAndreea MoldovanuTo DoNot started
ADS-8938 — Bug — [Asachi] - Problema echivalariTo DoNot started
ADS-8953 — Bug — [BE] statistici- valorile pentru mediul de provenienta sunt afisate gresit pentru anul scolar anteriorAndrei DraganTestingPartial completion
ADS-8955 — Task — Implement discipline elements on annual averageStefan AgrigoroaeiIn ProgressPartial completion
ADS-8997 — Story — [Mobile] - New User Experience PolishStefan AgrigoroaeiTo DoNot started
ADS-9019 — Task — stergere "servicii asignate" ID 1680Edgar AlexaTo DoDependency delay
ADS-9027 — Bug — [MOB] Imposibilitate autentificare in contstefan musatTo DoNot started
ADS-9032 — Bug — [Prod] - Eroare la emiterea adeverintei de absolvireIonut CiolanIn ProgressPartial completion
ADS-9063 — Bug — [MOB] pagina alba la accesarea Grupuri din perspectiva de parintestefan musatTo DoNot started
ADS-9065 — Bug — [MOB] Lipsa subscriptiestefan musatTo DoNot started
ADS-9068 — Improvement — Move fs events to object + previous_values; stop signalling moves via a `moved` field on createdAndrei DraganTo DoNot started
ADS-9078 — Story — Investigate login, subs, refresh token mechanismstefan musatTo DoNot started
ADS-9080 — Story — Create unit testing for Reports, Subjects, Activites, NewsfeedStefan AgrigoroaeiIn ProgressPartial completion
ADS-9095 — Task — [FE]: Fix erori din consolaIvan IoanaTo DoNot started
ADS-9102 — Task — [BE] Change response status codeMarian AndreiIn ProgressLate start / sequencing
ADS-9106 — Task — [Notifications] - Refactor notificări proiecte NodeDragoș IvanTo Do
ADS-9134 — Bug — [Prod][AWS][Billing] Core-service deletion returns 500 on undefined ORM primaryKeysEdgar AlexaTo DoNot started

Miss pattern summary

PatternCountWhat it suggests
Partial completion11Breakdown / sizing / stage-gating was not tight enough
Dependency delay5Capacity protection or dependency timing created slip
Not started13A committed item remained outside execution focus
In Progress / Code Review carryovers16Most misses were moving, but not closing

Workflow-truth mismatches

Items marked Done in the sprint-review field while Jira workflow status was still non-final.

Jira itemStatusIntent
ADS-8161 — [Burse] - US4 - Alocare burseReady to mergeProgress
ADS-8162 — [Burse] - US5 - PlatiReady to mergeFinish
ADS-8166 — [Burse] - US7 - View Student/actiuni studentReady to mergeProgress
ADS-8812 — Download RMReady to mergeFinish
ADS-8879 — [Asachi] - Eroare acces student in UMSReady for testingFinish
ADS-8972 — [Asachi] - Problema incheiere media anuala masterReady for testingFinish
ADS-8985 — [Prod][AWS][Web] Registration confirmation returns 500 on duplicate usernameReady to mergeFinish
ADS-9044 — [Cazari] - nu se actualizeaza corect datele din Obligatie plataReady to merge
ADS-9047 — Adaugare coordonator clasa in lista de destinatari propusiIn ProgressFinish
ADS-9064 — [SIIIR] - Elevi duplicati WurmbrandIn ProgressFinish
ADS-9117 — sincronizare SIIR id 7197In Progress
ADS-9125 — [Cazari] - Corectie sold conform fisa studentului + student duplicat cu status cazatReady to merge

Executive follow-up questions

QuestionWhy this mattersWhat evidence to ask for
Why did committed items carry over despite planning readiness?This tests execution quality rather than just scope quality.Show carryovers split by progress continuation, dependency, and not-started.
Are Progress items being managed intentionally?Progress items are allowed to continue, but the continuation should be visible and controlled.Show the original slice and the specific landing expectation for each item.
Is added work a healthy responsiveness level or chronic interruption?High responsiveness can hide systemic instability and diluted predictability.Show which added items were urgent/reactive versus discretionary scope change.
Can we trust Done in review when workflow is still non-final?Workflow-truth gaps reduce trust and make completion easy to game.Show the exact mismatches and the completion rule to enforce next sprint.

Included teams in this org pulse: Mobile, Team 1, Team 2, University.

Usage note: start with the top-line metrics, then use the traceability links to answer these questions with issue-level evidence.

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list7373 issues in the planning snapshot
Sprint review / outcome snapshot raw list9696 issues in the Friday review snapshot
Normalized sprint fact base8686 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

These companion artifacts keep the pulse debuggable when a leader wants the exact rows behind a metric or a count.