Executive summary

Yellow. The sprint closed 50/86 visible items. The org roll-up absorbed noise reasonably well — 21/25 added items were closed — but predictability on committed work was only 47.5% (29/61), and bugs made up 56.0% of completed items. The main drag was execution system quality, not readiness: 12/32 carryovers had been marked Ready at planning time.

Top-line metrics

MetricValueHow to read it
Committed completion47.5% (29/61)Planned items marked Done ÷ all planned committed items
Committed carryover52.5% (32/61)Planned committed carryovers ÷ all planned committed items
Finish predictability55.1% (27/49)Finish-intent planned items done ÷ all finish-intent planned items
Progress predictability100.0% (8/8)Progress items that behaved as intended by carrying
Added-during-sprint load29.1% (25/86)Added items ÷ all visible items
Added work closure21/25All added items marked Done
Reactive load (bug share)56.0% (28/50)Completed bugs ÷ all completed work
Planning quality39.3% (24/61)Committed items marked Ready ÷ all committed items
Workflow-truth mismatches9Items marked Done in review while workflow status remained non-final

Engineering readout

Across included teams, the sprint did not fail; it traded predictability for responsiveness. 21/25 added items were closed, but that responsiveness came with 56.0% bug share and diluted committed completion.

The miss pattern is concentrated: 16 partial-completion carryovers, 2 dependency-driven misses, and 10 committed items that never really started.

Most misses were not caused by poor readiness. 12 of the 32 carryovers had been marked Ready, so the stronger hypothesis is breakdown, sequencing, and capacity protection rather than simple scoping immaturity.

Delivered work mix

TypePlannedAddedStretchUnclearTotal doneDone %
Story3200510.0%
Task96001530.0%
Bug1612002856.0%

Committed work: plan vs execution

SignalValueWhy it matters
Committed items61Explicit promise set
Committed done29Closed as promised
Committed carry over32Unfinished promise
Committed items marked Ready24Planning-quality input
Carryovers marked Ready12Ready did not guarantee finish
Carryovers not started10Execution focus gap
Carryovers started but unfinished13Work moved, but did not close

Carryover pattern

Jira itemOwnerStatusWhy it carried
ADS-7354 — Story — [Abonamente] - Gestionare recurență pachete anualeEdgar AlexaReady for testingPartial completion
ADS-7474 — Task — [FE] - Optimizare viteză de încărcare paginiAlex MurarescuTo DoNot started
ADS-7803 — Task — [FE/BE/MOB/UNI] - TitulaturaIvan IoanaReady for testingPartial completion
ADS-7817 — Story — [SIIIR] - Import cadre didacticeMarian AndreiIn ProgressPartial completion
ADS-7849 — Story — Stergere date S3Cojan Paul-CatalinTo DoPriority Change
ADS-8164 — Story — [Burse] - US6 - RapoarteDana-Mihaela MarițcaIn ProgressPartial completion
ADS-8260 — Bug — [Prod][AWS][Web] Global-message modal fails on missing CMC metadata, including teacher-tab HTTP 500Marian AndreiTo DoNot started
ADS-8543 — Story — Flux alocare automata burse de performantaIonut CiolanIn ProgressLate start / sequencing
ADS-8567 — Story — NOMENCLATOR - Refactor structura clasaAndrei DraganIn ProgressPartial completion
ADS-8584 — Improvement — [Asachi]-Adaugare ,,Status student" in Clasamentul studentilor din modulul Statistici si rapoarteandrei.alexandruTo DoNot started
ADS-8679 — Story — Refactor student, situatie scolarastefan.achimIn ProgressPartial completion
ADS-8733 — Bug — [Prod][Billing] - Refactor charges cronEdgar AlexaTo DoPartial completion
ADS-8757 — Story — [Billing] - Migrat tot codul pe NestGeorge MurgociIn ProgressPartial completion
ADS-8763 — Task — [Asachi][BE] Import studenti pentru anul universitar 2026-2027andrei.alexandruIn ProgressDependency delay
ADS-8866 — Bug — [Asachi] - Problema echivalariAndreea MoldovanuTo DoNot started
ADS-8938 — Bug — [Asachi] - Problema echivalariTo DoNot started
ADS-8955 — Task — Implement discipline elements on annual averageStefan AgrigoroaeiIn ProgressPriority Change
ADS-8972 — Bug — [Asachi] - Problema incheiere media anuala masterReady for testingPartial completion
ADS-8981 — Task — Sterge permisiunile vechi - scholarship allocationandrei.alexandruIn ProgressPartial completion
ADS-8997 — Story — [Mobile] - New User Experience PolishStefan AgrigoroaeiTo DoNot started
ADS-9019 — Task — stergere "servicii asignate" ID 1680Edgar AlexaTo DoPartial completion
ADS-9032 — Bug — [Prod] - Eroare la emiterea adeverintei de absolvireandrei.alexandruIn ProgressBug / rework pressure
ADS-9047 — Task — Adaugare coordonator clasa in lista de destinatari propusiPetronel PavelReady for testingDependency delay
ADS-9068 — Improvement — Move fs events to object + previous_values; stop signalling moves via a `moved` field on createdAndrei DraganTo DoNot started
ADS-9080 — Story — Create unit testing for Reports, Subjects, Activites, NewsfeedStefan AgrigoroaeiTestingPartial completion
ADS-9095 — Task — [FE]: Fix erori din consolaIvan IoanaTo DoNot started
ADS-9102 — Task — [BE] Change response status codeMarian AndreiReady for testingPartial completion
ADS-9106 — Task — [Notifications] - Refactor notificări proiecte NodeDragoș IvanTo DoNot started
ADS-9130 — Task — [FE/BE/MOB] - Cleanup vechea pagina de incadrareAndrei DraganIn ProgressPartial completion
ADS-9149 — Task — Feature flags - Evolutie elevStefan AgrigoroaeiTestingPartial completion
ADS-9166 — Bug — [TUIASI] Shared database write stall blocked SSO logins and report creation on Oct 12Ionut CiolanTo DoNot started
ADS-9167 — Task — [BE]: Reset activation code timer after email/phone changeAndrei DraganReady for testingPartial completion

Miss pattern summary

PatternCountWhat it suggests
Partial completion16Breakdown / sizing / stage-gating was not tight enough
Dependency delay2Capacity protection or dependency timing created slip
Not started10A committed item remained outside execution focus
In Progress / Code Review carryovers13Most misses were moving, but not closing

Workflow-truth mismatches

Items marked Done in the sprint-review field while Jira workflow status was still non-final.

Jira itemStatusIntent
ADS-8371 — [Prod][AWS][uni-api] Student create leaves disciplines unassigned when AcademicPlan is missing - 2 errors/72hTo Do
ADS-8798 — [MOB][FE] - Local front-end proxy for mobile appTo DoFinish
ADS-8804 — [Asachi] - Student duplicat in catalog de restantieri la descarcareReady to mergeFinish
ADS-8879 — [Asachi] - Eroare acces student in UMSReady for testingFinish
ADS-9045 — Schimbări flow comparator și pagină de succes în urma achiziției unui pachetIn Progress
ADS-9161 — [Asachi] - Nu afiseaza anii de studiu in situatia scolara a studentuluiReady to mergeFinish
ADS-9191 — [Prod][TUIASI][uni-api] Discipline name edit fails when translation replacement deletes a referenced localizationTo Do
ADS-9194 — [Notificări] - Enhance notificări Web/Push cu icon și urlTesting
ADS-9195 — [FE] Eroare 400 la incercarea de a sterge o clasaIn Progress

Executive follow-up questions

QuestionWhy this mattersWhat evidence to ask for
Why did committed items carry over despite planning readiness?This tests execution quality rather than just scope quality.Show carryovers split by progress continuation, dependency, and not-started.
Are Progress items being managed intentionally?Progress items are allowed to continue, but the continuation should be visible and controlled.Show the original slice and the specific landing expectation for each item.
Is added work a healthy responsiveness level or chronic interruption?High responsiveness can hide systemic instability and diluted predictability.Show which added items were urgent/reactive versus discretionary scope change.
Can we trust Done in review when workflow is still non-final?Workflow-truth gaps reduce trust and make completion easy to game.Show the exact mismatches and the completion rule to enforce next sprint.

Included teams in this org pulse: Mobile, Team 1, Team 2, University.

Usage note: start with the top-line metrics, then use the traceability links to answer these questions with issue-level evidence.

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list7171 issues in the planning snapshot
Sprint review / outcome snapshot raw list9797 issues in the Friday review snapshot
Normalized sprint fact base8686 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

These companion artifacts keep the pulse debuggable when a leader wants the exact rows behind a metric or a count.