Sprint Pulse

Engineering Pulse — Org Adservio ADS Q4 W43 - 26-30 Oct

Aggregated sprint ADS Q4 W43 - 26-30 Oct • deduplicated roll-up across included teams

This org roll-up aggregates deduplicated frozen issue facts across 5 team snapshots. Count metrics link to snapshot-exact JQL result pages. Jira IDs in the report link to live Jira issues.

Download DOCX

Executive summary

Yellow. The sprint closed 42/83 visible items. The org roll-up absorbed noise reasonably well — 10/23 added items were closed — but predictability on committed work was only 50.0% (32/64), and bugs made up 33.3% of completed items. The main drag was execution system quality, not readiness: 7/32 carryovers had been marked Ready at planning time.

Top-line metrics

MetricValueHow to read it
Committed completion50.0% (32/64)Planned items marked Done ÷ all planned committed items
Committed carryover50.0% (32/64)Planned committed carryovers ÷ all planned committed items
Finish predictability55.1% (27/49)Finish-intent planned items done ÷ all finish-intent planned items
Progress predictability69.2% (9/13)Progress items that behaved as intended by carrying
Added-during-sprint load27.7% (23/83)Added items ÷ all visible items
Added work closure10/23All added items marked Done
Reactive load (bug share)33.3% (14/42)Completed bugs ÷ all completed work
Planning quality31.2% (20/64)Committed items marked Ready ÷ all committed items
Workflow-truth mismatches8Items marked Done in review while workflow status remained non-final

Engineering readout

Across included teams, the sprint did not fail; it traded predictability for responsiveness. 10/23 added items were closed, but that responsiveness came with 33.3% bug share and diluted committed completion.

The miss pattern is concentrated: 10 partial-completion carryovers, 5 dependency-driven misses, and 16 committed items that never really started.

Most misses were not caused by poor readiness. 7 of the 32 carryovers had been marked Ready, so the stronger hypothesis is breakdown, sequencing, and capacity protection rather than simple scoping immaturity.

Delivered work mix

TypePlannedAddedStretchUnclearTotal doneDone %
Story101001126.2%
Task105001535.7%
Bug113001433.3%

Committed work: plan vs execution

SignalValueWhy it matters
Committed items64Explicit promise set
Committed done32Closed as promised
Committed carry over32Unfinished promise
Committed items marked Ready20Planning-quality input
Carryovers marked Ready7Ready did not guarantee finish
Carryovers not started16Execution focus gap
Carryovers started but unfinished12Work moved, but did not close

Carryover pattern

Jira itemOwnerStatusWhy it carried
ADS-1321 — Story — [BE][LCY][FE] - Adding to the student edit several mother tonguesCojan Paul-CatalinTo DoNot started
ADS-5101 — Story — 3. [ISJ Account] Rapoarte agregate in contul ISJIvan IoanaTo DoNot started
ADS-6725 — Improvement — Adeverinta de elevPetronel PavelTo DoPartial completion
ADS-8543 — Story — Flux alocare automata burse de performantaIonut CiolanIn ProgressDependency delay
ADS-8567 — Story — NOMENCLATOR - Refactor structura clasaAndrei DraganTestingPartial completion
ADS-8576 — Story — [Elev][Parinte] - Redesign Note si absente - WebPetronel PavelReady for testingPartial completion
ADS-8679 — Story — Refactor student, situatie scolarastefan.achimTestingPartial completion
ADS-8753 — Improvement — Calcul credite in functie de nr total credite la disciplinele impuseandrei.alexandruTo DoNot started
ADS-8763 — Task — [Asachi][BE] Import studenti pentru anul universitar 2026-2027andrei.alexandruIn ProgressDependency delay
ADS-8944 — Story — Inchidere a tuturor cataloagelorstefan.achimIn ProgressPartial completion
ADS-9019 — Task — stergere "servicii asignate" ID 1680Edgar AlexaTo DoNot started
ADS-9024 — Story — Cerinte CentralizatorMagda GradinaruTo DoBreakdown issue
ADS-9047 — Task — Adaugare coordonator clasa in lista de destinatari propusiAntoci RazvanCode ReviewDependency delay
ADS-9068 — Improvement — Move fs events to object + previous_values; stop signalling moves via a `moved` field on createdAndrei DraganTo DoNot started
ADS-9102 — Task — [BE] Change response status codeMarian AndreiReady for testingPartial completion
ADS-9106 — Story — [Notifications] - Refactor notificări proiecte NodeDragoș IvanIn ProgressNot started
ADS-9151 — Bug — [UNMB] - Afisare eronata in lista de dropdown la tipul si categoria studentului din modulul StudentiTo DoNot started
ADS-9166 — Bug — [TUIASI] Shared database write stall blocked SSO logins and report creation on Oct 12Ionut CiolanTo DoNot started
ADS-9210 — Task — Migrare Timezone GMT+3 -> UTCAlex MurarescuIn ProgressPartial completion
ADS-9212 — Bug — [ANMGD-CLUJ] - Eroare la import studentiandrei.alexandruTo DoNot started
ADS-9239 — Task — raport orarDaniel OnisoruTo DoNot started
ADS-9259 — Task — Download RM cu Observatii si Semnataristefan.achimIn ProgressDependency delay
ADS-9265 — Task — Product Analytics v2 (team1)Marian AndreiIn ProgressPartial completion
ADS-9297 — Bug — [FE] calcul medie purtare -nu e setata by default purtare standard romaniaAndrei DraganTo DoNot started
ADS-9298 — Story — Remove FLAG_WELLBEING_AI_SUMMARYAlex MurarescuIn ProgressPartial completion
ADS-9315 — Bug — [Prod][TUIASI][rooms-api] Failing health probe restarts PHP-FPM and removes the only endpointIonut CiolanTo DoDependency delay
ADS-9328 — Story — [SUPERSET] Product analytics pentru SIIRMarian AndreiTo DoNot started
ADS-9332 — Improvement — Adaugare nr absente in statistica CESPetronel PavelIn ProgressPartial completion
ADS-9354 — Bug — [Prod] - Plan de invatamant - date lipsa la incarcare si discipline afisate in engleza la descarcareandrei.alexandruTo DoNot started
ADS-9373 — Task — [Subscriptions] - Design notificări abonamenteDaniel GîrbeaTo DoNot started
ADS-9375 — Bug — [Prod][TUIASI][uni-api] Role-cache update fails on null upstream roles after clearing cacheandrei.alexandruTo DoNot started
ADS-9385 — Bug — [FE] la transfer intre clase, nu s-au copiat notele si absenteleAndrei DraganTo DoNot started

Miss pattern summary

PatternCountWhat it suggests
Partial completion10Breakdown / sizing / stage-gating was not tight enough
Dependency delay5Capacity protection or dependency timing created slip
Not started16A committed item remained outside execution focus
In Progress / Code Review carryovers12Most misses were moving, but not closing

Workflow-truth mismatches

Items marked Done in the sprint-review field while Jira workflow status was still non-final.

Jira itemStatusIntent
ADS-8180 — [Registre Matricole] - US4 Download macheta RMUCode ReviewProgress
ADS-8757 — [Billing] - Migrat tot codul pe NestIn ProgressProgress
ADS-8818 — [Asachi] - Lipsa alocare studenti in sesiunea 2Ready for testingFinish
ADS-8997 — [Mobile] - New User Experience PolishReady for testingFinish
ADS-9080 — Create unit testing for Reports, Subjects, Activites, NewsfeedTestingFinish
ADS-9324 — Student/parents subject/evolution improvementsReady for testingFinish
ADS-9338 — Upgrade abonamente cumpărate Părinte+ la SuperPărinteTo Do
ADS-9372 — Fix add grade issue on last day of moduleReady for testing

Executive follow-up questions

QuestionWhy this mattersWhat evidence to ask for
Why did committed items carry over despite planning readiness?This tests execution quality rather than just scope quality.Show carryovers split by progress continuation, dependency, and not-started.
Are Progress items being managed intentionally?Progress items are allowed to continue, but the continuation should be visible and controlled.Show the original slice and the specific landing expectation for each item.
Is added work a healthy responsiveness level or chronic interruption?High responsiveness can hide systemic instability and diluted predictability.Show which added items were urgent/reactive versus discretionary scope change.
Can we trust Done in review when workflow is still non-final?Workflow-truth gaps reduce trust and make completion easy to game.Show the exact mismatches and the completion rule to enforce next sprint.

Included teams in this org pulse: Mobile, Platform, Team 1, Team 2, University.

Usage note: start with the top-line metrics, then use the traceability links to answer these questions with issue-level evidence.

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list6161 issues in the planning snapshot
Sprint review / outcome snapshot raw list8585 issues in the Friday review snapshot
Normalized sprint fact base8383 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

These companion artifacts keep the pulse debuggable when a leader wants the exact rows behind a metric or a count.