Sprint Pulse

Engineering Pulse — Org Adservio ADS Q4 W44 - 02-06 Nov

Aggregated sprint ADS Q4 W44 - 02-06 Nov • deduplicated roll-up across included teams

This org roll-up aggregates deduplicated frozen issue facts across 5 team snapshots. Count metrics link to snapshot-exact JQL result pages. Jira IDs in the report link to live Jira issues.

Download DOCX

Executive summary

Yellow. The sprint closed 52/101 visible items. The org roll-up absorbed noise reasonably well — 25/39 added items were closed — but predictability on committed work was only 43.1% (28/65), and bugs made up 34.6% of completed items. The main drag was execution system quality, not readiness: 11/37 carryovers had been marked Ready at planning time.

Top-line metrics

MetricValueHow to read it
Committed completion43.1% (28/65)Planned items marked Done ÷ all planned committed items
Committed carryover56.9% (37/65)Planned committed carryovers ÷ all planned committed items
Finish predictability48.0% (24/50)Finish-intent planned items done ÷ all finish-intent planned items
Progress predictability73.3% (11/15)Progress items that behaved as intended by carrying
Added-during-sprint load38.6% (39/101)Added items ÷ all visible items
Added work closure25/39All added items marked Done
Reactive load (bug share)34.6% (18/52)Completed bugs ÷ all completed work
Planning quality36.9% (24/65)Committed items marked Ready ÷ all committed items
Workflow-truth mismatches0Items marked Done in review while workflow status remained non-final

Engineering readout

Across included teams, the sprint did not fail; it traded predictability for responsiveness. 25/39 added items were closed, but that responsiveness came with 34.6% bug share and diluted committed completion.

The miss pattern is concentrated: 13 partial-completion carryovers, 7 dependency-driven misses, and 12 committed items that never really started.

Most misses were not caused by poor readiness. 11 of the 37 carryovers had been marked Ready, so the stronger hypothesis is breakdown, sequencing, and capacity protection rather than simple scoping immaturity.

Delivered work mix

TypePlannedAddedStretchUnclearTotal doneDone %
Story110001121.2%
Task613001936.5%
Bug810001834.6%

Committed work: plan vs execution

SignalValueWhy it matters
Committed items65Explicit promise set
Committed done28Closed as promised
Committed carry over37Unfinished promise
Committed items marked Ready24Planning-quality input
Carryovers marked Ready11Ready did not guarantee finish
Carryovers not started12Execution focus gap
Carryovers started but unfinished20Work moved, but did not close

Carryover pattern

Jira itemOwnerStatusWhy it carried
ADS-1321 — Story — [BE][LCY][FE] - Adding to the student edit several mother tonguesCojan Paul-CatalinTo DoNot started
ADS-6725 — Improvement — Adeverinta de elevPetronel PavelTo DoNot started
ADS-7560 — Story — Examinari studentiIonut CiolanIn ProgressPartial completion
ADS-7696 — Task — Alerta trimitere facturi in SPVGeorge MurgociIn ProgressPartial completion
ADS-8444 — Bug — [AWS prod][Mesaje] User search crashes on Unicode collation mismatchMarian AndreiTo DoNot started
ADS-8543 — Story — Flux alocare automata burse de performantaIonut CiolanTestingDependency delay
ADS-8596 — Task — Notificari SubscriptiiDragoș IvanIn ProgressDependency delay
ADS-8679 — Story — Refactor student, situatie scolarastefan.achimTestingDependency delay
ADS-9019 — Task — stergere "servicii asignate" ID 1680Edgar AlexaIn ProgressPartial completion
ADS-9068 — Improvement — Move fs events to object + previous_values; stop signalling moves via a `moved` field on createdAndrei DraganTo DoNot started
ADS-9080 — Story — Create unit testing for Reports, Subjects, Activites, NewsfeedStefan AgrigoroaeiReady to mergePartial completion
ADS-9102 — Task — [BE] Change response status codeDaniel OnisoruCode ReviewDependency delay
ADS-9166 — Bug — [TUIASI] Shared database write stall blocked SSO logins and report creation on Oct 12Ionut CiolanTo DoNot started
ADS-9187 — Story — Adauga forme de finantarestefan.achimIn ProgressPartial completion
ADS-9210 — Task — Migrare Timezone GMT+3 -> UTCAlex MurarescuIn ProgressPartial completion
ADS-9235 — Story — [Mobile] - Standarde de evaluareStefan AgrigoroaeiTo Do
ADS-9239 — Task — raport orarDaniel OnisoruTo DoNot started
ADS-9259 — Task — Download RM cu Observatii si Semnataristefan.achimIn ProgressDependency delay
ADS-9265 — Task — Product Analytics v2 (team1)Marian AndreiIn ProgressPartial completion
ADS-9297 — Bug — [FE] calcul medie purtare -nu e setata by default purtare standard romaniaAndrei DraganTestingLate start / sequencing
ADS-9298 — Story — Remove FLAG_WELLBEING_AI_SUMMARYAlex MurarescuIn ProgressPartial completion
ADS-9315 — Bug — [Prod][TUIASI][rooms-api] Failing health probe restarts PHP-FPM and removes the only endpointIonut CiolanIn ProgressPartial completion
ADS-9340 — Task — [FE][Mob] - Date elevi inactiviStefan AgrigoroaeiIn ProgressPriority Change
ADS-9344 — Bug — [Prod][AWS][Web] Class repartition returns HTTP 500 on exemption foreign keyMarian AndreiTo DoNot started
ADS-9355 — Story — [AI] Agent Vio de code review pe MR-uri GitLab (orice proiect)Marian AndreiIn ProgressPartial completion
ADS-9384 — Story — Adauga view IBAN pt studenti in modulul de burseIuliana GugeanuReady for testingDependency delay
ADS-9385 — Bug — [FE] la transfer intre clase, nu s-au copiat notele si absenteleAndrei DraganTo DoNot started
ADS-9392 — Bug — [Prod][Notifications] notifications-event-manager crashes overnight on "MySQL server has gone away": tenant DB connection is reused past wait_timeoutMarian AndreiIn ProgressPartial completion
ADS-9393 — Bug — [Security][Frontend] Upgrade Storybook 10.1.11 to 10.6.2+ (preview missing origin validation allows code injection)Dragoș IvanTo DoLate start / sequencing
ADS-9396 — Story — Permisiune Alocari burse pe facultatea atribuitaIonut CiolanTestingDependency delay
ADS-9402 — Task — [Mob] - Native new messagestefan musatIn ProgressLate start / sequencing
ADS-9405 — Improvement — [Billing] - Acțiuni manuale pe facturi eFacturaGeorge MurgociTo DoNot started
ADS-9408 — Task — [Marketing][GetResponse] - Curățare sync părinți: absolvenți cls. a XII-a, școală expirată, UAID dublatMarian AndreiTo DoNot started
ADS-9410 — Bug — [Prod][TUIASI] Eight deployments simultaneously lose all available replicasandrei.alexandruTo DoNot started
ADS-9415 — Task — [BE] Import SIIIR - specializareMarian AndreiIn ProgressPartial completion
ADS-9416 — Bug — [Prod][AWS][Web] Incident creation returns 500 on out-of-range incident numberCojan Paul-CatalinReady to mergePartial completion
ADS-9417 — Bug — [Prod][Auth][AWS+TUIASI] IAM lifetime limit rejects SSO and OAuth token issuanceDaniel OnisoruTo DoNot started

Miss pattern summary

PatternCountWhat it suggests
Partial completion13Breakdown / sizing / stage-gating was not tight enough
Dependency delay7Capacity protection or dependency timing created slip
Not started12A committed item remained outside execution focus
In Progress / Code Review carryovers20Most misses were moving, but not closing

Workflow-truth mismatches

Items marked Done in the sprint-review field while Jira workflow status was still non-final.

Jira itemStatusIntent
None

Executive follow-up questions

QuestionWhy this mattersWhat evidence to ask for
Why did committed items carry over despite planning readiness?This tests execution quality rather than just scope quality.Show carryovers split by progress continuation, dependency, and not-started.
Are Progress items being managed intentionally?Progress items are allowed to continue, but the continuation should be visible and controlled.Show the original slice and the specific landing expectation for each item.
Is added work a healthy responsiveness level or chronic interruption?High responsiveness can hide systemic instability and diluted predictability.Show which added items were urgent/reactive versus discretionary scope change.
Can we trust Done in review when workflow is still non-final?Workflow-truth gaps reduce trust and make completion easy to game.Show the exact mismatches and the completion rule to enforce next sprint.

Included teams in this org pulse: Mobile, Platform, Team 1, Team 2, University.

Usage note: start with the top-line metrics, then use the traceability links to answer these questions with issue-level evidence.

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list6565 issues in the planning snapshot
Sprint review / outcome snapshot raw list106106 issues in the Friday review snapshot
Normalized sprint fact base101101 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

These companion artifacts keep the pulse debuggable when a leader wants the exact rows behind a metric or a count.