Sprint Pulse

Engineering Pulse — Org Adservio ADS Q4 W45 - 09-13 Nov

Aggregated sprint ADS Q4 W45 - 09-13 Nov • deduplicated roll-up across included teams

This org roll-up aggregates deduplicated frozen issue facts across 5 team snapshots. Count metrics link to snapshot-exact JQL result pages. Jira IDs in the report link to live Jira issues.

Download DOCX

Executive summary

Yellow. The sprint closed 55/105 visible items. The org roll-up absorbed noise reasonably well — 29/34 added items were closed — but predictability on committed work was only 35.6% (26/73), and bugs made up 47.3% of completed items. The main drag was execution system quality, not readiness: 11/47 carryovers had been marked Ready at planning time.

Top-line metrics

MetricValueHow to read it
Committed completion35.6% (26/73)Planned items marked Done ÷ all planned committed items
Committed carryover64.4% (47/73)Planned committed carryovers ÷ all planned committed items
Finish predictability44.2% (23/52)Finish-intent planned items done ÷ all finish-intent planned items
Progress predictability85.0% (17/20)Progress items that behaved as intended by carrying
Added-during-sprint load32.4% (34/105)Added items ÷ all visible items
Added work closure29/34All added items marked Done
Reactive load (bug share)47.3% (26/55)Completed bugs ÷ all completed work
Planning quality35.6% (26/73)Committed items marked Ready ÷ all committed items
Workflow-truth mismatches0Items marked Done in review while workflow status remained non-final

Engineering readout

Across included teams, the sprint did not fail; it traded predictability for responsiveness. 29/34 added items were closed, but that responsiveness came with 47.3% bug share and diluted committed completion.

The miss pattern is concentrated: 24 partial-completion carryovers, 8 dependency-driven misses, and 11 committed items that never really started.

Most misses were not caused by poor readiness. 11 of the 47 carryovers had been marked Ready, so the stronger hypothesis is breakdown, sequencing, and capacity protection rather than simple scoping immaturity.

Delivered work mix

TypePlannedAddedStretchUnclearTotal doneDone %
Story4300712.7%
Task119002036.4%
Bug917002647.3%

Committed work: plan vs execution

SignalValueWhy it matters
Committed items73Explicit promise set
Committed done26Closed as promised
Committed carry over47Unfinished promise
Committed items marked Ready26Planning-quality input
Carryovers marked Ready11Ready did not guarantee finish
Carryovers not started11Execution focus gap
Carryovers started but unfinished23Work moved, but did not close

Carryover pattern

Jira itemOwnerStatusWhy it carried
ADS-1321 — Story — [BE][LCY][FE] - Adding to the student edit several mother tonguesCojan Paul-CatalinIn ProgressPartial completion
ADS-4410 — Story — Statistici - Progresul elevuluiPetronel PavelIn ProgressPartial completion
ADS-6725 — Improvement — Adeverinta de elevPetronel PavelTo DoDependency delay
ADS-7110 — Story — [Profesor][Teme] - Marcare status tema manualIvan IoanaIn ProgressPartial completion
ADS-7560 — Story — Examinari studentiIonut CiolanIn ProgressPartial completion
ADS-7698 — Task — Formatare valoare plata la 2 zecimale cand se face payment setup linkEdgar AlexaIn Progress
ADS-7966 — Story — [BE] Standarde de evaluareAndrei DraganIn ProgressPartial completion
ADS-8543 — Story — Flux alocare automata burse de performantaIonut CiolanReady to mergeDependency delay
ADS-8679 — Story — Refactor student, situatie scolarastefan.achimReady to mergeDependency delay
ADS-8840 — Bug — [Asachi] - Probleme titular curs sectiunea de "Restantieri"andrei.alexandruIn ProgressPartial completion
ADS-8906 — Improvement — [BE][Billing][Subs] - Migrate date columns from date -> dateTimeEdgar AlexaIn ProgressPartial completion
ADS-8960 — Story — [Edumarket] - Refactor pagina adaugare Oferta/ofertantPaul BostanTo DoPartial completion
ADS-9068 — Improvement — Move fs events to object + previous_values; stop signalling moves via a `moved` field on createdAndrei DraganTo DoNot started
ADS-9102 — Task — [BE] Change response status codeDaniel OnisoruCode ReviewPartial completion
ADS-9166 — Bug — [TUIASI] Shared database write stall blocked SSO logins and report creation on Oct 12Ionut CiolanTo DoNot started
ADS-9187 — Story — Adauga forme de finantarestefan.achimReady to mergePartial completion
ADS-9210 — Task — Migrare Timezone GMT+3 -> UTCAlex MurarescuIn ProgressPartial completion
ADS-9233 — Story — Imbunatatire proces echivalareandrei.alexandruIn ProgressPartial completion
ADS-9239 — Task — raport orarDaniel OnisoruTo DoNot started
ADS-9259 — Task — Download RM cu Observatii si Semnataristefan.achimReady to mergeDependency delay
ADS-9265 — Task — Product Analytics v2 (team1)Marian AndreiIn ProgressPartial completion
ADS-9266 — Task — Eliminare bifa evolutie + pagina EvolutiePetronel PavelIn ProgressPartial completion
ADS-9355 — Story — [AI] Agent Vio de code review pe MR-uri GitLab (orice proiect)Marian AndreiTo DoNot started
ADS-9384 — Story — Adauga view IBAN pt studenti in modulul de burseIuliana GugeanuReady to mergeDependency delay
ADS-9392 — Bug — [Prod][Notifications] notifications-event-manager crashes overnight on "MySQL server has gone away": tenant DB connection is reused past wait_timeoutMarian AndreiIn ProgressPartial completion
ADS-9393 — Bug — [Security][Frontend] Upgrade Storybook 10.1.11 to 10.6.2+ (preview missing origin validation allows code injection)Dragoș IvanTo Do
ADS-9396 — Story — Permisiune Alocari burse pe facultatea atribuitaIonut CiolanReady to mergeDependency delay
ADS-9405 — Improvement — [Billing] - Acțiuni manuale pe facturi eFacturaGeorge MurgociTo Do
ADS-9408 — Task — [Marketing][GetResponse] - Curățare sync părinți: absolvenți cls. a XII-a, școală expirată, UAID dublatMarian AndreiTo DoNot started
ADS-9410 — Bug — [Prod][TUIASI] Eight deployments simultaneously lose all available replicasandrei.alexandruTo DoNot started
ADS-9413 — Story — [Edumarket] - Refactor pagina Edumarket - Display ofertePaul BostanTo DoPartial completion
ADS-9415 — Task — [BE] Import SIIIR - Nomenclator nou & specializareMarian AndreiIn ProgressPartial completion
ADS-9419 — Story — Functie personalCosmin OlaruReady for testingPartial completion
ADS-9427 — Task — verificare plata recurenta id 6317Edgar AlexaTo DoNot started
ADS-9438 — Bug — [Prod][AWS][University] Academic-plan discipline deletion is blocked by owned attribute rowsandrei.alexandruIn ProgressPartial completion
ADS-9442 — Task — verificat de ce la o obligatiune de plata, nu se ia din soldEdgar AlexaTo DoNot started
ADS-9446 — Story — [FE] parintele Amet Ebru ID 1465705 nu vede evolutia copilului pe anii precedenti, cu toate ca a avut platitVlad LihaceanuTo DoNot started
ADS-9460 — Story — [FE] Standarde de evaluarePetronel PavelIn ProgressDependency delay
ADS-9493 — Task — [Billing] Log formatting & alerteEdgar AlexaCode ReviewDependency delay
ADS-9513 — Task — [#AI_FIRST] - MCP DBDiagramDragoș IvanIn ProgressPartial completion
ADS-9514 — Task — [PLATFORM] - Ștergere Redis vechi după confirmare migrare pe SentinelCojan Paul-CatalinTestingPartial completion
ADS-9515 — Task — [Alerte] - Endpoint /stats pentru billingGeorge MurgociTo Do
ADS-9517 — Task — [MOB] Adapt mobile app to UTCstefan musatIn ProgressPartial completion
ADS-9519 — Task — [MOB] Banner profesori pentru meditatiiStefan AgrigoroaeiTestingPartial completion
ADS-9531 — Task — Activities design updateStefan AgrigoroaeiTo DoNot started
ADS-9592 — Bug — Local Translation ResilienceGeorge MurgociIn ProgressPartial completion
ADS-9595 — Task — Add grades calendar issue - refactorStefan AgrigoroaeiTo DoNot started

Miss pattern summary

PatternCountWhat it suggests
Partial completion24Breakdown / sizing / stage-gating was not tight enough
Dependency delay8Capacity protection or dependency timing created slip
Not started11A committed item remained outside execution focus
In Progress / Code Review carryovers23Most misses were moving, but not closing

Workflow-truth mismatches

Items marked Done in the sprint-review field while Jira workflow status was still non-final.

Jira itemStatusIntent
None

Executive follow-up questions

QuestionWhy this mattersWhat evidence to ask for
Why did committed items carry over despite planning readiness?This tests execution quality rather than just scope quality.Show carryovers split by progress continuation, dependency, and not-started.
Are Progress items being managed intentionally?Progress items are allowed to continue, but the continuation should be visible and controlled.Show the original slice and the specific landing expectation for each item.
Is added work a healthy responsiveness level or chronic interruption?High responsiveness can hide systemic instability and diluted predictability.Show which added items were urgent/reactive versus discretionary scope change.
Can we trust Done in review when workflow is still non-final?Workflow-truth gaps reduce trust and make completion easy to game.Show the exact mismatches and the completion rule to enforce next sprint.

Included teams in this org pulse: Mobile, Platform, Team 1, Team 2, University.

Usage note: start with the top-line metrics, then use the traceability links to answer these questions with issue-level evidence.

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list7575 issues in the planning snapshot
Sprint review / outcome snapshot raw list112112 issues in the Friday review snapshot
Normalized sprint fact base105105 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

These companion artifacts keep the pulse debuggable when a leader wants the exact rows behind a metric or a count.