Sprint Pulse

Engineering Pulse — Team 1 ADS Q2 W20 - 18-22 May

Planned sprint ADS Q2 W20 - 18-22 May • planning snapshot + end-of-sprint outcome snapshot

This version uses the planning snapshot as the promise set and the outcome snapshot as the result set. Count metrics link to snapshot-exact JQL result pages. Jira IDs in the report link to live Jira issues.

Download DOCX

Executive summary

Yellow. The sprint closed 21/53 visible items. The team absorbed noise well — 7/19 added items were closed — but finish predictability was only 43.8% (14/32), and bugs made up 66.7% of completed items. Planning-baseline carryover includes 18 finish misses and 2 expected progress continuations.

Top-line metrics

MetricValueHow to read it
Committed completion41.2% (14/34)Planned items marked Done ÷ all planned committed items
Planning-baseline carryover58.8% (20/34)All planned items not Done, including expected Progress continuations
Finish-intent carryover56.2% (18/32)Finish-intent planned items not Done ÷ all finish-intent planned items
Finish predictability43.8% (14/32)Finish-intent planned items done ÷ all finish-intent planned items
Progress predictability100.0% (2/2)Progress items that behaved as intended by carrying
Added-during-sprint load35.8% (19/53)Outcome-only items ÷ all visible items
Added work closure7/19All added items marked Done
Reactive load (bug share)66.7% (14/21)Completed bugs ÷ all completed work
Planning quality44.1% (15/34)Committed items marked Ready ÷ all committed items
Workflow-truth mismatches1Items marked Done in review while workflow status remained non-final

Engineering readout

The sprint did not fail; it traded predictability for responsiveness. 7/19 added items were closed, but that responsiveness came with 66.7% bug share and diluted finish predictability.

The miss pattern is concentrated: 4 partial-completion carryovers, 1 dependency-driven misses, and 12 planning-baseline items that never really started.

Most misses were not caused by poor readiness. 6 of the 20 planning-baseline carryovers had been marked Ready, so the stronger hypothesis is breakdown, sequencing, and capacity protection rather than simple scoping immaturity.

Delivered work mix

TypePlannedAddedStretchUnclearTotal doneDone %
Story100014.8%
Task4100523.8%
Bug86001466.7%

Planning baseline: plan vs execution

SignalValueWhy it matters
Planning-baseline items34Items present in the frozen planning snapshot
Planning-baseline done14Closed by sprint review
Planning-baseline carryover20All planned items still open, including Progress continuation
Finish-intent carryover18Planned-to-finish items that did not finish
Progress continuation2Progress-intent planned items still open as expected
Planning-baseline items marked Ready15Planning-quality input
Carryovers marked Ready6Ready did not guarantee closure
Carryovers not started12Execution focus gap
Carryovers started but unfinished8Work moved, but did not close

Carryover pattern

Jira itemOwnerIntentStatusWhy it carried
ADS-2564 — Story — [School managment/Teachers] - Modules to be tested until the end of the school yearCosmin OlaruProgressTo DoDependency delay
ADS-6360 — Story — [Catalog PDF] - Număr indicatori incorect – SemestreAndrei DraganFinishIn ProgressPartial completion
ADS-6495 — Story — Service Internal APIIonut CiolanFinishReady for testing
ADS-6499 — Story — Implementat CRUD Etnii in LaravelIonut CiolanFinishIn ProgressNot started
ADS-6501 — Story — Input validation errorsIonut CiolanFinishReady for testing
ADS-6545 — Story — Implementare v1 layer comunicare native-web *post message bridgeIvan IoanaFinishIn ProgressNot started
ADS-6562 — Story — Remove any mentions of Laravel in production modeIonut CiolanFinishReady for testing
ADS-6712 — Task — [Note/absențe] - Recuperare informațiiMarian AndreiFinishTo DoNot started
ADS-6899 — Bug — [Medii] Calcul gresit medie semestreAndrei DraganFinishIn ProgressPartial completion
ADS-6974 — Bug — [Catalog Pdf] - Management clasa - Documente - Catalogul claseiCosmin OlaruFinishTestingPartial completion
ADS-7262 — Task — [Coordonator][Catalog][Absente][Note] - UpdatesCosmin OlaruFinishTestingPartial completion
ADS-7388 — Bug — docgen2-api: gradebook view/download endpoints return HTTP 500 - 15 hits/FridayPetronel PavelFinishTo DoNot started
ADS-7389 — Bug — AdservioAPI.php: svcAuth self-call failures turn web API endpoints into HTTP 500 - 20 hits/FridayIonut CiolanFinishTo DoNot started
ADS-7448 — Bug — [BE] Grades.php: deleting a grade can deadlock on cat_note and return HTTP 500 - 8 hits/24hIonut CiolanFinishTo DoNot started
ADS-7460 — Bug — Absences time interval export_xls returns HTTP 500 for inverted date range (6 errors/24h)Marian AndreiFinishIn ProgressNot started
ADS-7533 — Bug — medii_generale.php: secretary final averages page reads missing $cicluSelectatID when cycle filter is empty - 3 warnings/24hAndrei DraganFinishTo DoNot started
ADS-7565 — Bug — [FE] - Elev cu media incheiata poate primi in continuare noteAndrei DraganFinishTo DoNot started
ADS-7567 — Bug — [MOB] - Nu se pot adauga note sau absente din contul de secretar/director in aplicatia mobilaCosmin OlaruFinishIn ProgressNot started
ADS-7575 — Bug — M_export.php / Export.php: student export references missing second-semester average column and returns HTTP 500 on /ro/secretary/export/elevi - 16 hits/24hMarian AndreiFinishTo DoNot started
ADS-7591 — Bug — Elevi_transfer.php: missing source repartition row breaks subject transfer - 48 warnings/24hProgressTo DoNot started

Miss pattern summary

PatternCountWhat it suggests
Partial completion4Breakdown / sizing / stage-gating was not tight enough
Dependency delay1Capacity protection or dependency timing created slip
Not started12A committed item remained outside execution focus
In Progress / Code Review carryovers8Most misses were moving, but not closing

Workflow-truth mismatches

Items marked Done in the sprint-review field while Jira workflow status was still non-final.

Jira itemStatusIntent
ADS-4235 — [FE][Library] - Se face un request pentru wellbeing cand nu este cazulReady for testing

Executive follow-up questions

QuestionWhy this mattersWhat evidence to ask for
Why did finish-intent items carry over despite planning readiness?This tests execution quality rather than just scope quality.Show finish-intent carryovers split by dependency, partial completion, and not-started.
Are Progress items being managed intentionally?Progress items are allowed to continue, but the continuation should be visible and controlled.Show the original slice and the specific landing expectation for each item.
Is added work a healthy responsiveness level or chronic interruption?High responsiveness can hide systemic instability and diluted predictability.Show which added items were urgent/reactive versus discretionary scope change.
Can we trust Done in review when workflow is still non-final?Workflow-truth gaps reduce trust and make completion easy to game.Show the exact mismatches and the completion rule to enforce next sprint.

Usage note: start with the top-line metrics, then use the traceability links to answer these questions with issue-level evidence.

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list36Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list61Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base53Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline34Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot53Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review34planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning19planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review0planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows8Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Committed completion41.2% (14/34)planned committed items marked Done ÷ all planned committed items14/34Open denominator JQL
Planning-baseline carryover58.8% (20/34)planned baseline items not Done at review ÷ all planned baseline items20/34Open denominator JQL
Finish-intent carryover56.2% (18/32)finish-intent planned items not Done at review ÷ all finish-intent planned items18/32Open denominator JQL
Finish predictability43.8% (14/32)finish-intent committed items marked Done ÷ all finish-intent committed items14/32Open denominator JQL
Progress predictability100.0% (2/2)progress-intent items that carried as intended ÷ all progress-intent committed items2/2Open denominator JQL
Added-during-sprint load35.8% (19/53)visible items absent from planning and present in review ÷ all visible sprint items19/53Open denominator JQL
Added work closure7/19added visible items marked Done ÷ all added visible items7/19Open denominator JQL
Planning quality44.1% (15/34)committed items marked Ready in planning snapshot ÷ all committed items15/34Open denominator JQL
Carryovers marked Ready30.0% (6/20)carryovers that were marked Ready in planning snapshot ÷ all carryovers6/20Open denominator JQL
Reactive load66.7% (14/21)completed bugs ÷ all completed work14/21Open denominator JQL
Workflow-truth mismatches1Done rows with non-final workflow status1/21Open denominator JQL

Planning-baseline carryover includes both finish-intent misses and expected Progress continuations. Use Finish-intent carryover when you want only planned-to-finish items that did not finish.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

These companion artifacts keep the pulse debuggable when a leader wants the exact rows behind a metric or a count.