Sprint Pulse

Engineering Pulse — Team 1 ADS Q3 W27 - 06-10 Jul

Planned sprint ADS Q3 W27 - 06-10 Jul • planning snapshot + end-of-sprint outcome snapshot

This version uses the planning snapshot as the promise set and the outcome snapshot as the result set. Count metrics link to snapshot-exact JQL result pages. Jira IDs in the report link to live Jira issues.

Download DOCX

Executive summary

Yellow. The sprint closed 24/57 visible items. The team absorbed noise well — 17/29 added items were closed — but finish predictability was only 21.7% (5/23), and bugs made up 83.3% of completed items. Planning-baseline carryover includes 18 finish misses and 3 expected progress continuations.

Top-line metrics

MetricValueHow to read it
Committed completion25.0% (7/28)Planned items marked Done ÷ all planned committed items
Planning-baseline carryover75.0% (21/28)All planned items not Done, including expected Progress continuations
Finish-intent carryover78.3% (18/23)Finish-intent planned items not Done ÷ all finish-intent planned items
Finish predictability21.7% (5/23)Finish-intent planned items done ÷ all finish-intent planned items
Progress predictability60.0% (3/5)Progress items that behaved as intended by carrying
Added-during-sprint load50.9% (29/57)Outcome-only items ÷ all visible items
Added work closure17/29All added items marked Done
Reactive load (bug share)83.3% (20/24)Completed bugs ÷ all completed work
Planning quality21.4% (6/28)Committed items marked Ready ÷ all committed items
Workflow-truth mismatches0Items marked Done in review while workflow status remained non-final

Engineering readout

The sprint did not fail; it traded predictability for responsiveness. 17/29 added items were closed, but that responsiveness came with 83.3% bug share and diluted finish predictability.

The miss pattern is concentrated: 2 partial-completion carryovers, 1 dependency-driven misses, and 12 planning-baseline items that never really started.

Most misses were not caused by poor readiness. 5 of the 21 planning-baseline carryovers had been marked Ready, so the stronger hypothesis is breakdown, sequencing, and capacity protection rather than simple scoping immaturity.

Delivered work mix

TypePlannedAddedStretchUnclearTotal doneDone %
Story200028.3%
Task020028.3%
Bug515002083.3%

Planning baseline: plan vs execution

SignalValueWhy it matters
Planning-baseline items28Items present in the frozen planning snapshot
Planning-baseline done7Closed by sprint review
Planning-baseline carryover21All planned items still open, including Progress continuation
Finish-intent carryover18Planned-to-finish items that did not finish
Progress continuation3Progress-intent planned items still open as expected
Planning-baseline items marked Ready6Planning-quality input
Carryovers marked Ready5Ready did not guarantee closure
Carryovers not started12Execution focus gap
Carryovers started but unfinished2Work moved, but did not close

Carryover pattern

Jira itemOwnerIntentStatusWhy it carried
ADS-2001 — Bug — [BE][Setari ] - Desi profesoara a fost stearsa de la cadre didactice ea apare in continuare la roluri si permisiuni si nu se poate sterge de acolo- la stergere apare eroar 400Ivan IoanaFinishTo Do
ADS-4439 — Bug — [Teste si chestionare] - Numarul de destinatari care se afiseaza nu corespunde cu numarul real de destinatariMarian AndreiFinishTo DoNot started
ADS-5931 — Story — Seedere de date - cod in proiectAndrei DraganTo DoNot started
ADS-6545 — Story — [SDK] Implementare v1 layer comunicare native-web *post message bridgeIvan IoanaFinishReady to mergeNot started
ADS-6698 — Bug — [FE/BE] Restrictie vizualizare fise scolareMarian AndreiFinishTo DoNot started
ADS-7305 — Task — [REQ] - Remote Session Termination for UsersAndrei DraganProgressTo DoNot started
ADS-7389 — Bug — AdservioAPI.php: svcAuth self-call failures turn web API endpoints into HTTP 500 - 20 hits/FridayIonut CiolanFinishTo DoNot started
ADS-7390 — Bug — rooms-api: room search endpoint returns HTTP 500 - 3 hits/FridayIonut CiolanFinishTo DoNot started
ADS-7484 — Bug — Session.php: session_start() fails reading session data during teacher class-book requests - 26 errors/24hMarian AndreiFinishTo DoNot started
ADS-7653 — Bug — Clase_profesori.php / M_cmc.php: teacher-class assignment insert fails FK constraint in cat_cadre2materii2clase - 2 errors/24hMarian AndreiFinishTo DoNot started
ADS-7721 — Bug — Repartizari.php / M_elevi.php: grade-system visibility toggle inserts partial student config row and fails when no override exists - 3 errors/24hMarian AndreiFinishTo Do
ADS-7852 — Task — [BE]: Dezactivare actiuni noteaza (si bulk) daca media anuala si/sau media semestriala este incheiataAndrei DraganFinishCode ReviewPartial completion
ADS-7907 — Task — [BE] Refactoring SQL_CALC_FOUND_ROWSMarian AndreiFinishReady for testingPartial completion
ADS-7908 — Bug — [Prod][AWS][legacy-web] Auth recaptcha helper dereferences null verification responseDaniel OnisoruFinishTo DoNot started
ADS-8004 — Improvement — [FE] - Elevii transferati apar in statistici ca "medii neconfirmate"Marian AndreiFinishTo Do
ADS-8061 — Bug — [Prod][AWS][legacy-web] School-transfer edit recalculates status for NULL student ID - 64 errors/72hAndrei DraganFinishTo DoNot started
ADS-8062 — Bug — [Prod][AWS][legacy-web] Certificate template fetch returns 500 when forms schema lookup gets 403 - 26 errors/72hPetronel PavelFinishTo DoDependency delay
ADS-8067 — Improvement — [Incadrare] Refactoring React & APIAndrei DraganProgressTo DoLate start / sequencing
ADS-8105 — Story — Impartirea pe moduleIvan IoanaProgressIn Progress
ADS-8108 — Bug — [Prod][AWS][legacy-web] Teacher exam-prep save writes unsupported peeTipPregatire value - 2 errors/72hMarian AndreiFinishTo DoNot started
ADS-8151 — Bug — [Prod][AWS][legacy-web] POST /ro/secretary/export/elevi returns HTTP 500 from M_export num_rows on bool - 4 errors/72hMarian AndreiFinishTo Do

Miss pattern summary

PatternCountWhat it suggests
Partial completion2Breakdown / sizing / stage-gating was not tight enough
Dependency delay1Capacity protection or dependency timing created slip
Not started12A committed item remained outside execution focus
In Progress / Code Review carryovers2Most misses were moving, but not closing

Workflow-truth mismatches

Items marked Done in the sprint-review field while Jira workflow status was still non-final.

Jira itemStatusIntent
None

Executive follow-up questions

QuestionWhy this mattersWhat evidence to ask for
Why did finish-intent items carry over despite planning readiness?This tests execution quality rather than just scope quality.Show finish-intent carryovers split by dependency, partial completion, and not-started.
Are Progress items being managed intentionally?Progress items are allowed to continue, but the continuation should be visible and controlled.Show the original slice and the specific landing expectation for each item.
Is added work a healthy responsiveness level or chronic interruption?High responsiveness can hide systemic instability and diluted predictability.Show which added items were urgent/reactive versus discretionary scope change.
Can we trust Done in review when workflow is still non-final?Workflow-truth gaps reduce trust and make completion easy to game.Show the exact mismatches and the completion rule to enforce next sprint.

Usage note: start with the top-line metrics, then use the traceability links to answer these questions with issue-level evidence.

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list30Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list79Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base57Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline28Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot57Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review28planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning29planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review0planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows22Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Committed completion25.0% (7/28)planned committed items marked Done ÷ all planned committed items7/28Open denominator JQL
Planning-baseline carryover75.0% (21/28)planned baseline items not Done at review ÷ all planned baseline items21/28Open denominator JQL
Finish-intent carryover78.3% (18/23)finish-intent planned items not Done at review ÷ all finish-intent planned items18/23Open denominator JQL
Finish predictability21.7% (5/23)finish-intent committed items marked Done ÷ all finish-intent committed items5/23Open denominator JQL
Progress predictability60.0% (3/5)progress-intent items that carried as intended ÷ all progress-intent committed items3/5Open denominator JQL
Added-during-sprint load50.9% (29/57)visible items absent from planning and present in review ÷ all visible sprint items29/57Open denominator JQL
Added work closure17/29added visible items marked Done ÷ all added visible items17/29Open denominator JQL
Planning quality21.4% (6/28)committed items marked Ready in planning snapshot ÷ all committed items6/28Open denominator JQL
Carryovers marked Ready23.8% (5/21)carryovers that were marked Ready in planning snapshot ÷ all carryovers5/21Open denominator JQL
Reactive load83.3% (20/24)completed bugs ÷ all completed work20/24Open denominator JQL
Workflow-truth mismatches0Done rows with non-final workflow status0/24Open denominator JQL

Planning-baseline carryover includes both finish-intent misses and expected Progress continuations. Use Finish-intent carryover when you want only planned-to-finish items that did not finish.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

These companion artifacts keep the pulse debuggable when a leader wants the exact rows behind a metric or a count.