Planned sprint ADS Q4 W40 - 05-09 Oct • planning snapshot + end-of-sprint outcome snapshot
This version uses the planning snapshot as the promise set and the outcome snapshot as the result set. Count metrics link to snapshot-exact JQL result pages. Jira IDs in the report link to live Jira issues.
Download DOCXYellow. The sprint closed 17/30 visible items. The team absorbed noise well — 4/8 added items were closed — but predictability on committed work was only 59.1% (13/22), and bugs made up 58.8% of completed items. The main drag was execution system quality, not readiness: 4/9 carryovers had been marked Ready at planning time.
| Metric | Value | How to read it |
|---|---|---|
| Committed completion | 59.1% (13/22) | Planned items marked Done ÷ all planned committed items |
| Committed carryover | 40.9% (9/22) | Planned committed carryovers ÷ all planned committed items |
| Finish predictability | 60.0% (12/20) | Finish-intent planned items done ÷ all finish-intent planned items |
| Progress predictability | 50.0% (1/2) | Progress items that behaved as intended by carrying |
| Added-during-sprint load | 26.7% (8/30) | Added items ÷ all visible items |
| Added work closure | 4/8 | All added items marked Done |
| Reactive load (bug share) | 58.8% (10/17) | Completed bugs ÷ all completed work |
| Planning quality | 27.3% (6/22) | Committed items marked Ready ÷ all committed items |
| Workflow-truth mismatches | 4 | Items marked Done in review while workflow status remained non-final |
The sprint did not fail; it traded predictability for responsiveness. 4/8 added items were closed, but that responsiveness came with 58.8% bug share and diluted committed completion.
The miss pattern is concentrated: 4 partial-completion carryovers, 1 dependency-driven misses, and 3 committed items that never really started.
Most misses were not caused by poor readiness. 4 of the 9 carryovers had been marked Ready, so the stronger hypothesis is breakdown, sequencing, and capacity protection rather than simple scoping immaturity.
| Type | Planned | Added | Stretch | Unclear | Total done | Done % |
|---|---|---|---|---|---|---|
| Story | 1 | 0 | 0 | 0 | 1 | 5.9% |
| Task | 3 | 2 | 0 | 0 | 5 | 29.4% |
| Bug | 8 | 2 | 0 | 0 | 10 | 58.8% |
| Signal | Value | Why it matters |
|---|---|---|
| Committed items | 22 | Explicit promise set |
| Committed done | 13 | Closed as promised |
| Committed carry over | 9 | Unfinished promise |
| Committed items marked Ready | 6 | Planning-quality input |
| Carryovers marked Ready | 4 | Ready did not guarantee finish |
| Carryovers not started | 3 | Execution focus gap |
| Carryovers started but unfinished | 5 | Work moved, but did not close |
| Pattern | Count | What it suggests |
|---|---|---|
| Partial completion | 4 | Breakdown / sizing / stage-gating was not tight enough |
| Dependency delay | 1 | Capacity protection or dependency timing created slip |
| Not started | 3 | A committed item remained outside execution focus |
| In Progress / Code Review carryovers | 5 | Most misses were moving, but not closing |
Items marked Done in the sprint-review field while Jira workflow status was still non-final.
| Jira item | Status | Intent |
|---|---|---|
| ADS-8985 — [Prod][AWS][Web] Registration confirmation returns 500 on duplicate username | Ready to merge | Finish |
| ADS-9047 — Adaugare coordonator clasa in lista de destinatari propusi | In Progress | Finish |
| ADS-9064 — [SIIIR] - Elevi duplicati Wurmbrand | In Progress | Finish |
| ADS-9117 — sincronizare SIIR id 7197 | In Progress |
| Question | Why this matters | What evidence to ask for |
|---|---|---|
| Why did committed items carry over despite planning readiness? | This tests execution quality rather than just scope quality. | Show carryovers split by progress continuation, dependency, and not-started. |
| Are Progress items being managed intentionally? | Progress items are allowed to continue, but the continuation should be visible and controlled. | Show the original slice and the specific landing expectation for each item. |
| Is added work a healthy responsiveness level or chronic interruption? | High responsiveness can hide systemic instability and diluted predictability. | Show which added items were urgent/reactive versus discretionary scope change. |
| Can we trust Done in review when workflow is still non-final? | Workflow-truth gaps reduce trust and make completion easy to game. | Show the exact mismatches and the completion rule to enforce next sprint. |
Usage note: start with the top-line metrics, then use the traceability links to answer these questions with issue-level evidence.
| Snapshot | Issue count | Link |
|---|---|---|
| Planning snapshot raw list | 29 | 29 issues in the planning snapshot |
| Sprint review / outcome snapshot raw list | 37 | 37 issues in the Friday review snapshot |
| Normalized sprint fact base | 30 | 30 issues used for metrics and drill-down |
Planning and outcome are separate frozen moments.
Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.
| Artifact | Link |
|---|---|
| Issue audit register | Open issue-level audit CSV |
| Metric lineage | Open metric lineage CSV |
| JQL traceability register | Open JQL traceability CSV |
| Sprint metrics JSON | Open sprint metrics JSON |
These companion artifacts keep the pulse debuggable when a leader wants the exact rows behind a metric or a count.