Sprint Pulse

Engineering Pulse — Team 2 ADS Q4 W41 - 12-16 Oct

Planned sprint ADS Q4 W41 - 12-16 Oct • planning snapshot + end-of-sprint outcome snapshot

This version uses the planning snapshot as the promise set and the outcome snapshot as the result set. Count metrics link to snapshot-exact JQL result pages. Jira IDs in the report link to live Jira issues.

Download DOCX

Executive summary

Yellow. The sprint closed 9/18 visible items. The team absorbed noise well — 5/6 added items were closed — but predictability on committed work was only 33.3% (4/12), and bugs made up 33.3% of completed items. The main drag was execution system quality, not readiness: 2/8 carryovers had been marked Ready at planning time.

Top-line metrics

MetricValueHow to read it
Committed completion33.3% (4/12)Planned items marked Done ÷ all planned committed items
Committed carryover66.7% (8/12)Planned committed carryovers ÷ all planned committed items
Finish predictability44.4% (4/9)Finish-intent planned items done ÷ all finish-intent planned items
Progress predictability100.0% (2/2)Progress items that behaved as intended by carrying
Added-during-sprint load33.3% (6/18)Added items ÷ all visible items
Added work closure5/6All added items marked Done
Reactive load (bug share)33.3% (3/9)Completed bugs ÷ all completed work
Planning quality25.0% (3/12)Committed items marked Ready ÷ all committed items
Workflow-truth mismatches3Items marked Done in review while workflow status remained non-final

Engineering readout

The sprint did not fail; it traded predictability for responsiveness. 5/6 added items were closed, but that responsiveness came with 33.3% bug share and diluted committed completion.

The miss pattern is concentrated: 4 partial-completion carryovers, 0 dependency-driven misses, and 2 committed items that never really started.

Most misses were not caused by poor readiness. 2 of the 8 carryovers had been marked Ready, so the stronger hypothesis is breakdown, sequencing, and capacity protection rather than simple scoping immaturity.

Delivered work mix

TypePlannedAddedStretchUnclearTotal doneDone %
Story0100111.1%
Task1200333.3%
Bug2100333.3%

Committed work: plan vs execution

SignalValueWhy it matters
Committed items12Explicit promise set
Committed done4Closed as promised
Committed carry over8Unfinished promise
Committed items marked Ready3Planning-quality input
Carryovers marked Ready2Ready did not guarantee finish
Carryovers not started2Execution focus gap
Carryovers started but unfinished1Work moved, but did not close

Carryover pattern

Jira itemOwnerStatusWhy it carried
ADS-7354 — Story — [Abonamente] - Gestionare recurență pachete anualeEdgar AlexaReady for testingPartial completion
ADS-7474 — Task — [FE] - Optimizare viteză de încărcare paginiAlex MurarescuTo DoNot started
ADS-7849 — Story — Stergere date S3Cojan Paul-CatalinTo DoPriority Change
ADS-8733 — Bug — [Prod][Billing] - Refactor charges cronEdgar AlexaTo DoPartial completion
ADS-8757 — Story — [Billing] - Migrat tot codul pe NestGeorge MurgociIn ProgressPartial completion
ADS-9019 — Task — stergere "servicii asignate" ID 1680Edgar AlexaTo DoPartial completion
ADS-9106 — Task — [Notifications] - Refactor notificări proiecte NodeDragoș IvanTo DoNot started
ADS-9149 — Task — Feature flags - Evolutie elevDragoș IvanMissing from outcome snapshot

Miss pattern summary

PatternCountWhat it suggests
Partial completion4Breakdown / sizing / stage-gating was not tight enough
Dependency delay0Capacity protection or dependency timing created slip
Not started2A committed item remained outside execution focus
In Progress / Code Review carryovers1Most misses were moving, but not closing

Workflow-truth mismatches

Items marked Done in the sprint-review field while Jira workflow status was still non-final.

Jira itemStatusIntent
ADS-8798 — [MOB][FE] - Local front-end proxy for mobile appTo DoFinish
ADS-9045 — Schimbări flow comparator și pagină de succes în urma achiziției unui pachetIn Progress
ADS-9194 — [Notificări] - Enhance notificări Web/Push cu icon și urlTesting

Executive follow-up questions

QuestionWhy this mattersWhat evidence to ask for
Why did committed items carry over despite planning readiness?This tests execution quality rather than just scope quality.Show carryovers split by progress continuation, dependency, and not-started.
Are Progress items being managed intentionally?Progress items are allowed to continue, but the continuation should be visible and controlled.Show the original slice and the specific landing expectation for each item.
Is added work a healthy responsiveness level or chronic interruption?High responsiveness can hide systemic instability and diluted predictability.Show which added items were urgent/reactive versus discretionary scope change.
Can we trust Done in review when workflow is still non-final?Workflow-truth gaps reduce trust and make completion easy to game.Show the exact mismatches and the completion rule to enforce next sprint.

Usage note: start with the top-line metrics, then use the traceability links to answer these questions with issue-level evidence.

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1313 issues in the planning snapshot
Sprint review / outcome snapshot raw list1919 issues in the Friday review snapshot
Normalized sprint fact base1818 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

These companion artifacts keep the pulse debuggable when a leader wants the exact rows behind a metric or a count.