Sprint Pulse

Engineering Pulse — University ADS Q4 W42 - 19-23 Oct

Planned sprint ADS Q4 W42 - 19-23 Oct • planning snapshot + end-of-sprint outcome snapshot

This version uses the planning snapshot as the promise set and the outcome snapshot as the result set. Count metrics link to snapshot-exact JQL result pages. Jira IDs in the report link to live Jira issues.

Download DOCX

Executive summary

Yellow. The sprint closed 10/28 visible items. The team absorbed noise well — 5/7 added items were closed — but predictability on committed work was only 23.8% (5/21), and bugs made up 60.0% of completed items. The main drag was execution system quality, not readiness: 7/16 carryovers had been marked Ready at planning time.

Top-line metrics

MetricValueHow to read it
Committed completion23.8% (5/21)Planned items marked Done ÷ all planned committed items
Committed carryover76.2% (16/21)Planned committed carryovers ÷ all planned committed items
Finish predictability27.8% (5/18)Finish-intent planned items done ÷ all finish-intent planned items
Progress predictability100.0% (3/3)Progress items that behaved as intended by carrying
Added-during-sprint load25.0% (7/28)Added items ÷ all visible items
Added work closure5/7All added items marked Done
Reactive load (bug share)60.0% (6/10)Completed bugs ÷ all completed work
Planning quality42.9% (9/21)Committed items marked Ready ÷ all committed items
Workflow-truth mismatches5Items marked Done in review while workflow status remained non-final

Engineering readout

The sprint did not fail; it traded predictability for responsiveness. 5/7 added items were closed, but that responsiveness came with 60.0% bug share and diluted committed completion.

The miss pattern is concentrated: 5 partial-completion carryovers, 3 dependency-driven misses, and 8 committed items that never really started.

Most misses were not caused by poor readiness. 7 of the 16 carryovers had been marked Ready, so the stronger hypothesis is breakdown, sequencing, and capacity protection rather than simple scoping immaturity.

Delivered work mix

TypePlannedAddedStretchUnclearTotal doneDone %
Story1000110.0%
Task1100220.0%
Bug2400660.0%

Committed work: plan vs execution

SignalValueWhy it matters
Committed items21Explicit promise set
Committed done5Closed as promised
Committed carry over16Unfinished promise
Committed items marked Ready9Planning-quality input
Carryovers marked Ready7Ready did not guarantee finish
Carryovers not started8Execution focus gap
Carryovers started but unfinished7Work moved, but did not close

Carryover pattern

Jira itemOwnerStatusWhy it carried
ADS-8164 — Story — [Burse] - US6 - RapoarteDana-Mihaela MarițcaTestingPartial completion
ADS-8535 — Bug — [Prod][AWS][University] Add discipline sends string for localized disciplineName - 12 HTTP 400s/72handrei.alexandruTo DoNot started
ADS-8543 — Story — Flux alocare automata burse de performantaIonut CiolanIn ProgressDependency delay
ADS-8584 — Improvement — [Asachi]-Adaugare ,,Status student" in Clasamentul studentilor din modulul Statistici si rapoarteandrei.alexandruTo DoNot started
ADS-8679 — Story — Refactor student, situatie scolarastefan.achimTestingPartial completion
ADS-8753 — Improvement — Calcul credite in functie de nr total credite la disciplinele impuseandrei.alexandruTo DoNot started
ADS-8763 — Task — [Asachi][BE] Import studenti pentru anul universitar 2026-2027andrei.alexandruIn ProgressDependency delay
ADS-8866 — Bug — [Asachi] - Problema echivalariandrei.alexandruTo DoNot started
ADS-8938 — Bug — [Asachi] - Problema echivalariandrei.alexandruTo DoNot started
ADS-8944 — Story — Inchidere a tuturor cataloagelorMagda GradinaruIn ProgressPartial completion
ADS-8972 — Bug — [Asachi] - Problema incheiere media anuala masterTo DoPartial completion
ADS-8981 — Task — Sterge permisiunile vechi - scholarship allocationandrei.alexandruIn ProgressPartial completion
ADS-9051 — Task — [ANMGD -CLUJ] - Actualizare script conform planului de invatamant transmisandrei.alexandruTo DoNot started
ADS-9166 — Bug — [TUIASI] Shared database write stall blocked SSO logins and report creation on Oct 12Ionut CiolanTo DoNot started
ADS-9212 — Bug — [ANMGD-CLUJ] - Eroare la import studentiTo DoNot started
ADS-9259 — Task — Download RM cu Observatii si Semnataristefan.achimIn ProgressDependency delay

Miss pattern summary

PatternCountWhat it suggests
Partial completion5Breakdown / sizing / stage-gating was not tight enough
Dependency delay3Capacity protection or dependency timing created slip
Not started8A committed item remained outside execution focus
In Progress / Code Review carryovers7Most misses were moving, but not closing

Workflow-truth mismatches

Items marked Done in the sprint-review field while Jira workflow status was still non-final.

Jira itemStatusIntent
ADS-7660 — Modificari pe catalog noteReady to mergeFinish
ADS-8612 — [Petre Andrei]-Actualizare nume localitateReady to mergeFinish
ADS-8842 — Modificari venite dupa importReady to merge
ADS-9205 — [Petre Andrei] - Actualizare pondere din DBReady to mergeFinish
ADS-9311 — [Asachi]: Note eronateReady to merge

Executive follow-up questions

QuestionWhy this mattersWhat evidence to ask for
Why did committed items carry over despite planning readiness?This tests execution quality rather than just scope quality.Show carryovers split by progress continuation, dependency, and not-started.
Are Progress items being managed intentionally?Progress items are allowed to continue, but the continuation should be visible and controlled.Show the original slice and the specific landing expectation for each item.
Is added work a healthy responsiveness level or chronic interruption?High responsiveness can hide systemic instability and diluted predictability.Show which added items were urgent/reactive versus discretionary scope change.
Can we trust Done in review when workflow is still non-final?Workflow-truth gaps reduce trust and make completion easy to game.Show the exact mismatches and the completion rule to enforce next sprint.

Usage note: start with the top-line metrics, then use the traceability links to answer these questions with issue-level evidence.

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list2222 issues in the planning snapshot
Sprint review / outcome snapshot raw list2929 issues in the Friday review snapshot
Normalized sprint fact base2828 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

These companion artifacts keep the pulse debuggable when a leader wants the exact rows behind a metric or a count.