Sprint Pulse

Product Pulse — Mobile ADS Q4 W40 - 05-09 Oct

Planned sprint ADS Q4 W40 - 05-09 Oct • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 1 of 8 visible items, including 0 Stories, 1 Tasks, and 0 Bugs. Product movement was real, but the sprint was still noisy: 1 items entered after planning and all of them were closed. The main misses were concentrated in 7 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items8Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items1Items whose final outcome bucket is Done
Carry overs7Items not closed at sprint review
Delivered mix0 / 1 / 0Stories / Tasks / Bugs delivered
Entry kind mix7 / 1 / 0Planned / Added during sprint / Stretch visible
Readiness mix3 / 5 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended1/1Progress items were expected not to finish in this sprint

Stories done (0)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered

Tasks done (1)

Jira itemHow entered
ADS-9100 — AI widget notificationAdded

Bugs done (0)

Jira itemHow entered

Carry overs / not delivered (7)

Jira itemWhy it carried
ADS-8955 — Task — Implement discipline elements on annual averagePartial completion
ADS-8997 — Story — [Mobile] - New User Experience PolishNot started
ADS-9027 — Bug — [MOB] Imposibilitate autentificare in contNot started
ADS-9063 — Bug — [MOB] pagina alba la accesarea Grupuri din perspectiva de parinteNot started
ADS-9065 — Bug — [MOB] Lipsa subscriptieNot started
ADS-9078 — Story — Investigate login, subs, refresh token mechanismNot started
ADS-9080 — Story — Create unit testing for Reports, Subjects, Activites, NewsfeedPartial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion2Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started5Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

1 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list77 issues in the planning snapshot
Sprint review / outcome snapshot raw list99 issues in the Friday review snapshot
Normalized sprint fact base88 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.