Sprint Pulse

Product Pulse — Mobile ADS Q4 W41 - 12-16 Oct

Planned sprint ADS Q4 W41 - 12-16 Oct • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 10 of 14 visible items, including 2 Stories, 5 Tasks, and 3 Bugs. Product movement was real, but the sprint was still noisy: 4 items entered after planning and 3 of them were closed. The main misses were concentrated in 4 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items14Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items10Items whose final outcome bucket is Done
Carry overs4Items not closed at sprint review
Delivered mix2 / 5 / 3Stories / Tasks / Bugs delivered
Entry kind mix10 / 4 / 0Planned / Added during sprint / Stretch visible
Readiness mix5 / 9 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended1/1Progress items were expected not to finish in this sprint

Stories done (2)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-9078 — Investigate login, subs, refresh token mechanismPlanned
ADS-9245 — Implementare checkout flow subscriptiiAdded

Tasks done (5)

Jira itemHow entered
ADS-8969 — Update current subscription packagePlanned
ADS-8970 — Fixed web view loading for HuaweiPlanned
ADS-8971 — Fixes after 2.9.8 releasePlanned
ADS-9244 — Adaugare modul Asistenta chatAdded
ADS-9246 — OTA and Live navigation improvementsAdded

Bugs done (3)

Jira itemHow entered
ADS-9027 — [MOB] Imposibilitate autentificare in contPlanned
ADS-9063 — [MOB] pagina alba la accesarea Grupuri din perspectiva de parintePlanned
ADS-9065 — [MOB] Lipsa subscriptiePlanned

Carry overs / not delivered (4)

Jira itemWhy it carried
ADS-8955 — Task — Implement discipline elements on annual averagePriority Change
ADS-8997 — Story — [Mobile] - New User Experience PolishNot started
ADS-9080 — Story — Create unit testing for Reports, Subjects, Activites, NewsfeedPartial completion
ADS-9149 — Task — Feature flags - Evolutie elevPartial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion2Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started1Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

1 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1111 issues in the planning snapshot
Sprint review / outcome snapshot raw list1515 issues in the Friday review snapshot
Normalized sprint fact base1414 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.