Product Pulse — Mobile ADS Q4 W45 - 09-13 Nov

Planned sprint ADS Q4 W45 - 09-13 Nov • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 7 of 12 visible items, including 3 Stories, 4 Tasks, and 0 Bugs. Product movement was real, but the sprint was still noisy: 3 items entered after planning and 2 of them were closed. The main misses were concentrated in 5 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items12Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items7Items whose final outcome bucket is Done
Carry overs5Items not closed at sprint review
Delivered mix3 / 4 / 0Stories / Tasks / Bugs delivered
Entry kind mix9 / 3 / 0Planned / Added during sprint / Stretch visible
Readiness mix7 / 4 / 1Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended1/2Progress items were expected not to finish in this sprint

Stories done (3)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-9079 — Create agents directoryAdded
ADS-9080 — Create unit testing for Reports, Subjects, Activites, NewsfeedPlanned
ADS-9302 — Widget - Rapoarte AcademiceAdded

Tasks done (4)

Jira itemHow entered
ADS-9340 — [FE][Mob] - Date elevi inactiviPlanned
ADS-9402 — [Mob] - Native new messagePlanned
ADS-9499 — Indice evolutie pentru calificativePlanned
ADS-9518 — [MOB] Modificari titulaturaPlanned

Bugs done (0)

Jira itemHow entered

Carry overs / not delivered (5)

Jira itemWhy it carried
ADS-9446 — Story — [FE] parintele Amet Ebru ID 1465705 nu vede evolutia copilului pe anii precedenti, cu toate ca a avut platitNot started
ADS-9517 — Task — [MOB] Adapt mobile app to UTCPartial completion
ADS-9519 — Task — [MOB] Banner profesori pentru meditatiiPartial completion
ADS-9531 — Task — Activities design updateNot started
ADS-9559 — Task — Holy feedbackNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion2Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started2Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

1 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list99 issues in the planning snapshot
Sprint review / outcome snapshot raw list1313 issues in the Friday review snapshot
Normalized sprint fact base1212 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.