Product Pulse — Team 1 ADS Q3 W29 - 20-24 Jul

Planned sprint ADS Q3 W29 - 20-24 Jul • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 10 of 22 visible items, including 2 Stories, 1 Tasks, and 5 Bugs. Product movement was real, but the sprint was still noisy: 5 items entered after planning and 1 of them were closed. The main misses were concentrated in 12 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items22Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items10Items whose final outcome bucket is Done
Carry overs12Items not closed at sprint review
Delivered mix2 / 1 / 5Stories / Tasks / Bugs delivered
Entry kind mix17 / 5 / 0Planned / Added during sprint / Stretch visible
Readiness mix6 / 16 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended3/3Progress items were expected not to finish in this sprint

Stories done (2)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-6545 — [SDK] Implementare v1 layer comunicare native-web *post message bridgePlanned
ADS-8262 — [FE] Responsive conduită / listă eleviPlanned

Tasks done (1)

Jira itemHow entered
ADS-8205 — [FE]: Modificari rute pentru MobilePlanned

Bugs done (5)

Jira itemHow entered
ADS-8224 — [FE] La editarea elevului, campul "rol" nu afiseaza optiuni in dropdown si impiedica salvarea modificarilorPlanned
ADS-8245 — [FE] Preferințe generale alignmentPlanned
ADS-8257 — [BE] - Eroare 400 la debifare afisare in catalog a unui transfer intre clasePlanned
ADS-8269 — [Documente - Catalog] - De modificat fontul primei paginiPlanned
ADS-8282 — [Prod][AWS][legacy-web] Student profile save overflows adrCodPostal because postal length is not validated - 2 errors/72hPlanned

Carry overs / not delivered (12)

Jira itemWhy it carried
ADS-2590 — Bug — [Students] - Trebuie inlocuit articolul de la model import automat-date de completare si sa se deschida articolul din manualul de utilizare daca de da click pe linkul respectivPartial completion
ADS-3896 — Bug — [Classes][Homework] -Problema la Trimiterea Temelor Corectate din aplicatia de mobilNot started
ADS-5784 — Story — [FE/BE] Refactor pagina de permisiuni
ADS-7816 — Story — [SIIIR] - Import clasePartial completion
ADS-7907 — Task — [BE] Refactoring SQL_CALC_FOUND_ROWSPartial completion
ADS-8067 — Story — [Incadrare] Refactoring React & APILate start / sequencing
ADS-8105 — Story — Impartirea pe modulePartial completion
ADS-8129 — Improvement — Sincronizare istoric elevi
ADS-8209 — Bug — [Prod][AWS][legacy-web] GET /api/v2/fisiere/view returns HTTP 500 when M_fisiere.php calls query() on nullNot started
ADS-8285 — Bug — [Medii] - Recalculare medii greșite
ADS-8306 — Bug — [FE] - Nefunctionalitate filtru "Elevi"
ADS-8310 — Bug — [Prod][AWS][legacy-web] Admin home reads missing school session context and renders warnings - 35 errors/72h

Blocker / miss pattern

MetricValueHow to read it
Partial completion4Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started2Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

3 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

One Done row (ADS-8262 — Story — [FE] Responsive conduită / listă elevi) is still flagged as Partial completion in the outcome file. The report respects the outcome as Done and treats the flag as a data-quality anomaly.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list17Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list22Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base22Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline17Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot22Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review17planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning5planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review0planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows0Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Visible sprint items22all rows in the outcome snapshot22/22Open denominator JQL
Delivered items10rows whose Sprint Outcome is Done10/22Open denominator JQL
Carry overs12rows whose Sprint Outcome is Carry Over or remained open in review12/22Open denominator JQL
Stories done2done items where issue type = Story2/10Open denominator JQL
Tasks done1done items where issue type = Task1/10Open denominator JQL
Bugs done5done items where issue type = Bug5/10Open denominator JQL
Entry kind mix17 / 5 / 0Planned / Added / Stretch counts across all visible sprint items22/22Open denominator JQL
Readiness mix6 / 16 / 0Ready / At risk / Not Ready counts across all visible sprint items22/22Open denominator JQL
Progress items behaving as intended3/3progress-intent items that carried as intended ÷ all progress-intent committed items3/3Open denominator JQL
Partial completion misses4carryover items whose miss reason is Partial completion4/12Open denominator JQL
Dependency / competing work misses0carryover items whose miss reason is Dependency delay0/12Open denominator JQL
Not-started misses2carryover items whose miss reason is Not started2/12Open denominator JQL

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.