Product Pulse — Team 1 ADS Q3 W31 - 03-07 Aug

Planned sprint ADS Q3 W31 - 03-07 Aug • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 12 of 22 visible items, including 3 Stories, 2 Tasks, and 6 Bugs. Product movement was real, but the sprint was still noisy: 9 items entered after planning and 5 of them were closed. The main misses were concentrated in 10 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items22Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items12Items whose final outcome bucket is Done
Carry overs10Items not closed at sprint review
Delivered mix3 / 2 / 6Stories / Tasks / Bugs delivered
Entry kind mix13 / 9 / 0Planned / Added during sprint / Stretch visible
Readiness mix7 / 13 / 2Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended1/5Progress items were expected not to finish in this sprint

Stories done (3)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-3619 — [Conduita] - View dirigintePlanned
ADS-6357 — [Conduita] - Adaugarea materiei in conduitaPlanned
ADS-8105 — Impartirea pe modulePlanned

Tasks done (2)

Jira itemHow entered
ADS-8331 — [FE] - Student detailsPlanned
ADS-8421 — [BE] Download archive - presignedUrlAdded

Bugs done (6)

Jira itemHow entered
ADS-8306 — [FE] - Nefunctionalitate filtru "Elevi"Planned
ADS-8310 — [Prod][AWS][legacy-web] Admin home reads missing school session context and renders warnings - 35 errors/72hPlanned
ADS-8401 — [FE] - Incarcare fisier in folder SCIM/SCEACAdded
ADS-8402 — [BE] - Eroare la descarcare condicaAdded
ADS-8416 — [FE] - Nu se poate adăuga un video prin embed (Admitere & EduMarket)Added
ADS-8437 — [FE] Preferinte conturi - hover bugAdded

Carry overs / not delivered (10)

Jira itemWhy it carried
ADS-2590 — Bug — [Students] - Trebuie inlocuit articolul de la model import automat-date de completare si sa se deschida articolul din manualul de utilizare daca de da click pe linkul respectivPartial completion
ADS-669 — Story — [Conduita] - Editeaza conduitaNot started
ADS-7816 — Story — [SIIIR] - Import clasePartial completion
ADS-7907 — Task — [BE] Refactoring SQL_CALC_FOUND_ROWSPartial completion
ADS-8067 — Story — [Incadrare] Refactoring React & APIPartial completion
ADS-8209 — Bug — [Prod][AWS][legacy-web] GET /api/v2/fisiere/view returns HTTP 500 when M_fisiere.php calls query() on nullNot started
ADS-8254 — Bug — [PROD] - In sectiunea de Roluri si permisiuni apar denumiri de director, elevi, parintiDependency delay
ADS-8366 — Bug — [Prod][AWS][legacy-web] Tenantless API requests hit null school DB handle across timetable, grades, and portfolioPartial completion
ADS-8429 — Bug — [FE] - cod de inregistrare in litereNot started
ADS-8446 — Task — Probleme identificate după lansarea structurii pe moduleNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion5Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started1Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

1 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list14Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list25Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base22Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline13Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot22Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review13planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning9planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review0planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows3Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Visible sprint items22all rows in the outcome snapshot22/22Open denominator JQL
Delivered items12rows whose Sprint Outcome is Done12/22Open denominator JQL
Carry overs10rows whose Sprint Outcome is Carry Over or remained open in review10/22Open denominator JQL
Stories done3done items where issue type = Story3/12Open denominator JQL
Tasks done2done items where issue type = Task2/12Open denominator JQL
Bugs done6done items where issue type = Bug6/12Open denominator JQL
Entry kind mix13 / 9 / 0Planned / Added / Stretch counts across all visible sprint items22/22Open denominator JQL
Readiness mix7 / 13 / 2Ready / At risk / Not Ready counts across all visible sprint items22/22Open denominator JQL
Progress items behaving as intended1/5progress-intent items that carried as intended ÷ all progress-intent committed items1/5Open denominator JQL
Partial completion misses5carryover items whose miss reason is Partial completion5/10Open denominator JQL
Dependency / competing work misses0carryover items whose miss reason is Dependency delay0/10Open denominator JQL
Not-started misses1carryover items whose miss reason is Not started1/10Open denominator JQL

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.