Executive summary

Yellow. The sprint closed 3 of 22 visible items, including 1 Stories, 0 Tasks, and 2 Bugs. Product movement was real, but the sprint was still noisy: 8 items entered after planning and 2 of them were closed. The main misses were concentrated in 19 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items22Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items3Items whose final outcome bucket is Done
Carry overs19Items not closed at sprint review
Delivered mix1 / 0 / 2Stories / Tasks / Bugs delivered
Entry kind mix14 / 8 / 0Planned / Added during sprint / Stretch visible
Readiness mix11 / 10 / 1Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended3/4Progress items were expected not to finish in this sprint

Stories done (1)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-7921 — Upgrade to MySQL 8.4Planned

Tasks done (0)

Jira itemHow entered

Bugs done (2)

Jira itemHow entered
ADS-8511 — [BE] ordinea claselor la adaugareAdded
ADS-8515 — [FE] Preferinte notificari dividerAdded

Carry overs / not delivered (19)

Jira itemWhy it carried
ADS-2590 — Bug — [Students] - Trebuie inlocuit articolul de la model import automat-date de completare si sa se deschida articolul din manualul de utilizare daca de da click pe linkul respectivNot started
ADS-7111 — Story — Conturi parinti active/inactivePartial completion
ADS-7654 — Bug — Grades.php / AverageCalculator: POST /api/v2/grades accepts grade but skips average recomputation - 2 errors/24hNot started
ADS-7816 — Story — [SIIIR] - Import clasePartial completion
ADS-7818 — Story — [SIIIR] - Import eleviPartial completion
ADS-7852 — Task — [BE]: Dezactivare actiuni noteaza (si bulk) daca media anuala si/sau media semestriala este incheiataPartial completion
ADS-8067 — Story — [Incadrare] Refactoring React & APIPartial completion
ADS-8209 — Bug — [Prod][AWS][legacy-web] GET /api/v2/fisiere/view returns HTTP 500 when M_fisiere.php calls query() on nullNot started
ADS-8366 — Bug — [Prod][AWS][legacy-web] Tenantless API requests hit null school DB handle across timetable, grades, and portfolioNot started
ADS-8455 — Bug — [AWS prod][Teacher school years] M_cadre omits pagination total after merge - 396 errors/6hNot started
ADS-8462 — Task — [Localizare] Elemente netraduse în interfața English, grupate per rolPartial completion
ADS-8474 — Bug — [Documente] - Indicatori gresiti ID 5809Partial completion
ADS-8488 — Bug — [Catalog] - Nu se poate atribui nota la corigență pentru elev transferatNot started
ADS-8506 — Bug — [Prod][AWS][legacy-web] Student export binds an empty DATE value and silently returns no rows - 10 errors/72hNot started
ADS-8508 — Bug — [Cont] - Nu se poate modifica genul și data nașteriiNot started
ADS-8510 — Bug — [FE] diferenta numar elevi in raportul "promovabilitae elevi"Not started
ADS-8516 — Task — Routes calendar detailsPartial completion
ADS-8524 — Bug — [Prod][AWS][legacy-web] svcAuth cannot encrypt/cache service tokens across all web pods - 63,047 errors/72hNot started
ADS-8542 — Bug — [FE] Materiile nu au elevi asociati dupa copierea incadrariiNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion7Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started7Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

3 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1919 issues in the planning snapshot
Sprint review / outcome snapshot raw list2626 issues in the Friday review snapshot
Normalized sprint fact base2222 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.