Executive summary

Yellow. The sprint closed 17 of 30 visible items, including 1 Stories, 5 Tasks, and 10 Bugs. Product movement was real, but the sprint was still noisy: 8 items entered after planning and 4 of them were closed. The main misses were concentrated in 13 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items30Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items17Items whose final outcome bucket is Done
Carry overs13Items not closed at sprint review
Delivered mix1 / 5 / 10Stories / Tasks / Bugs delivered
Entry kind mix22 / 8 / 0Planned / Added during sprint / Stretch visible
Readiness mix10 / 19 / 1Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended1/2Progress items were expected not to finish in this sprint

Stories done (1)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-9098 — Mecanism trimite coduri de acces cu nr de zile configurabilPlanned

Tasks done (5)

Jira itemHow entered
ADS-8727 — Stergere din baza de date conturile eleviilor si parintiilor din anul scolar 2025-2026Added
ADS-9047 — Adaugare coordonator clasa in lista de destinatari propusiPlanned
ADS-9064 — [SIIIR] - Elevi duplicati WurmbrandPlanned
ADS-9084 — mutare ID 6179 la ID 6254Planned
ADS-9143 — Verificare dupa eliminarea vechiului S3Added

Bugs done (10)

Jira itemHow entered
ADS-8785 — [Prod][AWS][Auth] Password recovery silently skips missing parent profile - 28 requests/72hPlanned
ADS-8841 — [FE] Clase lipsa din statisticile de promovabilitate pentru anul scolar 2025-2026Planned
ADS-8964 — [Prod][AWS][Web] Absence save returns 500 when annual-average upsert deadlocksPlanned
ADS-8985 — [Prod][AWS][Web] Registration confirmation returns 500 on duplicate usernamePlanned
ADS-8992 — [FE] eroare 500 la atasarea unei poze la sala/cladirePlanned
ADS-9015 — [Prod][AWS][Grades] Boolean lock result is read as an array and can bypass locked-grade validationPlanned
ADS-9031 — [FE] promovabilitate afisata 0 in statistici pentru o clasaPlanned
ADS-9094 — [Prod][TUIASI][Auth] SSO token transport error is treated as access token and returns HTTP 400Planned
ADS-9112 — [Prod][AWS][Web] Parent API POST returns 500 on oversized adrBlocAdded
ADS-9117 — sincronizare SIIR id 7197Added

Carry overs / not delivered (13)

Jira itemWhy it carried
ADS-3757 — Story — [Site] - Actualizare website AdservioPartial completion
ADS-7803 — Task — [FE/BE/MOB/UNI] - TitulaturaDependency delay
ADS-7817 — Story — [SIIIR] - Import cadre didacticePartial completion
ADS-8260 — Bug — [Prod][AWS][Web] Global-message modal fails on missing CMC metadata, including teacher-tab HTTP 500Not started
ADS-8510 — Bug — [FE] diferenta numar elevi in raportul "promovabilitae elevi"Partial completion
ADS-8567 — Story — NOMENCLATOR - Refactor structura clasaPartial completion
ADS-8953 — Bug — [BE] statistici- valorile pentru mediul de provenienta sunt afisate gresit pentru anul scolar anteriorPartial completion
ADS-9068 — Improvement — Move fs events to object + previous_values; stop signalling moves via a `moved` field on createdNot started
ADS-9095 — Task — [FE]: Fix erori din consolaNot started
ADS-9102 — Task — [BE] Change response status codeLate start / sequencing
ADS-9130 — Task — [FE/BE/MOB] - Cleanup vechea pagina de incadrarePartial completion
ADS-9131 — Task — [BE/FE]: Validare pe edit incadrareNot started
ADS-9155 — Task — Fix Teste automatePartial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion4Carryovers blocked by partial completion
Dependency / competing work1Delivery slipped because attention or dependency landed elsewhere
Not started3Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

1 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list2929 issues in the planning snapshot
Sprint review / outcome snapshot raw list3737 issues in the Friday review snapshot
Normalized sprint fact base3030 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.