Sprint Pulse

Product Pulse — Team 1 ADS Q4 W41 - 12-16 Oct

Planned sprint ADS Q4 W41 - 12-16 Oct • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 16 of 27 visible items, including 1 Stories, 3 Tasks, and 12 Bugs. Product movement was real, but the sprint was still noisy: 7 items entered after planning and 6 of them were closed. The main misses were concentrated in 11 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items27Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items16Items whose final outcome bucket is Done
Carry overs11Items not closed at sprint review
Delivered mix1 / 3 / 12Stories / Tasks / Bugs delivered
Entry kind mix20 / 7 / 0Planned / Added during sprint / Stretch visible
Readiness mix14 / 12 / 1Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended1/1Progress items were expected not to finish in this sprint

Stories done (1)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-3757 — [Site] - Actualizare website AdservioPlanned

Tasks done (3)

Jira itemHow entered
ADS-9064 — [SIIIR] - Elevi duplicati WurmbrandPlanned
ADS-9131 — [BE/FE]: Validare pe edit incadrarePlanned
ADS-9250 — [BE] LInk parinti aceasi școalăAdded

Bugs done (12)

Jira itemHow entered
ADS-8510 — [FE] diferenta numar elevi in raportul "promovabilitae elevi"Planned
ADS-8953 — [BE] statistici- valorile pentru mediul de provenienta sunt afisate gresit pentru anul scolar anteriorPlanned
ADS-8985 — [Prod][AWS][Web] Registration confirmation returns 500 on duplicate usernamePlanned
ADS-9117 — sincronizare SIIR id 7197Planned
ADS-9163 — [Prod][AWS][Docgen] Gradebook module PDF returns 500 on one Yoga renderer podPlanned
ADS-9165 — [Prod][AWS][Web] Teacher history returns 500 when both date filters are blankPlanned
ADS-9178 — [FE] transferul elevului intre clase este blocat din cauza unei erori privind sistemul de notarePlanned
ADS-9185 — [FE] generarea nejustificata a codului de inregistrar pentru utilizatorii cu e-mail validatAdded
ADS-9195 — [FE] Eroare 400 la incercarea de a sterge o clasaAdded
ADS-9222 — [FE] Phone number prefix field too longAdded
ADS-9223 — [FE] Foaia matricola afiseaza media pe anul curent desi optiunea nu e bifataAdded
ADS-9237 — [FE] Calendar class select too longAdded

Carry overs / not delivered (11)

Jira itemWhy it carried
ADS-4641 — Story — Raport - Situatia privind Rezultatele obtinutePartial completion
ADS-7803 — Task — [FE/BE/MOB/UNI] - TitulaturaPartial completion
ADS-7817 — Story — [SIIIR] - Import cadre didacticePartial completion
ADS-8260 — Bug — [Prod][AWS][Web] Global-message modal fails on missing CMC metadata, including teacher-tab HTTP 500Not started
ADS-8567 — Story — NOMENCLATOR - Refactor structura clasaPartial completion
ADS-9047 — Task — Adaugare coordonator clasa in lista de destinatari propusiDependency delay
ADS-9068 — Improvement — Move fs events to object + previous_values; stop signalling moves via a `moved` field on createdNot started
ADS-9095 — Task — [FE]: Fix erori din consolaNot started
ADS-9102 — Task — [BE] Change response status codePartial completion
ADS-9130 — Task — [FE/BE/MOB] - Cleanup vechea pagina de incadrarePartial completion
ADS-9167 — Task — [BE]: Reset activation code timer after email/phone changePartial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion6Carryovers blocked by partial completion
Dependency / competing work1Delivery slipped because attention or dependency landed elsewhere
Not started3Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

1 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list2727 issues in the planning snapshot
Sprint review / outcome snapshot raw list3434 issues in the Friday review snapshot
Normalized sprint fact base2727 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.