Sprint Pulse

Product Pulse — Team 1 ADS Q4 W42 - 19-23 Oct

Planned sprint ADS Q4 W42 - 19-23 Oct • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 16 of 27 visible items, including 3 Stories, 4 Tasks, and 7 Bugs. Product movement was real, but the sprint was still noisy: 8 items entered after planning and 7 of them were closed. The main misses were concentrated in 11 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items27Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items16Items whose final outcome bucket is Done
Carry overs11Items not closed at sprint review
Delivered mix3 / 4 / 7Stories / Tasks / Bugs delivered
Entry kind mix19 / 8 / 0Planned / Added during sprint / Stretch visible
Readiness mix13 / 13 / 1Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended2/3Progress items were expected not to finish in this sprint

Stories done (3)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-4641 — Raport - Situatia privind Rezultatele obtinutePlanned
ADS-7817 — [SIIIR] - Import cadre didacticePlanned
ADS-9267 — [PUBLIC] iOS cookie missingAdded

Tasks done (4)

Jira itemHow entered
ADS-9037 — [Mesaje] - Default optiuni destinatari pentru parintiPlanned
ADS-9043 — Actualizare text info icon scutiriPlanned
ADS-9130 — [FE/BE/MOB] - Cleanup vechea pagina de incadrarePlanned
ADS-9307 — [BE] stergere moduleAdded

Bugs done (7)

Jira itemHow entered
ADS-9195 — [FE] Eroare 400 la incercarea de a sterge o clasaPlanned
ADS-9218 — [FE] Adaugarea unui eveniment in Grupuri esueaza pentru denumiri de peste 40 de caracterePlanned
ADS-9242 — [FE] notele introduse dispar dupa actualizarea aplicatieiPlanned
ADS-9276 — [MOB] mesaj clasa- selectia elevilor si parintilor nu e disponibila, iar lista profesorilor este incorectaAdded
ADS-9280 — [FE] Missing button style on news cardAdded
ADS-9308 — [FE] Raportul "Număr absențe pe clase" ramane blocat la schimbarea ciclului de studiuAdded
ADS-9322 — mesaj eroare la sincronizarea cu SIIRAdded

Carry overs / not delivered (11)

Jira itemWhy it carried
ADS-7803 — Task — [FE/BE/MOB/UNI] - TitulaturaPartial completion
ADS-8260 — Bug — [Prod][AWS][Web] Global-message modal fails on missing CMC metadata, including teacher-tab HTTP 500Partial completion
ADS-8567 — Story — NOMENCLATOR - Refactor structura clasaPartial completion
ADS-8581 — Story — Statistici - Distribuția elevilor pe intervale de medii - Top eleviPartial completion
ADS-9047 — Task — Adaugare coordonator clasa in lista de destinatari propusiDependency delay
ADS-9068 — Improvement — Move fs events to object + previous_values; stop signalling moves via a `moved` field on createdNot started
ADS-9102 — Task — [BE] Change response status codePartial completion
ADS-9167 — Task — [BE]: Reset activation code timer after email/phone changePartial completion
ADS-9239 — Task — raport orarPartial completion
ADS-9265 — Task — Product Analytics v2 (team1)Partial completion
ADS-9319 — Bug — [Prod][Docgen] Legacy ADST after token migration becomes report 500 instead of 401Partial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion8Carryovers blocked by partial completion
Dependency / competing work1Delivery slipped because attention or dependency landed elsewhere
Not started1Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

2 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list2121 issues in the planning snapshot
Sprint review / outcome snapshot raw list2929 issues in the Friday review snapshot
Normalized sprint fact base2727 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.