Executive summary

Yellow. The sprint closed 21 of 41 visible items, including 4 Stories, 11 Tasks, and 5 Bugs. Product movement was real, but the sprint was still noisy: 16 items entered after planning and 11 of them were closed. The main misses were concentrated in 20 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items41Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items21Items whose final outcome bucket is Done
Carry overs20Items not closed at sprint review
Delivered mix4 / 11 / 5Stories / Tasks / Bugs delivered
Entry kind mix25 / 16 / 0Planned / Added during sprint / Stretch visible
Readiness mix16 / 19 / 6Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended5/7Progress items were expected not to finish in this sprint

Stories done (4)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-8567 — NOMENCLATOR - Refactor structura clasaPlanned
ADS-8576 — [Elev][Parinte] - Redesign Note si absente - WebPlanned
ADS-9328 — [SUPERSET] Product analytics pentru SIIRPlanned
ADS-9345 — Delete clSpecID completely and drop from DBPlanned

Tasks done (11)

Jira itemHow entered
ADS-8760 — [FE]: Schimbari pe Suprascrieri si transferuriAdded
ADS-9041 — scoatere limitare afisare membrii grup sectiunea mesajePlanned
ADS-9047 — Adaugare coordonator clasa in lista de destinatari propusiPlanned
ADS-9372 — Fix add grade issue on last day of modulePlanned
ADS-9412 — stergere absente in vacanta de toamna din condica de prezentaPlanned
ADS-9440 — [FE] Class toolbar action hugAdded
ADS-9448 — Hotfix testeAdded
ADS-9480 — stergere adresa de e-mail din baza de dateAdded
ADS-9501 — Teste note și absențeAdded
ADS-9507 — [PUBLIC] Fix mobile menuAdded
ADS-9512 — [FE] Flags note și absențeAdded

Bugs done (5)

Jira itemHow entered
ADS-9398 — [FE] Daycare Actions menu disappears when table columns refreshPlanned
ADS-9444 — [MOB] nu se poate nota pe modulul 1, cu toate ca setarile scolii permitAdded
ADS-9447 — [FE] elevii apar cu status "inactivi" cand se incearca adaugarea unei scutiriAdded
ADS-9484 — [UNI] [Catalog] Note lipsă la disciplina din catalog în urma schimbării formei de evaluare (TUIASI)Added
ADS-9485 — [FE] lipsa nume/prenume invatator in catalog PDF pe ultima pagina la clasele primareAdded

Carry overs / not delivered (20)

Jira itemWhy it carried
ADS-6725 — Improvement — Adeverinta de elevNot started
ADS-7966 — Story — [BE] Standarde de evaluarePartial completion
ADS-8444 — Bug — [AWS prod][Mesaje] User search crashes on Unicode collation mismatchNot started
ADS-9068 — Improvement — Move fs events to object + previous_values; stop signalling moves via a `moved` field on createdNot started
ADS-9102 — Task — [BE] Change response status codeDependency delay
ADS-9239 — Task — raport orarNot started
ADS-9265 — Task — Product Analytics v2 (team1)Partial completion
ADS-9297 — Bug — [FE] calcul medie purtare -nu e setata by default purtare standard romaniaLate start / sequencing
ADS-9344 — Bug — [Prod][AWS][Web] Class repartition returns HTTP 500 on exemption foreign keyNot started
ADS-9355 — Story — [AI] Agent Vio de code review pe MR-uri GitLab (orice proiect)Partial completion
ADS-9385 — Bug — [FE] la transfer intre clase, nu s-au copiat notele si absenteleNot started
ADS-9392 — Bug — [Prod][Notifications] notifications-event-manager crashes overnight on "MySQL server has gone away": tenant DB connection is reused past wait_timeoutPartial completion
ADS-9408 — Task — [Marketing][GetResponse] - Curățare sync părinți: absolvenți cls. a XII-a, școală expirată, UAID dublatNot started
ADS-9415 — Task — [BE] Import SIIIR - specializarePartial completion
ADS-9416 — Bug — [Prod][AWS][Web] Incident creation returns 500 on out-of-range incident numberPartial completion
ADS-9417 — Bug — [Prod][Auth][AWS+TUIASI] IAM lifetime limit rejects SSO and OAuth token issuanceNot started
ADS-9419 — Story — Functie personalPartial completion
ADS-9460 — Story — [FE] Standarde de evaluarePartial completion
ADS-9499 — Task — Indice evolutie pentru calificativePartial completion
ADS-9504 — Bug — [Prod][TUIASI][Auth] IAM signing-key connection reset returns SSO HTTP 500Not started

Blocker / miss pattern

MetricValueHow to read it
Partial completion5Carryovers blocked by partial completion
Dependency / competing work1Delivery slipped because attention or dependency landed elsewhere
Not started8Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

5 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list2626 issues in the planning snapshot
Sprint review / outcome snapshot raw list4444 issues in the Friday review snapshot
Normalized sprint fact base4141 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.