Sprint Pulse

Product Pulse — Team 1 ADS Q4 W45 - 09-13 Nov

Planned sprint ADS Q4 W45 - 09-13 Nov • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 27 of 44 visible items, including 1 Stories, 6 Tasks, and 18 Bugs. Product movement was real, but the sprint was still noisy: 18 items entered after planning and 16 of them were closed. The main misses were concentrated in 17 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items44Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items27Items whose final outcome bucket is Done
Carry overs17Items not closed at sprint review
Delivered mix1 / 6 / 18Stories / Tasks / Bugs delivered
Entry kind mix26 / 18 / 0Planned / Added during sprint / Stretch visible
Readiness mix26 / 15 / 3Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended8/10Progress items were expected not to finish in this sprint

Stories done (1)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-9328 — [SUPERSET] Product analytics pentru SIIRPlanned

Tasks done (6)

Jira itemHow entered
ADS-9208 — [Catalog] - Actualizare punct la Observatii din fisierul de import notePlanned
ADS-9333 — [FE]- Taburi ascunse pe detalii elevPlanned
ADS-9455 — nationalitate maghiara la toti elevii din scoalaAdded
ADS-9495 — [Preuni][FE][Edumarket] - Pe responsive titlul unui articol nu este afisatPlanned
ADS-9538 — [BE][Timetables] Recuperare orarAdded
ADS-9560 — de modificat in bulk programele pentru orarAdded

Bugs done (18)

Jira itemHow entered
ADS-8444 — [AWS prod][Mesaje] User search crashes on Unicode collation mismatchPlanned
ADS-9297 — [FE] calcul medie purtare -nu e setata by default purtare standard romaniaPlanned
ADS-9385 — [FE] la transfer intre clase, nu s-au copiat notele si absentelePlanned
ADS-9416 — [Prod][AWS][Web] Incident creation returns 500 on out-of-range incident numberPlanned
ADS-9524 — [FE] eroare la deselectarea unui elev din incadrarePlanned
ADS-9526 — [FE] lipsa an scolar 2026-2027 in setari unitate invatamant/configurare ani scolarAdded
ADS-9533 — [FE][Incadrare] - Erori modul incadrariAdded
ADS-9537 — [FE] Ecran alb la adăugarea unei scutiri medicale din Management clasăAdded
ADS-9546 — [FE] Eroare la descărcarea documentului din CatalogAdded
ADS-9548 — [MOB] Solicitarea de ștergere a unei note nu este transmisă directorului pentru aprobareAdded
ADS-9553 — [FE] Notele și absențele se transferă parțial la transferul elevilor între claseAdded
ADS-9556 — [FE] Certificatele de formare ale unui cadru didactic nu sunt vizibile pentru secretar/directorAdded
ADS-9562 — [FE] Eroare 400 la bifarea elevului din încadrareAdded
ADS-9571 — [FE] Clase de profesionala lipsă în perspectiva directorului și eroare 404 la eleviAdded
ADS-9575 — [FE] Temele din modulul 1 nu apar la filtrul module „Toate”Added
ADS-9576 — [FE] Lista „Nivel de învățământ” este goală la crearea claseiAdded
ADS-9582 — [FE][Messages] - Nu se incarca date pe categorie din mesagerieAdded
ADS-9589 — [FE] Clase lipsă în perspectiva directoruluiAdded

Carry overs / not delivered (17)

Jira itemWhy it carried
ADS-4410 — Story — Statistici - Progresul elevuluiPartial completion
ADS-6725 — Improvement — Adeverinta de elevDependency delay
ADS-7110 — Story — [Profesor][Teme] - Marcare status tema manualPartial completion
ADS-7966 — Story — [BE] Standarde de evaluarePartial completion
ADS-9068 — Improvement — Move fs events to object + previous_values; stop signalling moves via a `moved` field on createdNot started
ADS-9102 — Task — [BE] Change response status codePartial completion
ADS-9239 — Task — raport orarNot started
ADS-9265 — Task — Product Analytics v2 (team1)Partial completion
ADS-9266 — Task — Eliminare bifa evolutie + pagina EvolutiePartial completion
ADS-9355 — Story — [AI] Agent Vio de code review pe MR-uri GitLab (orice proiect)Not started
ADS-9392 — Bug — [Prod][Notifications] notifications-event-manager crashes overnight on "MySQL server has gone away": tenant DB connection is reused past wait_timeoutPartial completion
ADS-9408 — Task — [Marketing][GetResponse] - Curățare sync părinți: absolvenți cls. a XII-a, școală expirată, UAID dublatNot started
ADS-9415 — Task — [BE] Import SIIIR - Nomenclator nou & specializarePartial completion
ADS-9419 — Story — Functie personalPartial completion
ADS-9460 — Story — [FE] Standarde de evaluareDependency delay
ADS-9557 — Bug — [UNI] [Catalog] Note lipsă la disciplina Practică topografică / Opțional 1-limbi moderne (limba engleză) 1Partial completion
ADS-9595 — Task — Add grades calendar issue - refactorNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion9Carryovers blocked by partial completion
Dependency / competing work2Delivery slipped because attention or dependency landed elsewhere
Not started5Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

8 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list2929 issues in the planning snapshot
Sprint review / outcome snapshot raw list4747 issues in the Friday review snapshot
Normalized sprint fact base4444 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.