Sprint Pulse

Product Pulse — Team 2 ADS Q2 W18 - 4-8 may

Planned sprint ADS Q2 W18 - 4-8 may • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 6 of 25 visible items, including 1 Stories, 3 Tasks, and 2 Bugs. Product movement was real, but the sprint was still noisy: 13 items entered after planning and 5 of them were closed. The main misses were concentrated in 19 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items25Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items6Items whose final outcome bucket is Done
Carry overs19Items not closed at sprint review
Delivered mix1 / 3 / 2Stories / Tasks / Bugs delivered
Entry kind mix12 / 13 / 0Planned / Added during sprint / Stretch visible
Readiness mix11 / 11 / 2Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended4/8Progress items were expected not to finish in this sprint

Stories done (1)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-6606 — [Admitere v2] - US2 Generarea de clasamente/distribuirea automataAdded

Tasks done (3)

Jira itemHow entered
ADS-5949 — [BE] - Implementare procesator de plati local pe main si productiePlanned
ADS-7227 — Testare la tot ce a făcut George la AdmitereAdded
ADS-7260 — [Spike + Solving] - Investigare latenta adaugare Note/AbsenteAdded

Bugs done (2)

Jira itemHow entered
ADS-7344 — [BE] - Eroare 500 la plati online prin EuPlatescAdded
ADS-7387 — admission-api: admission document endpoint returns HTTP 500 - 13 hits/FridayAdded

Carry overs / not delivered (19)

Jira itemWhy it carried
ADS-1757 — Story — [Financiar] - Plati partialePartial completion
ADS-6494 — Story — Log levels & Log formatsNot started
ADS-6675 — Story — [Financiar] - Managementul penalitatilorPartial completion
ADS-7010 — Bug — [FE][Mesagerie] - Eroare mesagerie grupMissing from outcome snapshot
ADS-7191 — Task — [BE] - Tabela subscription_organizations/subscription_users se populeaza chiar daca BE intoarce mesaj de eroare la assignNot started
ADS-7197 — Improvement — [Admission] - ESLintNot started
ADS-7225 — Story — [Admitere V2] - Adaugare manuala candidat&editare candidatPartial completion
ADS-7226 — Task — [BE] - Teste automate pe NewsNot started
ADS-7284 — Story — Refactorizare "Anuleaza recurenta"Not started
ADS-7289 — Bug — [SUBSCRIPTIONS] - Pachetul superior ar trebui folosit când calculăm featuresNot started
ADS-7343 — Task — [Stiri] - Distribuie UpdatesPartial completion
ADS-7405 — Story — [BE] - Local CachePartial completion
ADS-7415 — Story — [Abonamnete] - Carduri promovare pachet - UpdateNot started
ADS-7419 — Bug — [SUBSCRIPTIONS] - Bug-uriPartial completion
ADS-7425 — Story — [Admitere v2][Taxe] - 1. Create session - TaxePartial completion
ADS-7426 — Story — [Admitere v2][Taxe] - 2. Candidate apply - Plata TaxelorNot started
ADS-7481 — Bug — [BE][News] - Issues news uniPartial completion
ADS-7510 — Task — [FR][FE] - UI Enhancement for Single-Image PostsNot started
ADS-7519 — Task — [BE] "Afișează noutăți Adservio" toggle is non-functionalNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion5Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started7Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

4 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1717 issues in the planning snapshot
Sprint review / outcome snapshot raw list2424 issues in the Friday review snapshot
Normalized sprint fact base2525 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.