Product Pulse — Team 2 ADS Q2 W24 - 15-19 Jun

Planned sprint ADS Q2 W24 - 15-19 Jun • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 5 of 15 visible items, including 4 Stories, 0 Tasks, and 1 Bugs. Product movement was real, but the sprint was still noisy: 4 items entered after planning and 2 of them were closed. The main misses were concentrated in 10 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items15Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items5Items whose final outcome bucket is Done
Carry overs10Items not closed at sprint review
Delivered mix4 / 0 / 1Stories / Tasks / Bugs delivered
Entry kind mix11 / 4 / 0Planned / Added during sprint / Stretch visible
Readiness mix7 / 8 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended3/4Progress items were expected not to finish in this sprint

Stories done (4)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-1757 — [Financiar] - Plati partialePlanned
ADS-6805 — [Admitere v2] - Clonarea sesiunilorAdded
ADS-7239 — [Admitere v2] - Label/eticheta cazuri specialePlanned
ADS-7885 — [Admitere v2][Sesiune] - Vizibilitate tranzitii, editare numar de optiuni search dupa ID dosarPlanned

Tasks done (0)

Jira itemHow entered

Bugs done (1)

Jira itemHow entered
ADS-7903 — [FE] - Antetul nu se afiseaza la generarea diplomelor pentru anumite sabloane cand numele directorului/dirigintelui contine doua prenumeAdded

Carry overs / not delivered (10)

Jira itemWhy it carried
ADS-6494 — Story — Log levels & Log formatsDependency delay
ADS-7405 — Story — [BE] - Local CacheDependency delay
ADS-7430 — Story — [Admitere v2][Taxe] - 5. Export platile candidatului&extinderea cu alte informatii ale candidatilorNot started
ADS-7487 — Story — [Admitere v2] - Adaugare candidat in billing&eliberare chitantaPartial completion
ADS-7519 — Task — [BE] "Afișează noutăți Adservio" toggle is non-functionalDependency delay
ADS-7825 — Story — [Admitere v2] - Adaugare specializare & forma de finantare pe optiunile de candidare//Flow candidarePartial completion
ADS-7849 — Story — Stergere date S3Partial completion
ADS-7874 — Task — [Node/React] Cache images for news created by admins via CDNPartial completion
ADS-7896 — Story — Migrare documente S3Partial completion
ADS-7971 — Bug — [Prod][AWS][legacy-web] GET /api/v2/fisiere/view returns HTTP 500 when legacy OSS presign uses a false S3 endpointNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion4Carryovers blocked by partial completion
Dependency / competing work3Delivery slipped because attention or dependency landed elsewhere
Not started1Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

3 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list11Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list15Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base15Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline11Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot15Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review11planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning4planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review0planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows0Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Visible sprint items15all rows in the outcome snapshot15/15Open denominator JQL
Delivered items5rows whose Sprint Outcome is Done5/15Open denominator JQL
Carry overs10rows whose Sprint Outcome is Carry Over or remained open in review10/15Open denominator JQL
Stories done4done items where issue type = Story4/5Open denominator JQL
Tasks done0done items where issue type = Task0/5Open denominator JQL
Bugs done1done items where issue type = Bug1/5Open denominator JQL
Entry kind mix11 / 4 / 0Planned / Added / Stretch counts across all visible sprint items15/15Open denominator JQL
Readiness mix7 / 8 / 0Ready / At risk / Not Ready counts across all visible sprint items15/15Open denominator JQL
Progress items behaving as intended3/4progress-intent items that carried as intended ÷ all progress-intent committed items3/4Open denominator JQL
Partial completion misses4carryover items whose miss reason is Partial completion4/10Open denominator JQL
Dependency / competing work misses3carryover items whose miss reason is Dependency delay3/10Open denominator JQL
Not-started misses1carryover items whose miss reason is Not started1/10Open denominator JQL

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.