Sprint Pulse

Product Pulse — Team 2 ADS Q4 W44 - 02-06 Nov

Planned sprint ADS Q4 W44 - 02-06 Nov • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 7 of 19 visible items, including 2 Stories, 1 Tasks, and 2 Bugs. Product movement was real, but the sprint was still noisy: 9 items entered after planning and 3 of them were closed. The main misses were concentrated in 12 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items19Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items7Items whose final outcome bucket is Done
Carry overs12Items not closed at sprint review
Delivered mix2 / 1 / 2Stories / Tasks / Bugs delivered
Entry kind mix10 / 9 / 0Planned / Added during sprint / Stretch visible
Readiness mix4 / 12 / 3Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended2/2Progress items were expected not to finish in this sprint

Stories done (2)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-6201 — Log formatting - node.js, subscriptionsPlanned
ADS-8757 — [Billing] - Migrat tot codul pe NestPlanned

Tasks done (1)

Jira itemHow entered
ADS-9373 — [Subscriptions] - Design notificări abonamentePlanned

Bugs done (2)

Jira itemHow entered
ADS-9422 — investigat/rezolvat top 10 erorri in sentryPlanned
ADS-9489 — [Prod][AWS][Billing] Billing cycle worker has 0/1 available replicas after Nest migrationAdded

Carry overs / not delivered (12)

Jira itemWhy it carried
ADS-1321 — Story — [BE][LCY][FE] - Adding to the student edit several mother tonguesNot started
ADS-5223 — Story — Raport - Situatia privind Starea disciplinara a elevilorPartial completion
ADS-7696 — Task — Alerta trimitere facturi in SPVPartial completion
ADS-8596 — Task — Notificari SubscriptiiDependency delay
ADS-9019 — Task — stergere "servicii asignate" ID 1680Partial completion
ADS-9210 — Task — Migrare Timezone GMT+3 -> UTCPartial completion
ADS-9298 — Story — Remove FLAG_WELLBEING_AI_SUMMARYPartial completion
ADS-9393 — Bug — [Security][Frontend] Upgrade Storybook 10.1.11 to 10.6.2+ (preview missing origin validation allows code injection)Late start / sequencing
ADS-9405 — Improvement — [Billing] - Acțiuni manuale pe facturi eFacturaNot started
ADS-9427 — Task — verificare plata recurenta id 6317Not started
ADS-9442 — Task — verificat de ce la o obligatiune de plata, nu se ia din soldNot started
ADS-9493 — Task — [Billing] Log formatting & alertePartial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion4Carryovers blocked by partial completion
Dependency / competing work1Delivery slipped because attention or dependency landed elsewhere
Not started2Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

2 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1212 issues in the planning snapshot
Sprint review / outcome snapshot raw list2121 issues in the Friday review snapshot
Normalized sprint fact base1919 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.