Sprint Pulse

Product Pulse — Team 2 ADS Q4 W45 - 09-13 Nov

Planned sprint ADS Q4 W45 - 09-13 Nov • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 13 of 28 visible items, including 2 Stories, 9 Tasks, and 2 Bugs. Product movement was real, but the sprint was still noisy: 7 items entered after planning and 6 of them were closed. The main misses were concentrated in 15 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items28Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items13Items whose final outcome bucket is Done
Carry overs15Items not closed at sprint review
Delivered mix2 / 9 / 2Stories / Tasks / Bugs delivered
Entry kind mix21 / 7 / 0Planned / Added during sprint / Stretch visible
Readiness mix4 / 23 / 1Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended4/4Progress items were expected not to finish in this sprint

Stories done (2)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-5223 — Raport - Situatia privind Starea disciplinara a elevilorPlanned
ADS-9298 — Remove FLAG_WELLBEING_AI_SUMMARYPlanned

Tasks done (9)

Jira itemHow entered
ADS-7696 — Alerta trimitere facturi in SPVPlanned
ADS-8596 — Notificari SubscriptiiPlanned
ADS-9019 — stergere "servicii asignate" ID 1680Planned
ADS-9407 — [Admin][Marketing] - Segmente noi: părinți Grigore Moisil Timișoara + abonament „Marketing test”Planned
ADS-9544 — [AI] - Guard AI summaries complaints endpointsAdded
ADS-9547 — [AI] Student summary shows only ":" instead of the reportAdded
ADS-9549 — Add AI complaints interface for adminsAdded
ADS-9563 — Fixare teste webAdded
ADS-9567 — [AI] Remove the student’s first name from MCP tools and address the student by gender in summariesAdded

Bugs done (2)

Jira itemHow entered
ADS-9509 — [Prod][AWS][Billing] billing-api replicas exit 139 and remove all service endpointsPlanned
ADS-9591 — sentry errors v2Added

Carry overs / not delivered (15)

Jira itemWhy it carried
ADS-1321 — Story — [BE][LCY][FE] - Adding to the student edit several mother tonguesPartial completion
ADS-7698 — Task — Formatare valoare plata la 2 zecimale cand se face payment setup link
ADS-8906 — Improvement — [BE][Billing][Subs] - Migrate date columns from date -> dateTimePartial completion
ADS-8960 — Story — [Edumarket] - Refactor pagina adaugare Oferta/ofertantPartial completion
ADS-9210 — Task — Migrare Timezone GMT+3 -> UTCPartial completion
ADS-9393 — Bug — [Security][Frontend] Upgrade Storybook 10.1.11 to 10.6.2+ (preview missing origin validation allows code injection)
ADS-9405 — Improvement — [Billing] - Acțiuni manuale pe facturi eFactura
ADS-9413 — Story — [Edumarket] - Refactor pagina Edumarket - Display ofertePartial completion
ADS-9427 — Task — verificare plata recurenta id 6317Not started
ADS-9442 — Task — verificat de ce la o obligatiune de plata, nu se ia din soldNot started
ADS-9493 — Task — [Billing] Log formatting & alerteDependency delay
ADS-9513 — Task — [#AI_FIRST] - MCP DBDiagramPartial completion
ADS-9514 — Task — [PLATFORM] - Ștergere Redis vechi după confirmare migrare pe SentinelPartial completion
ADS-9515 — Task — [Alerte] - Endpoint /stats pentru billing
ADS-9592 — Bug — Local Translation ResiliencePartial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion8Carryovers blocked by partial completion
Dependency / competing work1Delivery slipped because attention or dependency landed elsewhere
Not started2Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

4 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list2121 issues in the planning snapshot
Sprint review / outcome snapshot raw list2828 issues in the Friday review snapshot
Normalized sprint fact base2828 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.