Sprint Pulse

Product Pulse — University ADS Q2 W18 - 4-8 may

Planned sprint ADS Q2 W18 - 4-8 may • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 10 of 15 visible items, including 1 Stories, 2 Tasks, and 7 Bugs. Product movement was real, but the sprint was still noisy: 3 items entered after planning and all of them were closed. The main misses were concentrated in 5 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items15Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items10Items whose final outcome bucket is Done
Carry overs5Items not closed at sprint review
Delivered mix1 / 2 / 7Stories / Tasks / Bugs delivered
Entry kind mix12 / 3 / 0Planned / Added during sprint / Stretch visible
Readiness mix6 / 9 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended1/2Progress items were expected not to finish in this sprint

Stories done (1)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-7486 — [ Tuiasi ] Platform has been experiencing high latency at timesAdded

Tasks done (2)

Jira itemHow entered
ADS-7276 — [UNI] University Onboarding - Bulk Operations by RC TeamPlanned
ADS-7462 — [FE] [Cazari]- Data de inceput default >= 12 luniPlanned

Bugs done (7)

Jira itemHow entered
ADS-7331 — [BE][Adauga disciplina][Plan de învățământ] - Adaugarea manuala a unei disciplinePlanned
ADS-7347 — [BUG] - Imposibilitate modificare data sesiunePlanned
ADS-7348 — [FE/BE] [Asachi][Catalog-absente]- Afisare limitata a studentilor de la o anumita grupaPlanned
ADS-7350 — [BE][UPA][Catalog-note discipline] - Nu se afiseaza studentii la DPPD Nivelul II- postuniversitarPlanned
ADS-7461 — [BE][Cazari][Asachi] - Obligatia de plata (taxa aprilie 2026 suma 657) apare incasata dar nu s-a procesat in contul studentuluiPlanned
ADS-7479 — Prod alert: TraefikServiceHighErrorRate [critical] affecting accommodations-apiAdded
ADS-7522 — [BE][UPA][Catalog-note discipline] - Nu se afiseaza studentii la disciplina Practica de specialitateAdded

Carry overs / not delivered (5)

Jira itemWhy it carried
ADS-6661 — Story — [Catalog][Situatie scolara] - US4 EchivalariBug / rework pressure
ADS-6705 — Story — [BE][UPA] -Feedback pe diferite secțiuni din platforma ep.2Partial completion
ADS-7132 — Story — [FE/BE] - Gestiunea restantierilorPriority Change
ADS-7349 — Bug — [BE][Asachi] [Catalog-note discipline]- Student incadrat la un program de studiu eronatDependency delay
ADS-7451 — Bug — [BE] - Condica - Activitati duplicatePartial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion2Carryovers blocked by partial completion
Dependency / competing work1Delivery slipped because attention or dependency landed elsewhere
Not started0Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

1 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1212 issues in the planning snapshot
Sprint review / outcome snapshot raw list1616 issues in the Friday review snapshot
Normalized sprint fact base1515 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.