Sprint Pulse

Product Pulse — University ADS Q2 W20 - 18-22 May

Planned sprint ADS Q2 W20 - 18-22 May • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 9 of 15 visible items, including 2 Stories, 2 Tasks, and 5 Bugs. Product movement was real, but the sprint was still noisy: 9 items entered after planning and 7 of them were closed. The main misses were concentrated in 6 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items15Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items9Items whose final outcome bucket is Done
Carry overs6Items not closed at sprint review
Delivered mix2 / 2 / 5Stories / Tasks / Bugs delivered
Entry kind mix6 / 9 / 0Planned / Added during sprint / Stretch visible
Readiness mix4 / 10 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended3/5Progress items were expected not to finish in this sprint

Delivered work mix

TypePlannedAddedStretchUnclearTotal doneDone %
Story1100222.2%
Task1100222.2%
Bug0500555.6%

Stories done

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-6661 — [Catalog][Situatie scolara] - US4 EchivalariPlanned
ADS-7488 — [Admitere v2] [Cont candidat][PHP][MOB]- Posibilitatea de vizualizare/editare preferinte contAdded

Tasks done

Jira itemHow entered
ADS-5459 — [Universitati][FE] - Missing/incorrect translations in ENPlanned
ADS-6802 — Userii cu permisiune de manager ar trebui sa poata adauga procente la o disciplinaAdded

Bugs done

Jira itemHow entered
ADS-7545 — [FE/BE] [Optionale-facultative] - Mesaj de alerta la dezactivarea disciplinei optionaleAdded
ADS-7569 — [FE/BE][Asachi] - Nu se afișează studenții la căutarea din Admin → StudențiAdded
ADS-7592 — Uni API cohort search returns HTTP 500 on POST /api/v2/uni/cohorts/search due to missing dppd column - 9/293 in 24hAdded
ADS-7593 — Uni API absence creation returns HTTP 500 on POST /api/v2/uni/absences/add - 5/5 in 24hAdded
ADS-7631 — uni-api: POST /api/v2/uni/structure/GRUPA returns HTTP 500 for duplicate-group conflictsAdded

Carry overs / not delivered

Jira itemWhy it carried
ADS-7132 — Story — [FE/BE] - Gestiunea restantierilorDependency delay
ADS-7334 — Bug — [FE/BE] [UPA] [Catalog] - Informatia de la "Forma de învățământ: " nu se completeazaBug / rework pressure
ADS-7451 — Bug — [BE] - Condica - Activitati duplicateMissing from outcome snapshot
ADS-7495 — Story — [FE/BE][Adeverinte absolvire] - Creare Probe evaluareNot started
ADS-7496 — Story — [FE/BE][Adeverinte absolvire] - Probe&medie pe situatie scolaraPartial completion
ADS-7603 — Bug — [BE][Situatie scoalara] - Confirmarea mediei de absolvire nu se propaga pe anii anterioriLate start / sequencing

Blocker / miss pattern

MetricValueHow to read it
Partial completion1Carryovers blocked by partial completion
Dependency / competing work1Delivery slipped because attention or dependency landed elsewhere
Not started1Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

3 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1414 issues in the planning snapshot
Sprint review / outcome snapshot raw list1414 issues in the Friday review snapshot
Normalized sprint fact base1515 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.