Sprint Pulse

Product Pulse — University ADS Q2 W21 - 25-29 Mai

Planned sprint ADS Q2 W21 - 25-29 Mai • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 11 of 16 visible items, including 0 Stories, 5 Tasks, and 6 Bugs. Product movement was real, but the sprint was still noisy: 8 items entered after planning and 7 of them were closed. The main misses were concentrated in 5 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items16Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items11Items whose final outcome bucket is Done
Carry overs5Items not closed at sprint review
Delivered mix0 / 5 / 6Stories / Tasks / Bugs delivered
Entry kind mix8 / 8 / 0Planned / Added during sprint / Stretch visible
Readiness mix6 / 9 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended3/3Progress items were expected not to finish in this sprint

Delivered work mix

TypePlannedAddedStretchUnclearTotal doneDone %
Story000000.0%
Task4100545.5%
Bug0600654.5%

Stories done

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered

Tasks done

Jira itemHow entered
ADS-5459 — [Universitati][FE] - Missing/incorrect translations in ENPlanned
ADS-7431 — [BE] - Nu matricol si initiala pe catalogul PDF AsachiPlanned
ADS-7472 — [FE/BE][UNMB] - Actualizare a structurii (serii, grupe) astfel încât afișarea să respecte ordinea din fișierele transmisePlanned
ADS-7635 — [FE/BE][UNMB] - Posibilitatea introducerii notelor cu zecimalePlanned
ADS-7681 — Îmbunătățirea procesului pentru import Excel studențiAdded

Bugs done

Jira itemHow entered
ADS-7334 — [FE/BE] [UPA] [Catalog] - Informatia de la "Forma de învățământ: " nu se completeazaAdded
ADS-7603 — [BE][Situatie scoalara] - Confirmarea mediei de absolvire nu se propaga pe anii anterioriAdded
ADS-7627 — [BE][UPA][Catalog-> note discipline] - Nu se afiseaza studentii la o disciplina nou adaugata in planAdded
ADS-7650 — [FE][Cazari] - Obligatiile trimise au label 'Netrimis'Added
ADS-7710 — [BE][Asachi][Cazari] - Rambursarea nu se calculează corect și înregistrările nu apar în fișa studentuluiAdded
ADS-7711 — Incasari prin Euplatesc neinregistrate in CAzariAdded

Carry overs / not delivered

Jira itemWhy it carried
ADS-7132 — Story — [FE/BE] - Gestiunea restantierilorDependency delay
ADS-7375 — Story — [BE/FE] - Disciplinele in EN pentru programele de studiu din ENBug / rework pressure
ADS-7476 — Story — [UNI][MAIN][Plan invatamant] - Teste automate Plan invatamant (adaugare, editare, import) E2EPartial completion
ADS-7495 — Story — [FE/BE][Adeverinte absolvire] - Creare Probe evaluarePartial completion
ADS-7496 — Story — [FE/BE][Adeverinte absolvire] - Probe&medie pe situatie scolaraPartial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion3Carryovers blocked by partial completion
Dependency / competing work1Delivery slipped because attention or dependency landed elsewhere
Not started0Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

3 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1313 issues in the planning snapshot
Sprint review / outcome snapshot raw list1616 issues in the Friday review snapshot
Normalized sprint fact base1616 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.