Sprint Pulse

Product Pulse — University ADS Q3 W27 - 06-10 Jul

Planned sprint ADS Q3 W27 - 06-10 Jul • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 6 of 24 visible items, including 0 Stories, 3 Tasks, and 3 Bugs. Product movement was real, but the sprint was still noisy: 3 items entered after planning and 1 of them were closed. The main misses were concentrated in 18 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items24Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items6Items whose final outcome bucket is Done
Carry overs18Items not closed at sprint review
Delivered mix0 / 3 / 3Stories / Tasks / Bugs delivered
Entry kind mix20 / 3 / 1Planned / Added during sprint / Stretch visible
Readiness mix4 / 20 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended5/5Progress items were expected not to finish in this sprint

Stories done (0)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered

Tasks done (3)

Jira itemHow entered
ADS-8000 — [UNI][Denumire disciplina] Refactor atribut Denumire disciplina - locPlanned
ADS-8010 — [BE] -Pe disciplina s-au modificat procentelePlanned
ADS-8056 — [BE] -Inchiderea cataloagelor istorice pentru facultatea CMMIStretch

Bugs done (3)

Jira itemHow entered
ADS-8135 — [BE-PHP][Cazari] - Neconcordanta de solduri pentru un studentPlanned
ADS-8150 — [Prod][AWS][uni-api] POST /api/v2/uni/structure/SECTIE returns 500 when saving section group - 12 errors/72hPlanned
ADS-8190 — [Prod][TUIASI][uni-api] Student profile section lookup joins missing sec.idGrup - 7 errors/72hAdded

Carry overs / not delivered (18)

Jira itemWhy it carried
ADS-6438 — Task — [BE][UNI] - Sincronizare ID-uri Ani universitari/scolari - UNI/preuni - master
ADS-7495 — Story — [FE/BE][Adeverinte absolvire] - Creare Probe evaluareDependency delay
ADS-7496 — Story — [FE/BE][Adeverinte absolvire] - Probe&medie pe situatie scolaraDependency delay
ADS-7534 — Story — [FE/BE][Adeverinte absolvire] - Flow generare adeverintePartial completion
ADS-7535 — Story — [FE] - Download Adeverinta de absolvireDependency delay
ADS-7666 — Bug — accommodations-api: shared HTTP 500 burst on POST /api/v2/accommodations/dorms/list and related endpoints - 16 hits/20mBug / rework pressure
ADS-7890 — Story — [BE PHP][Cazari] - Stingerea obligatiilor din E-taxeDependency delay
ADS-7952 — Story — [Burse] - US1 - Implementare mecanism AtributePartial completion
ADS-7958 — Story — [FE/BE] - Reconstituire scolaritate - transfer, an repetarePartial completion
ADS-8073 — Task — [FE/BE] - Aducerea titularilor din planul curent in tab-ul restantieri pe disciplinaPartial completion
ADS-8104 — Story — [BE-PHP] - Gestiunea cazarilor de vara
ADS-8111 — Bug — [FE/BE] - In centralizator note nu apare numele unei disciplineNot started
ADS-8118 — Bug — [BE] - Lipsa nota si catalog deschis pe restantieriNot started
ADS-8141 — Task — [FE][Situatie scolara] - Lipsa mesaj de eroare la modificarea mediei de absolvireNot started
ADS-8147 — Bug — [BE] - Nu apar studentii pe sesiunea 2Not started
ADS-8153 — Bug — [Prod][TUIASI][accommodations-api] Student balance export returns HTTP 500 when mPDF hits pcre.backtrack_limitNot started
ADS-8186 — Bug — [Prod][AWS][accommodations-api] External person create returns 500 after partial create when fallback faculty is hidden by scopeBug / rework pressure
ADS-8188 — Task — Extindere import studenti cu coloana sectie

Blocker / miss pattern

MetricValueHow to read it
Partial completion4Carryovers blocked by partial completion
Dependency / competing work4Delivery slipped because attention or dependency landed elsewhere
Not started5Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

5 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list21Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list24Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base24Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline21Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot24Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review21planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning3planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review0planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows0Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Visible sprint items24all rows in the outcome snapshot24/24Open denominator JQL
Delivered items6rows whose Sprint Outcome is Done6/24Open denominator JQL
Carry overs18rows whose Sprint Outcome is Carry Over or remained open in review18/24Open denominator JQL
Stories done0done items where issue type = Story0/6Open denominator JQL
Tasks done3done items where issue type = Task3/6Open denominator JQL
Bugs done3done items where issue type = Bug3/6Open denominator JQL
Entry kind mix20 / 3 / 1Planned / Added / Stretch counts across all visible sprint items24/24Open denominator JQL
Readiness mix4 / 20 / 0Ready / At risk / Not Ready counts across all visible sprint items24/24Open denominator JQL
Progress items behaving as intended5/5progress-intent items that carried as intended ÷ all progress-intent committed items5/5Open denominator JQL
Partial completion misses4carryover items whose miss reason is Partial completion4/18Open denominator JQL
Dependency / competing work misses4carryover items whose miss reason is Dependency delay4/18Open denominator JQL
Not-started misses5carryover items whose miss reason is Not started5/18Open denominator JQL

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.