Sprint Pulse

Product Pulse — University ADS Q3 W31 - 03-07 Aug

Planned sprint ADS Q3 W31 - 03-07 Aug • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 7 of 14 visible items, including 3 Stories, 0 Tasks, and 4 Bugs. Product movement was real, but the sprint was still noisy: 2 items entered after planning and all of them were closed. The main misses were concentrated in 7 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items14Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items7Items whose final outcome bucket is Done
Carry overs7Items not closed at sprint review
Delivered mix3 / 0 / 4Stories / Tasks / Bugs delivered
Entry kind mix12 / 2 / 0Planned / Added during sprint / Stretch visible
Readiness mix10 / 4 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended3/3Progress items were expected not to finish in this sprint

Stories done (3)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-7534 — [FE/BE][Adeverinte absolvire] - Flow generare adeverintePlanned
ADS-7535 — [FE] - Download Adeverinta de absolvirePlanned
ADS-8023 — [BE/FE][Adeverinte] Permisiuni &feature flagsPlanned

Tasks done (0)

Jira itemHow entered

Bugs done (4)

Jira itemHow entered
ADS-8318 — [FE] - Eroare la descarcarea unor documente din mesaje expediatePlanned
ADS-8390 — [FE/BE/] - UPA - Incarcare incompleta a notelor studentilor din fisier de import bulkPlanned
ADS-8408 — [Prod][AWS][uni-api] Grade import validation logs national identifiers and expected HTTP 400 as ERROR - 2 requests/72hAdded
ADS-8413 — [FE/BE -Asachi] - Echivalare discipline - nu se pot salva echivalarile pentru disciplinele cu calificativ Admis/RespinsAdded

Carry overs / not delivered (7)

Jira itemWhy it carried
ADS-6142 — Story — [Registre Matricole] -US1.1 Creare volume si asociere studenti incadratiPartial completion
ADS-6438 — Task — [BE][UNI] - Sincronizare ID-uri Ani universitari/scolari - UNI/preuni - masterPartial completion
ADS-7906 — Story — [FE/BE] - Config -posibilitatea setarii mediei ca fiind confirmataPartial completion
ADS-8058 — Story — [BE/FE][UNI] - Generare serii si ani universitari bulkPartial completion
ADS-8159 — Story — [Burse] - US2 - Configurare bugete, PanouPartial completion
ADS-8176 — Story — [State de functii] - Functionalitati si fluxNot started
ADS-8370 — Bug — [FE/BE] - Informatiile din anii anteriori pentru studenti care au trunchi comun nu sunt aduse pe filtru anual selectat atunci cand situatia scolara a unui astfel de studentNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion5Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started2Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

3 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list13Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list15Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base14Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline12Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot14Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review12planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning2planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review0planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows1Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Visible sprint items14all rows in the outcome snapshot14/14Open denominator JQL
Delivered items7rows whose Sprint Outcome is Done7/14Open denominator JQL
Carry overs7rows whose Sprint Outcome is Carry Over or remained open in review7/14Open denominator JQL
Stories done3done items where issue type = Story3/7Open denominator JQL
Tasks done0done items where issue type = Task0/7Open denominator JQL
Bugs done4done items where issue type = Bug4/7Open denominator JQL
Entry kind mix12 / 2 / 0Planned / Added / Stretch counts across all visible sprint items14/14Open denominator JQL
Readiness mix10 / 4 / 0Ready / At risk / Not Ready counts across all visible sprint items14/14Open denominator JQL
Progress items behaving as intended3/3progress-intent items that carried as intended ÷ all progress-intent committed items3/3Open denominator JQL
Partial completion misses5carryover items whose miss reason is Partial completion5/7Open denominator JQL
Dependency / competing work misses0carryover items whose miss reason is Dependency delay0/7Open denominator JQL
Not-started misses2carryover items whose miss reason is Not started2/7Open denominator JQL

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.