Planned sprint ADS Q4 W40 - 05-09 Oct • planning snapshot + end-of-sprint outcome snapshot
This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.
Download DOCXYellow. The sprint closed 16 of 26 visible items, including 4 Stories, 3 Tasks, and 9 Bugs. Product movement was real, but the sprint was still noisy: 7 items entered after planning and 5 of them were closed. The main misses were concentrated in 10 carryovers.
| Metric | Value | How to read it |
|---|---|---|
| Visible sprint items | 26 | Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses |
| Delivered items | 16 | Items whose final outcome bucket is Done |
| Carry overs | 10 | Items not closed at sprint review |
| Delivered mix | 4 / 3 / 9 | Stories / Tasks / Bugs delivered |
| Entry kind mix | 19 / 7 / 0 | Planned / Added during sprint / Stretch visible |
| Readiness mix | 14 / 11 / 1 | Ready / At risk / Not Ready across the normalized sprint fact base |
| Progress items behaving as intended | 3/5 | Progress items were expected not to finish in this sprint |
Below are the items marked Done in the sprint review snapshot, grouped by work-item type.
| Jira item | How entered |
|---|---|
| ADS-8161 — [Burse] - US4 - Alocare burse | Planned |
| ADS-8162 — [Burse] - US5 - Plati | Planned |
| ADS-8166 — [Burse] - US7 - View Student/actiuni student | Planned |
| ADS-8812 — Download RM | Planned |
| Jira item | Why it carried |
|---|---|
| ADS-8164 — Story — [Burse] - US6 - Rapoarte | Late start / sequencing |
| ADS-8679 — Story — Refactor student, situatie scolara | Partial completion |
| ADS-8763 — Task — [Asachi][BE] Import studenti pentru anul universitar 2026-2027 | Dependency delay |
| ADS-8804 — Bug — [Asachi] - Student duplicat in catalog de restantieri la descarcare | Not started |
| ADS-8810 — Bug — [Asachi] - Eroare alocare restantieri | Dependency delay |
| ADS-8866 — Bug — [Asachi] - Problema echivalari | Not started |
| ADS-8938 — Bug — [Asachi] - Problema echivalari | Not started |
| ADS-8981 — Task — Sterge permisiunile vechi - scholarship allocation | Dependency delay |
| ADS-9032 — Bug — [Prod] - Eroare la emiterea adeverintei de absolvire | Partial completion |
| ADS-9123 — Story — Burse - Ceinte dupa demo | Partial completion |
| Metric | Value | How to read it |
|---|---|---|
| Partial completion | 2 | Carryovers blocked by partial completion |
| Dependency / competing work | 2 | Delivery slipped because attention or dependency landed elsewhere |
| Not started | 3 | Committed item never really got underway |
This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.
3 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.
| Report element | How to drill down | Traceability mechanism |
|---|---|---|
| Delivered Stories / Tasks / Bugs | Click the section count rows | Snapshot-exact JQL by issuekey list |
| Carry overs / not delivered | Click the Carry overs count | Snapshot-exact JQL by issuekey list |
| Miss pattern summary | Click each miss-pattern count | Snapshot-exact JQL by issuekey list |
| Snapshot | Issue count | Link |
|---|---|---|
| Planning snapshot raw list | 20 | 20 issues in the planning snapshot |
| Sprint review / outcome snapshot raw list | 27 | 27 issues in the Friday review snapshot |
| Normalized sprint fact base | 26 | 26 issues used for metrics and drill-down |
Planning and outcome are separate frozen moments.
Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.
| Artifact | Link |
|---|---|
| Issue audit register | Open issue-level audit CSV |
| Metric lineage | Open metric lineage CSV |
| JQL traceability register | Open JQL traceability CSV |
| Sprint metrics JSON | Open sprint metrics JSON |
Use these files when you need to validate the exact rows and formulas behind a pulse claim.