Sprint Pulse

Product Pulse — University ADS Q4 W41 - 12-16 Oct

Planned sprint ADS Q4 W41 - 12-16 Oct • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 15 of 28 visible items, including 1 Stories, 4 Tasks, and 10 Bugs. Product movement was real, but the sprint was still noisy: 9 items entered after planning and 7 of them were closed. The main misses were concentrated in 13 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items28Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items15Items whose final outcome bucket is Done
Carry overs13Items not closed at sprint review
Delivered mix1 / 4 / 10Stories / Tasks / Bugs delivered
Entry kind mix19 / 9 / 0Planned / Added during sprint / Stretch visible
Readiness mix11 / 16 / 1Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended4/4Progress items were expected not to finish in this sprint

Stories done (1)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-9123 — Burse - Ceinte dupa demoPlanned

Tasks done (4)

Jira itemHow entered
ADS-6438 — [BE][UNI] - Sincronizare ID-uri Ani universitari/scolari - UNI/preuni - masterPlanned
ADS-9121 — [UNMB] - Inchidere contPlanned
ADS-9172 — [Cazari] - Generare in format editabil lista studenti cazati pe T9, T10 si T11Planned
ADS-9196 — Registru Matricol - AjustariAdded

Bugs done (10)

Jira itemHow entered
ADS-8371 — [Prod][AWS][uni-api] Student create leaves disciplines unassigned when AcademicPlan is missing - 2 errors/72hAdded
ADS-8804 — [Asachi] - Student duplicat in catalog de restantieri la descarcarePlanned
ADS-8810 — [Asachi] - Eroare alocare restantieriPlanned
ADS-8879 — [Asachi] - Eroare acces student in UMSPlanned
ADS-8889 — Ora afisata incorect in istoricul noteiAdded
ADS-9161 — [Asachi] - Nu afiseaza anii de studiu in situatia scolara a studentuluiPlanned
ADS-9190 — Duplicate Scholarships menu selector matches Allocated Scholarships and Financial SituationAdded
ADS-9191 — [Prod][TUIASI][uni-api] Discipline name edit fails when translation replacement deletes a referenced localizationAdded
ADS-9221 — [Cazari-rapoarte] - Formatare eronată în descriere pe Fișa StudentuluiAdded
ADS-9247 — [Cazari] - eroare la afisare cameraAdded

Carry overs / not delivered (13)

Jira itemWhy it carried
ADS-8164 — Story — [Burse] - US6 - RapoartePartial completion
ADS-8543 — Story — Flux alocare automata burse de performantaLate start / sequencing
ADS-8584 — Improvement — [Asachi]-Adaugare ,,Status student" in Clasamentul studentilor din modulul Statistici si rapoarteNot started
ADS-8679 — Story — Refactor student, situatie scolaraPartial completion
ADS-8763 — Task — [Asachi][BE] Import studenti pentru anul universitar 2026-2027Dependency delay
ADS-8866 — Bug — [Asachi] - Problema echivalariNot started
ADS-8938 — Bug — [Asachi] - Problema echivalariNot started
ADS-8972 — Bug — [Asachi] - Problema incheiere media anuala masterPartial completion
ADS-8981 — Task — Sterge permisiunile vechi - scholarship allocationPartial completion
ADS-9032 — Bug — [Prod] - Eroare la emiterea adeverintei de absolvireBug / rework pressure
ADS-9166 — Bug — [TUIASI] Shared database write stall blocked SSO logins and report creation on Oct 12Not started
ADS-9203 — Bug — [UNMB] - Eroare la promovare studentiNot started
ADS-9205 — Task — [Petre Andrei] - Actualizare pondere din DBNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion4Carryovers blocked by partial completion
Dependency / competing work1Delivery slipped because attention or dependency landed elsewhere
Not started4Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

4 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list2020 issues in the planning snapshot
Sprint review / outcome snapshot raw list2929 issues in the Friday review snapshot
Normalized sprint fact base2828 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.