Sprint Pulse

Product Pulse — University ADS Q4 W43 - 26-30 Oct

Planned sprint ADS Q4 W43 - 26-30 Oct • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 16 of 29 visible items, including 3 Stories, 4 Tasks, and 8 Bugs. Product movement was real, but the sprint was still noisy: 3 items entered after planning and 0 of them were closed. The main misses were concentrated in 13 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items29Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items16Items whose final outcome bucket is Done
Carry overs13Items not closed at sprint review
Delivered mix3 / 4 / 8Stories / Tasks / Bugs delivered
Entry kind mix26 / 3 / 0Planned / Added during sprint / Stretch visible
Readiness mix9 / 17 / 3Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended4/5Progress items were expected not to finish in this sprint

Stories done (3)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-8164 — [Burse] - US6 - RapoartePlanned
ADS-8180 — [Registre Matricole] - US4 Download macheta RMUPlanned
ADS-9188 — Numele universitatii contine ghilimele in documentele decarcatePlanned

Tasks done (4)

Jira itemHow entered
ADS-8981 — Sterge permisiunile vechi - scholarship allocationPlanned
ADS-9051 — [ANMGD -CLUJ] - Actualizare script conform planului de invatamant transmisPlanned
ADS-9099 — [ANMGD -Cluj] - Creare ani pentru noi cohorte in planul de invatamantPlanned
ADS-9295 — [Asachi]: Suport actualizare status studentPlanned

Bugs done (8)

Jira itemHow entered
ADS-8535 — [Prod][AWS][University] Add discipline sends string for localized disciplineName - 12 HTTP 400s/72hPlanned
ADS-8800 — [Asachi] - Absent eronat pentru anul 2026-2027Planned
ADS-8818 — [Asachi] - Lipsa alocare studenti in sesiunea 2Planned
ADS-8866 — [Asachi] - Problema echivalariPlanned
ADS-8881 — [Asachi] - Eroare calculare creditePlanned
ADS-8883 — [Asachi] - Eroare asignare titular curs/aplicatii la disciplinaPlanned
ADS-8972 — [Asachi] - Problema incheiere media anuala masterPlanned
ADS-9331 — [Cazari] - Desincronizare numar studenti la afisarea ,,Cazati" fata de raportul ,,Situatii cazari pe camine".Planned

Carry overs / not delivered (13)

Jira itemWhy it carried
ADS-8543 — Story — Flux alocare automata burse de performantaDependency delay
ADS-8679 — Story — Refactor student, situatie scolaraPartial completion
ADS-8753 — Improvement — Calcul credite in functie de nr total credite la disciplinele impuseNot started
ADS-8763 — Task — [Asachi][BE] Import studenti pentru anul universitar 2026-2027Dependency delay
ADS-8944 — Story — Inchidere a tuturor cataloagelorPartial completion
ADS-9024 — Story — Cerinte CentralizatorBreakdown issue
ADS-9151 — Bug — [UNMB] - Afisare eronata in lista de dropdown la tipul si categoria studentului din modulul StudentiNot started
ADS-9212 — Bug — [ANMGD-CLUJ] - Eroare la import studentiNot started
ADS-9259 — Task — Download RM cu Observatii si SemnatariDependency delay
ADS-9315 — Bug — [Prod][TUIASI][rooms-api] Failing health probe restarts PHP-FPM and removes the only endpointDependency delay
ADS-9354 — Bug — [Prod] - Plan de invatamant - date lipsa la incarcare si discipline afisate in engleza la descarcareNot started
ADS-9375 — Bug — [Prod][TUIASI][uni-api] Role-cache update fails on null upstream roles after clearing cacheNot started
ADS-9396 — Story — Permisiune Alocari burse pe facultatea atribuitaNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion2Carryovers blocked by partial completion
Dependency / competing work4Delivery slipped because attention or dependency landed elsewhere
Not started5Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

4 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list2727 issues in the planning snapshot
Sprint review / outcome snapshot raw list3030 issues in the Friday review snapshot
Normalized sprint fact base2929 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.