Product Pulse — University ADS Q4 W44 - 02-06 Nov

Planned sprint ADS Q4 W44 - 02-06 Nov • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 14 of 25 visible items, including 3 Stories, 1 Tasks, and 9 Bugs. Product movement was real, but the sprint was still noisy: 6 items entered after planning and 4 of them were closed. The main misses were concentrated in 11 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items25Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items14Items whose final outcome bucket is Done
Carry overs11Items not closed at sprint review
Delivered mix3 / 1 / 9Stories / Tasks / Bugs delivered
Entry kind mix19 / 6 / 0Planned / Added during sprint / Stretch visible
Readiness mix11 / 13 / 1Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended3/4Progress items were expected not to finish in this sprint

Stories done (3)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-8180 — [Registre Matricole] - US4 Download macheta RMUPlanned
ADS-8944 — Inchidere a tuturor cataloagelorPlanned
ADS-9024 — Cerinte CentralizatorPlanned

Tasks done (1)

Jira itemHow entered
ADS-9481 — [Cazari] - Activare plati onlineAdded

Bugs done (9)

Jira itemHow entered
ADS-8818 — [Asachi] - Lipsa alocare studenti in sesiunea 2Planned
ADS-9151 — [UNMB] - Afisare eronata in lista de dropdown la tipul si categoria studentului din modulul StudentiPlanned
ADS-9212 — [ANMGD-CLUJ] - Eroare la import studentiPlanned
ADS-9354 — [Prod] - Plan de invatamant - date lipsa la incarcare si discipline afisate in engleza la descarcarePlanned
ADS-9375 — [Prod][TUIASI][uni-api] Role-cache update fails on null upstream roles after clearing cachePlanned
ADS-9426 — [Cazari] - eroare la trimitere obligatii de plata studentilorPlanned
ADS-9467 — [Cazari] - Actualizare informatii student Gerges Mahfouz Abdelmasih BebawyAdded
ADS-9474 — [Cazari] - Corectare numar zile la transfer in obligatie de plata a studentuluiAdded
ADS-9476 — [Cazari] - Desincronizare la obligatiile de plata emise si netrimise pentru luna noiembrie vs cazatiAdded

Carry overs / not delivered (11)

Jira itemWhy it carried
ADS-7560 — Story — Examinari studentiPartial completion
ADS-8543 — Story — Flux alocare automata burse de performantaDependency delay
ADS-8679 — Story — Refactor student, situatie scolaraDependency delay
ADS-9187 — Story — Adauga forme de finantarePartial completion
ADS-9259 — Task — Download RM cu Observatii si SemnatariDependency delay
ADS-9315 — Bug — [Prod][TUIASI][rooms-api] Failing health probe restarts PHP-FPM and removes the only endpointPartial completion
ADS-9384 — Story — Adauga view IBAN pt studenti in modulul de burseDependency delay
ADS-9396 — Story — Permisiune Alocari burse pe facultatea atribuitaDependency delay
ADS-9410 — Bug — [Prod][TUIASI] Eight deployments simultaneously lose all available replicasNot started
ADS-9438 — Bug — [Prod][AWS][University] Academic-plan discipline deletion is blocked by owned attribute rowsNot started
ADS-9505 — Bug — [Prod][TUIASI][University] Student-data export returns 400 when uaID is missing from the query projectionPartial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion3Carryovers blocked by partial completion
Dependency / competing work5Delivery slipped because attention or dependency landed elsewhere
Not started1Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

3 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1919 issues in the planning snapshot
Sprint review / outcome snapshot raw list2525 issues in the Friday review snapshot
Normalized sprint fact base2525 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.