Product Pulse — University ADS Q4 W45 - 09-13 Nov

Planned sprint ADS Q4 W45 - 09-13 Nov • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 8 of 20 visible items, including 1 Stories, 1 Tasks, and 6 Bugs. Product movement was real, but the sprint was still noisy: 6 items entered after planning and 5 of them were closed. The main misses were concentrated in 12 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items20Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items8Items whose final outcome bucket is Done
Carry overs12Items not closed at sprint review
Delivered mix1 / 1 / 6Stories / Tasks / Bugs delivered
Entry kind mix14 / 6 / 0Planned / Added during sprint / Stretch visible
Readiness mix7 / 12 / 1Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended4/4Progress items were expected not to finish in this sprint

Stories done (1)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-9545 — Improvement Borderou incasariAdded

Tasks done (1)

Jira itemHow entered
ADS-8763 — [Asachi][BE] Import studenti pentru anul universitar 2026-2027Added

Bugs done (6)

Jira itemHow entered
ADS-9035 — [Asachi] - Eroare echivalare disciplinaPlanned
ADS-9315 — [Prod][TUIASI][rooms-api] Failing health probe restarts PHP-FPM and removes the only endpointPlanned
ADS-9522 — [Prod][AWS][University] Student studies return HTTP 500 when academic credit columns are missingPlanned
ADS-9558 — [Prod][TUIASI][Accommodations] Student invoice list returns 500 when UNI profile connection is refusedAdded
ADS-9561 — [Asachi] - Eroare la inchiderea cataloagelor in calitate de secretarAdded
ADS-9586 — [Asachi] - Studentul nu isi vede obligatia de plata din contul lui desi este emisa si neachitataAdded

Carry overs / not delivered (12)

Jira itemWhy it carried
ADS-7560 — Story — Examinari studentiPartial completion
ADS-8543 — Story — Flux alocare automata burse de performantaDependency delay
ADS-8679 — Story — Refactor student, situatie scolaraDependency delay
ADS-8840 — Bug — [Asachi] - Probleme titular curs sectiunea de "Restantieri"Partial completion
ADS-9187 — Story — Adauga forme de finantarePartial completion
ADS-9233 — Story — Imbunatatire proces echivalarePartial completion
ADS-9259 — Task — Download RM cu Observatii si SemnatariDependency delay
ADS-9384 — Story — Adauga view IBAN pt studenti in modulul de burseDependency delay
ADS-9396 — Story — Permisiune Alocari burse pe facultatea atribuitaDependency delay
ADS-9410 — Bug — [Prod][TUIASI] Eight deployments simultaneously lose all available replicasNot started
ADS-9438 — Bug — [Prod][AWS][University] Academic-plan discipline deletion is blocked by owned attribute rowsPartial completion
ADS-9540 — Bug — [Petre Andrei] - Eroare la sincronizarea codurilor de acces dupa importul fisierului cu studenti studentiNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion5Carryovers blocked by partial completion
Dependency / competing work5Delivery slipped because attention or dependency landed elsewhere
Not started1Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

4 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1515 issues in the planning snapshot
Sprint review / outcome snapshot raw list2323 issues in the Friday review snapshot
Normalized sprint fact base2020 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.