Trend View

Sprint Trends — Org Adservio

Aggregated source-backed sprint trend view

Adservio trend points come from persisted source-pair metrics and the published pulse archive. The dashboard is designed to show miss patterns and execution quality, not just output volume.

Overview

Adservio now has 12 source-backed checkpoint(s) in the persisted trend store.

These cards bias toward leadership questions: can we trust the promise set, what diluted it, and what actually came out of the sprint system.

Committed completion
37.3%
9.8 pts down vs prior checkpoint
Planning quality
28.0%
Improved by 0.9 pts vs prior checkpoint
Added load
82.7%
Worse by 11.0 pts vs prior checkpoint
Workflow mismatch
0
Improved by 18 vs prior checkpoint
Bug share
59.6%
Worse by 9.6 pts vs prior checkpoint
Product stories
9
1 down vs prior checkpoint

Historical checkpoints were reconstructed from their published pulse metric tables; frozen source-pair rows remain authoritative whenever both are available.

Trend explorer

Choose a consecutive week window to inspect how the delivery system changed over time for this scope.

Select a consecutive window to reslice the same persisted trend facts.
Delivery predictability
Committed completion, finish predictability, and planning quality should move together if the sprint system is healthy.
Committed completionFinish predictabilityPlanning quality
0%25%50%75%100%W11-12W14W18W19W20W21W22W23W24W25W26W27
Percentage scale, higher is better.
Scope pressure
Carryover, added load, and bug share show how much execution was displaced by noise or late scope motion.
Committed carryoverAdded loadBug share
0%25%50%75%100%W11-12W14W18W19W20W21W22W23W24W25W26W27
Percentage scale, lower is better.
Delivered mix
Stories, tasks, and bugs should stay legible enough that leaders can see where capacity actually landed.
StoriesTasksBugs
037101415736173749395336444844W11-12W14W18W19W20W21W22W23W24W25W26W27
Stacked counts by checkpoint.
Miss pattern
Partial completion, dependency delay, and not-started misses help distinguish breakdown, coordination, and focus failure.
PartialDependencyNot started
025811431963336422939412841W11-12W14W18W19W20W21W22W23W24W25W26W27
Stacked miss counts by checkpoint.
Execution truth
Workflow mismatches, not-started committed items, and delivered product stories show whether the sprint closed cleanly and usefully.
Workflow mismatchNot-started committedProduct stories
01357W11-12W14W18W19W20W21W22W23W24W25W26W27
Grouped counts by checkpoint.

Predictability

MetricW11-12W14W18W19W20W21W22W23W24W25W26W27
Committed completion55.6%63.6%43.6%25.8%43.3%37.8%38.8%42.4%25.0%37.4%47.1%37.3%
Finish predictability71.4%63.6%46.2%28.3%45.6%40.3%40.3%42.4%26.7%40.0%50.0%40.4%
Planning quality100.0%0.0%45.5%46.8%44.8%45.1%48.8%34.8%37.5%20.9%27.1%28.0%
Committed carryover44.4%36.4%56.4%74.2%56.7%62.2%61.3%57.6%75.0%62.6%52.9%62.7%
Added load31.6%8.3%41.6%61.4%63.7%68.1%22.3%44.7%42.3%50.9%71.7%82.7%
Bug share40.0%57.1%43.6%36.8%48.7%63.5%48.9%51.7%46.5%56.2%50.0%59.6%

Delivery and misses

MetricW11-12W14W18W19W20W21W22W23W24W25W26W27
Stories50461027978109
Tasks43154814101499117
Bugs641771933223020272728
Partial227412141261415911
Dependency111035533245
Not started101121817252022241525
Workflow mismatch2043515624180
Not-started committed101121817252022241525
Product stories50461027978109