Adservio trend points are generated from persisted sprint issue facts and centralized formulas. The dashboard is designed to show miss patterns and execution quality, not just output volume.

Overview

Adservio now has 5 source-backed checkpoint(s) in the persisted trend store.

These cards bias toward leadership questions: can we trust the promise set, what diluted it, and what actually came out of the sprint system.

Committed completion
33.3%
13.4 pts down vs prior checkpoint
Planning quality
31.0%
4.0 pts down vs prior checkpoint
Added load
30.0%
Worse by 15.7 pts vs prior checkpoint
Workflow mismatch
0
Improved by 2 vs prior checkpoint
Bug share
64.3%
Worse by 26.1 pts vs prior checkpoint
Product stories
6
5 down vs prior checkpoint

Trend explorer

Choose a consecutive week window to inspect how the delivery system changed over time for this scope.

Select a consecutive window to reslice the same persisted trend facts.
Delivery predictability
Committed completion, finish predictability, and planning quality should move together if the sprint system is healthy.
Committed completionFinish predictabilityPlanning quality
0%25%50%75%100%W11-12W14W29W29W30
Percentage scale, higher is better.
Scope pressure
Carryover, added load, and bug share show how much execution was displaced by noise or late scope motion.
Planning-baseline carryoverFinish-intent carryoverAdded loadBug share
0%25%50%75%100%W11-12W14W29W29W30
Percentage scale, lower is better.
Delivered mix
Stories, tasks, and bugs should stay legible enough that leaders can see where capacity actually landed.
StoriesTasksBugs
02468157293127W11-12W14W29W29W30
Stacked counts by checkpoint.
Miss pattern
Partial completion, dependency delay, and not-started misses help distinguish breakdown, coordination, and focus failure.
PartialDependencyNot started
0135743272526W11-12W14W29W29W30
Stacked miss counts by checkpoint.
Execution truth
Workflow mismatches, not-started committed items, and delivered product stories show whether the sprint closed cleanly and usefully.
Workflow mismatchNot-started committedProduct stories
01234W11-12W14W29W29W30
Grouped counts by checkpoint.

Predictability

MetricW11-12W14W29W29W30
Committed completion55.6%63.6%46.7%46.7%33.3%
Finish predictability71.4%63.6%53.5%53.5%44.8%
Planning quality100.0%0.0%35.0%35.0%31.0%
Planning-baseline carryover44.4%36.4%53.3%53.3%66.7%
Finish-intent carryover0.0%0.0%46.5%46.5%55.2%
Added load31.6%8.3%14.3%14.3%30.0%
Bug share40.0%57.1%38.2%38.2%64.3%

Delivery and misses

MetricW11-12W14W29W29W30
Stories5011116
Tasks43773
Bugs64131318
Partial22141419
Dependency11113
Not started1010104
Workflow mismatch20220
Not-started committed1010104
Product stories5011116