Trend View

Sprint Trends — Team Team 1

Finalized-registry view of predictability, throughput, misses, and quality signals

Team 1 trend points are generated from persisted sprint issue facts and centralized formulas. The dashboard is designed to show miss patterns and execution quality, not just output volume. Every persisted point was rebuilt from the current validated revision in the finalized sprint registry.

Overview

Team 1 now has 12 source-backed checkpoint(s) in the persisted trend store.

These cards bias toward leadership questions: can we trust the promise set, what diluted it, and what actually came out of the sprint system.

Committed completion
50.0%
9.1 pts down vs prior checkpoint
Planning quality
50.0%
Improved by 22.7 pts vs prior checkpoint
Added load
25.9%
Improved by 0.8 pts vs prior checkpoint
Workflow mismatch
1
Improved by 3 vs prior checkpoint
Bug share
75.0%
Worse by 16.2 pts vs prior checkpoint
Product stories
1
Flat vs prior checkpoint

Trend explorer

Choose a consecutive week window to inspect how the delivery system changed over time for this scope.

Select a consecutive window to reslice the same persisted trend facts.
Delivery predictability
Committed completion, finish predictability, and planning quality should move together if the sprint system is healthy.
Committed completionFinish predictabilityPlanning quality
0%25%50%75%100%W30W31W32W33W34W35W36W37W38W39W40W41
Percentage scale, higher is better.
Scope pressure
Carryover, added load, and bug share show how much execution was displaced by noise or late scope motion.
Committed carryoverAdded loadBug share
0%25%50%75%100%W30W31W32W33W34W35W36W37W38W39W40W41
Percentage scale, lower is better.
Delivered mix
Stories, tasks, and bugs should stay legible enough that leaders can see where capacity actually landed.
StoriesTasksBugs
012341112431211131415161616W30W31W32W33W34W35W36W37W38W39W40W41
Stacked counts by checkpoint.
Miss pattern
Partial completion, dependency delay, and not-started misses help distinguish breakdown, coordination, and focus failure.
PartialDependencyNot started
012358561481019141013810W30W31W32W33W34W35W36W37W38W39W40W41
Stacked miss counts by checkpoint.
Execution truth
Workflow mismatches, not-started committed items, and delivered product stories show whether the sprint closed cleanly and usefully.
Workflow mismatchNot-started committedProduct stories
01234W30W31W32W33W34W35W36W37W38W39W40W41
Grouped counts by checkpoint.

Predictability

MetricW30W31W32W33W34W35W36W37W38W39W40W41
Committed completion30.8%61.5%33.3%12.5%50.0%31.2%25.9%33.3%50.0%43.5%59.1%50.0%
Finish predictability33.3%50.0%33.3%8.3%55.6%28.6%30.4%31.6%56.2%38.5%60.0%52.9%
Planning quality15.4%23.1%100.0%62.5%50.0%25.0%37.0%47.6%35.0%26.1%27.3%50.0%
Committed carryover69.2%38.5%66.7%87.5%50.0%68.8%74.1%66.7%50.0%56.5%40.9%50.0%
Added load50.0%40.9%25.0%27.3%40.0%46.7%32.4%38.2%39.4%37.8%26.7%25.9%
Bug share41.7%46.2%40.0%66.7%64.3%54.5%73.3%53.3%29.4%57.9%58.8%75.0%

Delivery and misses

MetricW30W31W32W33W34W35W36W37W38W39W40W41
Stories430124010011
Tasks2320112510553
Bugs5622961185111012
Partial442731499946
Dependency000013000011
Not started4147461551433
Workflow mismatch200000200141
Not-started committed4147461551433
Product stories430124010011