Trend View

Sprint Trends — Team Team 2

Finalized-registry view of predictability, throughput, misses, and quality signals

Team 2 trend points are generated from persisted sprint issue facts and centralized formulas. The dashboard is designed to show miss patterns and execution quality, not just output volume. Every persisted point was rebuilt from the current validated revision in the finalized sprint registry.

Overview

Team 2 now has 13 source-backed checkpoint(s) in the persisted trend store.

These cards bias toward leadership questions: can we trust the promise set, what diluted it, and what actually came out of the sprint system.

Committed completion
40.0%
Improved by 6.7 pts vs prior checkpoint
Planning quality
50.0%
Improved by 25.0 pts vs prior checkpoint
Added load
28.6%
Improved by 4.7 pts vs prior checkpoint
Workflow mismatch
0
Improved by 3 vs prior checkpoint
Bug share
0.0%
Improved by 33.3 pts vs prior checkpoint
Product stories
1
Flat vs prior checkpoint

Trend explorer

Choose a consecutive week window to inspect how the delivery system changed over time for this scope.

Select a consecutive window to reslice the same persisted trend facts.
Delivery predictability
Committed completion, finish predictability, and planning quality should move together if the sprint system is healthy.
Committed completionFinish predictabilityPlanning quality
0%25%50%75%100%W30W31W32W33W34W35W36W37W38W39W40W41W42
Percentage scale, higher is better.
Scope pressure
Carryover, added load, and bug share show how much execution was displaced by noise or late scope motion.
Committed carryoverAdded loadBug share
0%25%50%75%100%W30W31W32W33W34W35W36W37W38W39W40W41W42
Percentage scale, lower is better.
Delivered mix
Stories, tasks, and bugs should stay legible enough that leaders can see where capacity actually landed.
StoriesTasksBugs
01234414456758101474W30W31W32W33W34W35W36W37W38W39W40W41W42
Stacked counts by checkpoint.
Miss pattern
Partial completion, dependency delay, and not-started misses help distinguish breakdown, coordination, and focus failure.
PartialDependencyNot started
012343591271111131013766W30W31W32W33W34W35W36W37W38W39W40W41W42
Stacked miss counts by checkpoint.
Execution truth
Workflow mismatches, not-started committed items, and delivered product stories show whether the sprint closed cleanly and usefully.
Workflow mismatchNot-started committedProduct stories
01234W30W31W32W33W34W35W36W37W38W39W40W41W42
Grouped counts by checkpoint.

Predictability

MetricW30W31W32W33W34W35W36W37W38W39W40W41W42
Committed completion25.0%16.7%25.0%25.0%33.3%26.7%21.4%23.5%33.3%33.3%57.9%33.3%40.0%
Finish predictability50.0%50.0%37.5%30.8%40.0%27.3%30.0%33.3%38.5%38.9%57.1%44.4%50.0%
Planning quality25.0%33.3%41.7%56.2%46.7%60.0%57.1%52.9%60.0%33.3%26.3%25.0%50.0%
Committed carryover75.0%83.3%75.0%75.0%66.7%73.3%78.6%76.5%66.7%66.7%42.1%66.7%60.0%
Added load42.9%0.0%28.6%5.9%16.7%11.8%30.0%19.0%37.5%27.6%27.3%33.3%28.6%
Bug share75.0%0.0%25.0%25.0%20.0%50.0%71.4%33.3%50.0%70.0%21.4%33.3%0.0%

Delivery and misses

MetricW30W31W32W33W34W35W36W37W38W39W40W41W42
Stories0120131020411
Tasks1013301323733
Bugs3011135247330
Partial3488276887344
Dependency0000201100200
Not started0114344426222
Workflow mismatch0000000000030
Not-started committed0114344426222
Product stories0120131020411