Executive summary

Yellow. The sprint closed 48/112 visible items. The org roll-up absorbed noise reasonably well — 14/27 added items were closed — but finish predictability was only 43.2% (32/74), and bugs made up 56.2% of completed items. Planning-baseline carryover includes 42 finish misses and 6 expected progress continuations.

Top-line metrics

MetricValueHow to read it
Committed completion40.0% (34/85)Planned items marked Done ÷ all planned committed items
Planning-baseline carryover60.0% (51/85)All planned items not Done, including expected Progress continuations
Finish-intent carryover56.8% (42/74)Finish-intent planned items not Done ÷ all finish-intent planned items
Finish predictability43.2% (32/74)Finish-intent planned items done ÷ all finish-intent planned items
Progress predictability75.0% (6/8)Progress items that behaved as intended by carrying
Added-during-sprint load24.1% (27/112)Outcome-only items ÷ all visible items
Added work closure14/27All added items marked Done
Reactive load (bug share)56.2% (27/48)Completed bugs ÷ all completed work
Planning quality22.4% (19/85)Committed items marked Ready ÷ all committed items
Workflow-truth mismatches4Items marked Done in review while workflow status remained non-final

Engineering readout

Across included teams, the sprint did not fail; it traded predictability for responsiveness. 14/27 added items were closed, but that responsiveness came with 56.2% bug share and diluted finish predictability.

The miss pattern is concentrated: 15 partial-completion carryovers, 2 dependency-driven misses, and 21 planning-baseline items that never really started.

Most misses were not caused by poor readiness. 13 of the 51 planning-baseline carryovers had been marked Ready, so the stronger hypothesis is breakdown, sequencing, and capacity protection rather than simple scoping immaturity.

Delivered work mix

TypePlannedAddedStretchUnclearTotal doneDone %
Story7100816.7%
Task7200918.8%
Bug189002756.2%

Planning baseline: plan vs execution

SignalValueWhy it matters
Planning-baseline items85Items present in the frozen planning snapshot
Planning-baseline done34Closed by sprint review
Planning-baseline carryover51All planned items still open, including Progress continuation
Finish-intent carryover42Planned-to-finish items that did not finish
Progress continuation6Progress-intent planned items still open as expected
Planning-baseline items marked Ready19Planning-quality input
Carryovers marked Ready13Ready did not guarantee closure
Carryovers not started21Execution focus gap
Carryovers started but unfinished17Work moved, but did not close

Carryover pattern

Jira itemOwnerIntentStatusWhy it carried
ADS-406 — Bug — [Files] Missing description in ‘’Istoric’ when sharing documentsPetronel PavelFinishTo DoNot started
ADS-4341 — Bug — [Condica de prezenta] - Nu apare butonul ,, semneaza condica pentru toata ziuaLuiza HorlescuFinishTo DoNot started
ADS-4439 — Bug — [Teste si chestionare] - Numarul de destinatari care se afiseaza nu corespunde cu numarul real de destinatariMarian AndreiFinishTo DoNot started
ADS-4857 — Bug — [Mesagerie] - Restricționarea mesajelor de grup, conform configurărilor setatePetronel PavelFinishTo DoNot started
ADS-5722 — Bug — [BE/FE] Modal adauga noteAndrei DraganFinishIn ProgressNot started
ADS-5737 — Bug — [MOB][Photo] - Nu functioneaza filtrele de ani si de albumeStefan AgrigoroaeiFinishTo DoNot started
ADS-5784 — Story — [FE/BE] Refactor pagina de permisiuniPetronel PavelFinishTo Do
ADS-5808 — Bug — [MOB][Wellbeing] - Parintele nu poate vizualiza testele de autocunoastere pe mobAntoci RazvanFinishTo DoNot started
ADS-5919 — Bug — [Fotografii] - Distribuirea nu este afișată exclusiv pe clasele sau grupele configurate în modulul ClasePetronel PavelFinishTo DoNot started
ADS-6201 — Story — Log formatting - node.js, subscriptionsDragoș IvanStretch / OptionalTo DoPartial completion
ADS-6494 — Story — Log levels & Log formatsCojan Paul-CatalinFinishDone
ADS-6638 — Story — [Preferinte][Notificari] Refactor pagina de gestionare notificăriPetronel PavelProgressIn ProgressPartial completion
ADS-6698 — Bug — [FE/BE] Restrictie vizualizare fise scolareMarian AndreiFinishTo DoNot started
ADS-6712 — Task — [Note/absențe] - Recuperare informațiiMarian AndreiFinishTo DoNot started
ADS-6980 — Story — Tracing & Error LoggingDragoș IvanStretch / OptionalTo DoPartial completion
ADS-6990 — Bug — [MOB] - Mesaj gresit la stergerea unei note mai vechi de 24 orestefan musatFinishTo Do
ADS-7141 — Story — [Mob] - Redesign dashboard profesorStefan AgrigoroaeiFinishDoneBug / rework pressure
ADS-7266 — Task — [Portofoliu][Profesor] - Actualizare sectiuniPetronel PavelFinishIn ProgressPartial completion
ADS-7305 — Task — [REQ] - Remote Session Termination for UsersAndrei DraganFinishTo Do
ADS-7389 — Bug — AdservioAPI.php: svcAuth self-call failures turn web API endpoints into HTTP 500 - 20 hits/FridayIonut CiolanFinishTo DoNot started
ADS-7390 — Bug — rooms-api: room search endpoint returns HTTP 500 - 3 hits/FridayIonut CiolanFinishTo DoNot started
ADS-7419 — Bug — [SUBSCRIPTIONS] - Bug-uriEdgar AlexaFinishTo DoNot started
ADS-7430 — Story — [Admitere v2][Taxe] - 5. Export platile candidatului&extinderea cu alte informatii ale candidatilorGeorge MurgociFinishTo DoNot started
ADS-7474 — Task — [FE] - Optimizare viteză de încărcare paginiDragoș IvanProgressIn ProgressPartial completion
ADS-7484 — Bug — Session.php: session_start() fails reading session data during teacher class-book requests - 26 errors/24hMarian AndreiFinishTo DoNot started
ADS-7495 — Story — [FE/BE][Adeverinte absolvire] - Creare Probe evaluareIonut CiolanFinishCode ReviewPartial completion
ADS-7496 — Story — [FE/BE][Adeverinte absolvire] - Probe&medie pe situatie scolaraIonut CiolanFinishCode ReviewPartial completion
ADS-7534 — Story — [FE/BE][Adeverinte absolvire] - Flow generare adeverinteCristina CondreaProgressIn ProgressPartial completion
ADS-7575 — Bug — M_export.php / Export.php: student export references missing second-semester average column and returns HTTP 500 on /ro/secretary/export/elevi - 16 hits/24hMarian AndreiFinishIn ProgressPartial completion
ADS-7642 — Story — DSS Romania + Creeaza institutii updatesCosmin OlaruProgressIn Progress
ADS-7653 — Bug — Clase_profesori.php / M_cmc.php: teacher-class assignment insert fails FK constraint in cat_cadre2materii2clase - 2 errors/24hMarian AndreiFinishTo DoNot started
ADS-7666 — Bug — accommodations-api: shared HTTP 500 burst on POST /api/v2/accommodations/dorms/list and related endpoints - 16 hits/20mIonut CiolanFinishTo DoBug / rework pressure
ADS-7732 — Bug — TUIASI M_fisiere.php: file list query expects fsScimCeacSyncFsID missing from on-prem schema and breaks document listings - 12 errors/24hMarian AndreiFinishTo DoNot started
ADS-7746 — Bug — Fill.php / FormResultAnswerTable.php: questionnaire save fails when fraAnswer contains unsupported 4-byte emoji - 43 errors/72hMarian AndreiFinishTo DoDependency delay
ADS-7803 — Task — [SPIKE][FE] - TitulaturaIvan IoanaFinishTo DoNot started
ADS-7807 — Story — [MOB] - Notificări modul admitereStefan AgrigoroaeiFinishReady for testing
ADS-7831 — Story — [Spike] - Mobile app cold startstefan musatStretch / OptionalTo Do
ADS-7852 — Task — [BE]: Dezactivare actiuni noteaza (si bulk) daca media anuala si/sau media semestriala este incheiataCosmin OlaruFinishTesting
ADS-7880 — Bug — TUIASI uni-api: catalog import and adjacent grades endpoints return HTTP 500 - 23 hits/72handrei.alexandruFinishIn Progress
ADS-7890 — Story — [BE PHP][Cazari] - Stingerea obligatiilor din E-taxeIonut CiolanFinishIn ProgressDependency delay
ADS-7896 — Story — Migrare documente S3Cojan Paul-CatalinFinishMergedPartial completion
ADS-7904 — Bug — [BE] - Elev cu situatie scolara neincheiata apare in topul elevilor cu media 9,50,premiantaAndrei DraganFinishIn ProgressPartial completion
ADS-7907 — Task — [BE] Refactoring SQL_CALC_FOUND_ROWSMarian AndreiProgressReady for testingPartial completion
ADS-7908 — Bug — [Prod][AWS][legacy-web] Auth recaptcha helper dereferences null verification responseDaniel OnisoruFinishTo DoNot started
ADS-7910 — Bug — [Prod][TUIASI][uni-api] DB pool exhaustion breaks academic-years, faculty, and grade-save flowsandrei.alexandruFinishIn Progress
ADS-7952 — Story — [Persoana] - Implementare mecanism Atributeandrei.alexandruProgressIn ProgressPartial completion
ADS-7962 — Story — [MOB] Translate app in Frenchstefan musatProgressTesting
ADS-7976 — Story — [MOB] BFF - newsfeedstefan musatFinishTo DoPartial completion
ADS-7981 — Bug — Notificările nu se trimit pe AdmitereGeorge MurgociFinishIn ProgressPartial completion
ADS-7989 — Bug — [BE] - Job zilnic - publicare rezultate chestionareMarian AndreiFinishTo DoNot started
ADS-8000 — Task — [UNI][Denumire disciplina] Refactor atribut Denumire disciplina - locVirlan Francisc-GabrielFinishTo DoNot started

Miss pattern summary

PatternCountWhat it suggests
Partial completion15Breakdown / sizing / stage-gating was not tight enough
Dependency delay2Capacity protection or dependency timing created slip
Not started21A committed item remained outside execution focus
In Progress / Code Review carryovers17Most misses were moving, but not closing

Workflow-truth mismatches

Items marked Done in the sprint-review field while Jira workflow status was still non-final.

Jira itemStatusIntent
ADS-7574 — [UPG/ASachi] - Calculul mediilor la nivel de grupa/serieTestingProgress
ADS-7748 — Fisiere.php: POST /api/v2/fisiere/upload reuses non-unique thumb_/resized_ temp paths and races same-name image uploads - 9 warnings+errors/72hCode ReviewFinish
ADS-8010 — [BE] -Pe disciplina s-au modificat procenteleReady to merge
ADS-8019 — [BE-JAVA] -Nu mai sunt afisate notele la laborator si seminar pe anumite disciplineReady to merge

Executive follow-up questions

QuestionWhy this mattersWhat evidence to ask for
Why did finish-intent items carry over despite planning readiness?This tests execution quality rather than just scope quality.Show finish-intent carryovers split by dependency, partial completion, and not-started.
Are Progress items being managed intentionally?Progress items are allowed to continue, but the continuation should be visible and controlled.Show the original slice and the specific landing expectation for each item.
Is added work a healthy responsiveness level or chronic interruption?High responsiveness can hide systemic instability and diluted predictability.Show which added items were urgent/reactive versus discretionary scope change.
Can we trust Done in review when workflow is still non-final?Workflow-truth gaps reduce trust and make completion easy to game.Show the exact mismatches and the completion rule to enforce next sprint.

Included teams in this org pulse: Mobile, Team 1, Team 2, University.

Usage note: start with the top-line metrics, then use the traceability links to answer these questions with issue-level evidence.

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list88Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list116Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base112Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline85Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot112Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review85planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning27planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review0planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows4Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Committed completion40.0% (34/85)planned committed items marked Done ÷ all planned committed items34/85Open denominator JQL
Planning-baseline carryover60.0% (51/85)planned baseline items not Done at review ÷ all planned baseline items51/85Open denominator JQL
Finish-intent carryover56.8% (42/74)finish-intent planned items not Done at review ÷ all finish-intent planned items42/74Open denominator JQL
Finish predictability43.2% (32/74)finish-intent committed items marked Done ÷ all finish-intent committed items32/74Open denominator JQL
Progress predictability75.0% (6/8)progress-intent items that carried as intended ÷ all progress-intent committed items6/8Open denominator JQL
Added-during-sprint load24.1% (27/112)visible items absent from planning and present in review ÷ all visible sprint items27/112Open denominator JQL
Added work closure14/27added visible items marked Done ÷ all added visible items14/27Open denominator JQL
Planning quality22.4% (19/85)committed items marked Ready in planning snapshot ÷ all committed items19/85Open denominator JQL
Carryovers marked Ready25.5% (13/51)carryovers that were marked Ready in planning snapshot ÷ all carryovers13/51Open denominator JQL
Reactive load56.2% (27/48)completed bugs ÷ all completed work27/48Open denominator JQL
Workflow-truth mismatches4Done rows with non-final workflow status4/48Open denominator JQL

Planning-baseline carryover includes both finish-intent misses and expected Progress continuations. Use Finish-intent carryover when you want only planned-to-finish items that did not finish.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

These companion artifacts keep the pulse debuggable when a leader wants the exact rows behind a metric or a count.