Sprint Pulse

Engineering Pulse — Team 1 ADS Q2 W22 - 01-05 Iunie

Planned sprint ADS Q2 W22 - 01-05 Iunie • planning snapshot + end-of-sprint outcome snapshot

This version uses the planning snapshot as the promise set and the outcome snapshot as the result set. Count metrics link to snapshot-exact JQL result pages. Jira IDs in the report link to live Jira issues.

Download DOCX

Executive summary

Yellow. The sprint closed 31/64 visible items. The team absorbed noise well — 11/15 added items were closed — but finish predictability was only 42.2% (19/45), and bugs made up 54.8% of completed items. Planning-baseline carryover includes 26 finish misses and 3 expected progress continuations.

Top-line metrics

MetricValueHow to read it
Committed completion40.8% (20/49)Planned items marked Done ÷ all planned committed items
Planning-baseline carryover59.2% (29/49)All planned items not Done, including expected Progress continuations
Finish-intent carryover57.8% (26/45)Finish-intent planned items not Done ÷ all finish-intent planned items
Finish predictability42.2% (19/45)Finish-intent planned items done ÷ all finish-intent planned items
Progress predictability100.0% (3/3)Progress items that behaved as intended by carrying
Added-during-sprint load23.4% (15/64)Outcome-only items ÷ all visible items
Added work closure11/15All added items marked Done
Reactive load (bug share)54.8% (17/31)Completed bugs ÷ all completed work
Planning quality51.0% (25/49)Committed items marked Ready ÷ all committed items
Workflow-truth mismatches3Items marked Done in review while workflow status remained non-final

Engineering readout

The sprint did not fail; it traded predictability for responsiveness. 11/15 added items were closed, but that responsiveness came with 54.8% bug share and diluted finish predictability.

The miss pattern is concentrated: 5 partial-completion carryovers, 1 dependency-driven misses, and 20 planning-baseline items that never really started.

Most misses were not caused by poor readiness. 10 of the 29 planning-baseline carryovers had been marked Ready, so the stronger hypothesis is breakdown, sequencing, and capacity protection rather than simple scoping immaturity.

Delivered work mix

TypePlannedAddedStretchUnclearTotal doneDone %
Story110026.5%
Task3210619.4%
Bug107001754.8%

Planning baseline: plan vs execution

SignalValueWhy it matters
Planning-baseline items49Items present in the frozen planning snapshot
Planning-baseline done20Closed by sprint review
Planning-baseline carryover29All planned items still open, including Progress continuation
Finish-intent carryover26Planned-to-finish items that did not finish
Progress continuation3Progress-intent planned items still open as expected
Planning-baseline items marked Ready25Planning-quality input
Carryovers marked Ready10Ready did not guarantee closure
Carryovers not started20Execution focus gap
Carryovers started but unfinished3Work moved, but did not close

Carryover pattern

Jira itemOwnerIntentStatusWhy it carried
ADS-2564 — Story — [School managment/Teachers] - Modules to be tested until the end of the school yearCosmin OlaruProgressTo DoDependency delay
ADS-406 — Bug — [Files] Missing description in ‘’Istoric’ when sharing documentsAntoci RazvanFinishTo DoNot started
ADS-4341 — Bug — [Condica de prezenta] - Nu apare butonul ,, semneaza condica pentru toata ziuaVlad LihaceanuFinishTo DoNot started
ADS-4439 — Bug — [Teste si chestionare] - Numarul de destinatari care se afiseaza nu corespunde cu numarul real de destinatariMarian AndreiFinishTo DoNot started
ADS-4857 — Bug — [Mesagerie] - Restricționarea mesajelor de grup, conform configurărilor setatePetronel PavelProgressIn ProgressPartial completion
ADS-5722 — Bug — [BE/FE] Modal adauga noteAndrei DraganFinishTo Do
ADS-5808 — Bug — [FE][Wellbeing] - Parintele nu poate vizualiza testele de autocunoastere pe mobAntoci RazvanFinishTo DoNot started
ADS-5919 — Bug — [Fotografii] - Distribuirea nu este afișată exclusiv pe clasele sau grupele configurate în modulul ClasePetronel PavelFinishTo DoNot started
ADS-6495 — Story — Service Internal APIIonut CiolanFinishDonePartial completion
ADS-6499 — Story — Implementat CRUD Etnii in LaravelIonut CiolanFinishDoneNot started
ADS-6501 — Story — Input validation errorsIonut CiolanFinishDonePartial completion
ADS-6545 — Story — Implementare v1 layer comunicare native-web *post message bridgeIvan IoanaFinishTo DoNot started
ADS-6562 — Story — Remove any mentions of Laravel in production modeIonut CiolanFinishDonePartial completion
ADS-6698 — Bug — [FE/BE] Restrictie vizualizare fise scolareMarian AndreiFinishTo DoNot started
ADS-6712 — Task — [Note/absențe] - Recuperare informațiiMarian AndreiFinishTo DoNot started
ADS-7009 — Task — Dezactivare actiuni noteaza/absenta (si bulk) daca media anuala si/sau media semestriala este incheiataIvan IoanaFinishTo DoNot started
ADS-7330 — Task — [BE] - Valoare implicita incorecta pentru tipul de calcul al mediei la adaugarea unei materii noiAndrei DraganFinishTo Do
ADS-7388 — Bug — docgen2-api: gradebook view/download endpoints return HTTP 500 - 15 hits/FridayIvan IoanaFinishMissing from outcome snapshot
ADS-7389 — Bug — AdservioAPI.php: svcAuth self-call failures turn web API endpoints into HTTP 500 - 20 hits/FridayIonut CiolanFinishTo DoNot started
ADS-7390 — Bug — rooms-api: room search endpoint returns HTTP 500 - 3 hits/FridayIonut CiolanFinishTo DoNot started
ADS-7448 — Bug — [BE] Grades.php: deleting a grade can deadlock on cat_note and return HTTP 500 - 8 hits/24hAndrei DraganFinishTo DoNot started
ADS-7451 — Bug — [BE] - Condica - Activitati duplicateIonut CiolanFinishIn ProgressPartial completion
ADS-7460 — Bug — Absences time interval export_xls returns HTTP 500 for inverted date range (6 errors/24h)Marian AndreiFinishTo DoNot started
ADS-7484 — Bug — Session.php: session_start() fails reading session data during teacher class-book requests - 26 errors/24hMarian AndreiFinishTo DoNot started
ADS-7575 — Bug — M_export.php / Export.php: student export references missing second-semester average column and returns HTTP 500 on /ro/secretary/export/elevi - 16 hits/24hMarian AndreiFinishTo DoNot started
ADS-760 — Bug — [Classes][LCY][WEB][FE/MOB] - Classroom - Unable to delete a document attached to a messageAntoci RazvanFinishTo DoNot started
ADS-7618 — Bug — [BE/FE] Chestionare - Descarcarea raspunsurilor individuale descarca mereu primul parinte din lista, iar status completare este gresitMarian AndreiFinishIn ProgressNot started
ADS-7654 — Bug — Grades.php / AverageCalculator: POST /api/v2/grades accepts grade but skips average recomputation - 2 errors/24hIonut CiolanFinishTo DoNot started
ADS-7724 — Task — [FR] Setare calcul medie - Standard RomaniaAndrei DraganProgressTo DoNot started

Miss pattern summary

PatternCountWhat it suggests
Partial completion5Breakdown / sizing / stage-gating was not tight enough
Dependency delay1Capacity protection or dependency timing created slip
Not started20A committed item remained outside execution focus
In Progress / Code Review carryovers3Most misses were moving, but not closing

Workflow-truth mismatches

Items marked Done in the sprint-review field while Jira workflow status was still non-final.

Jira itemStatusIntent
ADS-6360 — [Catalog PDF] - Număr indicatori incorect – SemestreReady for testingFinish
ADS-7786 — [Docgen] -Catalogul pe semestre nu afiseaza datele legate de situatia scolaraCode Review
ADS-7795 — [FE] - Examenul de specialitate nu e trecut complet cand e cu virgula in catalogul PDFCode Review

Executive follow-up questions

QuestionWhy this mattersWhat evidence to ask for
Why did finish-intent items carry over despite planning readiness?This tests execution quality rather than just scope quality.Show finish-intent carryovers split by dependency, partial completion, and not-started.
Are Progress items being managed intentionally?Progress items are allowed to continue, but the continuation should be visible and controlled.Show the original slice and the specific landing expectation for each item.
Is added work a healthy responsiveness level or chronic interruption?High responsiveness can hide systemic instability and diluted predictability.Show which added items were urgent/reactive versus discretionary scope change.
Can we trust Done in review when workflow is still non-final?Workflow-truth gaps reduce trust and make completion easy to game.Show the exact mismatches and the completion rule to enforce next sprint.

Usage note: start with the top-line metrics, then use the traceability links to answer these questions with issue-level evidence.

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list52Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list66Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base64Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline49Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot63Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review48planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning15planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review1planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows3Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Committed completion40.8% (20/49)planned committed items marked Done ÷ all planned committed items20/49Open denominator JQL
Planning-baseline carryover59.2% (29/49)planned baseline items not Done at review ÷ all planned baseline items29/49Open denominator JQL
Finish-intent carryover57.8% (26/45)finish-intent planned items not Done at review ÷ all finish-intent planned items26/45Open denominator JQL
Finish predictability42.2% (19/45)finish-intent committed items marked Done ÷ all finish-intent committed items19/45Open denominator JQL
Progress predictability100.0% (3/3)progress-intent items that carried as intended ÷ all progress-intent committed items3/3Open denominator JQL
Added-during-sprint load23.4% (15/64)visible items absent from planning and present in review ÷ all visible sprint items15/64Open denominator JQL
Added work closure11/15added visible items marked Done ÷ all added visible items11/15Open denominator JQL
Planning quality51.0% (25/49)committed items marked Ready in planning snapshot ÷ all committed items25/49Open denominator JQL
Carryovers marked Ready34.5% (10/29)carryovers that were marked Ready in planning snapshot ÷ all carryovers10/29Open denominator JQL
Reactive load54.8% (17/31)completed bugs ÷ all completed work17/31Open denominator JQL
Workflow-truth mismatches3Done rows with non-final workflow status3/31Open denominator JQL

Planning-baseline carryover includes both finish-intent misses and expected Progress continuations. Use Finish-intent carryover when you want only planned-to-finish items that did not finish.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

These companion artifacts keep the pulse debuggable when a leader wants the exact rows behind a metric or a count.