Sprint Pulse

Engineering Pulse — Team 2 ADS Q3 W33 - 17-21 Aug

Planned sprint ADS Q3 W33 - 17-21 Aug • planning snapshot + end-of-sprint outcome snapshot

This version uses the planning snapshot as the promise set and the outcome snapshot as the result set. Count metrics link to snapshot-exact JQL result pages. Jira IDs in the report link to live Jira issues.

Download DOCX

Executive summary

Yellow. The sprint closed 4/17 visible items. The team absorbed noise well — 0/1 added items were closed — but predictability on committed work was only 25.0% (4/16), and bugs made up 25.0% of completed items. The main drag was execution system quality, not readiness: 6/12 carryovers had been marked Ready at planning time.

Top-line metrics

MetricValueHow to read it
Committed completion25.0% (4/16)Planned items marked Done ÷ all planned committed items
Committed carryover75.0% (12/16)Planned committed carryovers ÷ all planned committed items
Finish predictability30.8% (4/13)Finish-intent planned items done ÷ all finish-intent planned items
Progress predictability100.0% (2/2)Progress items that behaved as intended by carrying
Added-during-sprint load5.9% (1/17)Added items ÷ all visible items
Added work closure0/1All added items marked Done
Reactive load (bug share)25.0% (1/4)Completed bugs ÷ all completed work
Planning quality56.2% (9/16)Committed items marked Ready ÷ all committed items
Workflow-truth mismatches0Items marked Done in review while workflow status remained non-final

Engineering readout

The sprint did not fail; it traded predictability for responsiveness. 0/1 added items were closed, but that responsiveness came with 25.0% bug share and diluted committed completion.

The miss pattern is concentrated: 8 partial-completion carryovers, 0 dependency-driven misses, and 4 committed items that never really started.

Most misses were not caused by poor readiness. 6 of the 12 carryovers had been marked Ready, so the stronger hypothesis is breakdown, sequencing, and capacity protection rather than simple scoping immaturity.

Delivered work mix

TypePlannedAddedStretchUnclearTotal doneDone %
Story000000.0%
Task3000375.0%
Bug1000125.0%

Committed work: plan vs execution

SignalValueWhy it matters
Committed items16Explicit promise set
Committed done4Closed as promised
Committed carry over12Unfinished promise
Committed items marked Ready9Planning-quality input
Carryovers marked Ready6Ready did not guarantee finish
Carryovers not started4Execution focus gap
Carryovers started but unfinished6Work moved, but did not close

Carryover pattern

Jira itemOwnerStatusWhy it carried
ADS-5654 — Story — [UPA,UPG, Asachi] Taxe școlarizareGeorge MurgociIn ProgressPartial completion
ADS-7251 — Story — Mutarea subscriptii de pe recurenta An scolar pe recurenta an calendaristicEdgar AlexaTestingPartial completion
ADS-7279 — Task — [Billing] - Implementare Stripe + Apple pay + Google payEdgar AlexaReady for testingPartial completion
ADS-7578 — Bug — Cache_redis_sentinel.php: Redis token-cache connection refusals turn GET /api/v2/fisiere/view into HTTP 500 - 254 hits/24hCojan Paul-CatalinTo DoNot started
ADS-7659 — Story — [Abonamente] - Nu pot selecta România din secțiunea de publicare, și nu mai apar pachetele pe site-ul publicEdgar AlexaIn ProgressPartial completion
ADS-7849 — Story — Stergere date S3Cojan Paul-CatalinTo DoNot started
ADS-8223 — Bug — [Prod][AWS][ingress] POST /api/v2/fisiere/upload maps backend 400 to HTTP 500 - 10/72hCojan Paul-CatalinTo DoNot started
ADS-8339 — Story — ToolsAlex MurarescuIn ProgressPartial completion
ADS-8383 — Story — [BE] - Local Cache BillingGeorge MurgociIn ProgressPartial completion
ADS-8499 — Task — Sync coduri SirutaCojan Paul-CatalinMergedPartial completion
ADS-8500 — Task — [AI] - Shared folder, logging, tracingAlex MurarescuIn ProgressPartial completion
ADS-8501 — Task — S3: Ștergere variabile OSS vechi și verificat că totul merge bineCojan Paul-CatalinTo DoNot started

Miss pattern summary

PatternCountWhat it suggests
Partial completion8Breakdown / sizing / stage-gating was not tight enough
Dependency delay0Capacity protection or dependency timing created slip
Not started4A committed item remained outside execution focus
In Progress / Code Review carryovers6Most misses were moving, but not closing

Workflow-truth mismatches

Items marked Done in the sprint-review field while Jira workflow status was still non-final.

Jira itemStatusIntent
None

Executive follow-up questions

QuestionWhy this mattersWhat evidence to ask for
Why did committed items carry over despite planning readiness?This tests execution quality rather than just scope quality.Show carryovers split by progress continuation, dependency, and not-started.
Are Progress items being managed intentionally?Progress items are allowed to continue, but the continuation should be visible and controlled.Show the original slice and the specific landing expectation for each item.
Is added work a healthy responsiveness level or chronic interruption?High responsiveness can hide systemic instability and diluted predictability.Show which added items were urgent/reactive versus discretionary scope change.
Can we trust Done in review when workflow is still non-final?Workflow-truth gaps reduce trust and make completion easy to game.Show the exact mismatches and the completion rule to enforce next sprint.

Usage note: start with the top-line metrics, then use the traceability links to answer these questions with issue-level evidence.

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1616 issues in the planning snapshot
Sprint review / outcome snapshot raw list1717 issues in the Friday review snapshot
Normalized sprint fact base1717 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

These companion artifacts keep the pulse debuggable when a leader wants the exact rows behind a metric or a count.