Product Pulse — Mobile ADS Q2 W22 - 01-05 Iunie

Planned sprint ADS Q2 W22 - 01-05 Iunie • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 3 of 8 visible items, including 2 Stories, 0 Tasks, and 1 Bugs. Product movement was real, but the sprint was still noisy: 3 items entered after planning and 2 of them were closed. The main misses were concentrated in 5 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items8Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items3Items whose final outcome bucket is Done
Carry overs5Items not closed at sprint review
Delivered mix2 / 0 / 1Stories / Tasks / Bugs delivered
Entry kind mix5 / 3 / 0Planned / Added during sprint / Stretch visible
Readiness mix6 / 2 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended2/2Progress items were expected not to finish in this sprint

Capacity context

SignalValueHow to read it
Available capacity50Policy-weighted engineering availability after holidays and OOO
Nominal capacity54.4Active workdays after weekends and bank holidays, before OOO
OOO capacity4.4Vacation / OOO days from tracker evidence when present
Bank holiday capacity13.6Policy-weighted public-holiday capacity removed from the sprint window
Included people18People with non-zero implementation capacity in this sprint window

Capacity is companion context for the pulse; it does not alter snapshot issue-count denominators.

It is not a true hours estimate.

OOO tracker export: capacity_ooo_tracker_export.csv

Pavel Petronel replaced Dron Gabriel

Paul Tanasuca ended without configured replacement

Rojan Shrestha replaced Raul Popovici

Stories done (2)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-7568 — [MOB] - Redesign menuPlanned
ADS-7761 — [MOB] Caching mechanism for news images & duplicates issue in news feedAdded

Tasks done (0)

Jira itemHow entered

Bugs done (1)

Jira itemHow entered
ADS-7758 — [MOB] - Ecran alba la accesarea notificarilor din categoria Wellbeing si mesaje pe aplicatia mobilaAdded

Carry overs / not delivered (5)

Jira itemWhy it carried
ADS-6358 — Story — [FE/Mobile] - Setari Sistem de notare
ADS-7141 — Story — [Mob] - Redesign dashboard profesorBug / rework pressure
ADS-7454 — Story — [MOB] - Afisare medii in functie de perioada de studiuPriority Change
ADS-7709 — Improvement — [MOB]: Nu se deschide modalul de adauga absenta / nota din catalog-secretariatNot started
ADS-7807 — Story — [MOB] - Notificări modul admitere

Blocker / miss pattern

MetricValueHow to read it
Partial completion0Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started1Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

2 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list44 issues in the planning snapshot
Sprint review / outcome snapshot raw list88 issues in the Friday review snapshot
Normalized sprint fact base88 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.