Sprint Pulse

Product Pulse — Mobile ADS Q2 W25 - 22-26 Jun

Planned sprint ADS Q2 W25 - 22-26 Jun • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 5 of 16 visible items, including 2 Stories, 2 Tasks, and 1 Bugs. Product movement was real, but the sprint was still noisy: 3 items entered after planning and 0 of them were closed. The main misses were concentrated in 11 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items16Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items5Items whose final outcome bucket is Done
Carry overs11Items not closed at sprint review
Delivered mix2 / 2 / 1Stories / Tasks / Bugs delivered
Entry kind mix12 / 3 / 1Planned / Added during sprint / Stretch visible
Readiness mix7 / 9 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended1/2Progress items were expected not to finish in this sprint

Stories done (2)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-7832 — BFF - MobilePlanned
ADS-7977 — [MOB] - Deeplink emailPlanned

Tasks done (2)

Jira itemHow entered
ADS-6098 — [Mobile] - nu apare "Management clasa" daca nu este materia "Dirigentie" in incadrarePlanned
ADS-7542 — [MOB] - Fixes and changesPlanned

Bugs done (1)

Jira itemHow entered
ADS-7811 — [Prod][mobile] Extracurricular periods endpoint returns error-level 403s when first-party app hits feature-disabled schoolsPlanned

Carry overs / not delivered (11)

Jira itemWhy it carried
ADS-5048 — Bug — [MOB] - Fixuri pentru release
ADS-5737 — Bug — [MOB][Photo] - Nu functioneaza filtrele de ani si de albumeNot started
ADS-5808 — Bug — [MOB][Wellbeing] - Parintele nu poate vizualiza testele de autocunoastere pe mobNot started
ADS-6990 — Bug — [MOB] - Mesaj gresit la stergerea unei note mai vechi de 24 ore
ADS-7141 — Story — [Mob] - Redesign dashboard profesorBug / rework pressure
ADS-7807 — Story — [MOB] - Notificări modul admitere
ADS-7831 — Story — [Spike] - Mobile app cold start
ADS-7962 — Story — [MOB] Translate app in French
ADS-7976 — Story — [MOB] BFF - newsfeedPartial completion
ADS-8049 — Bug — [MOB] - Primele doua ecrane de autentificare raman in limba romana dupa selectarea limbii engleze
ADS-8068 — Story — [MOB] - Încheiere situatie

Blocker / miss pattern

MetricValueHow to read it
Partial completion1Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started2Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

1 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

One Done row (ADS-7832 — Story — BFF - Mobile) is still flagged as Partial completion in the outcome file. The report respects the outcome as Done and treats the flag as a data-quality anomaly.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list13Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list16Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base16Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline13Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot16Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review13planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning3planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review0planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows0Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Visible sprint items16all rows in the outcome snapshot16/16Open denominator JQL
Delivered items5rows whose Sprint Outcome is Done5/16Open denominator JQL
Carry overs11rows whose Sprint Outcome is Carry Over or remained open in review11/16Open denominator JQL
Stories done2done items where issue type = Story2/5Open denominator JQL
Tasks done2done items where issue type = Task2/5Open denominator JQL
Bugs done1done items where issue type = Bug1/5Open denominator JQL
Entry kind mix12 / 3 / 1Planned / Added / Stretch counts across all visible sprint items16/16Open denominator JQL
Readiness mix7 / 9 / 0Ready / At risk / Not Ready counts across all visible sprint items16/16Open denominator JQL
Progress items behaving as intended1/2progress-intent items that carried as intended ÷ all progress-intent committed items1/2Open denominator JQL
Partial completion misses1carryover items whose miss reason is Partial completion1/11Open denominator JQL
Dependency / competing work misses0carryover items whose miss reason is Dependency delay0/11Open denominator JQL
Not-started misses2carryover items whose miss reason is Not started2/11Open denominator JQL

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.