Product Pulse — Mobile ADS Q3 W27 - 06-10 Jul

Planned sprint ADS Q3 W27 - 06-10 Jul • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 8 of 13 visible items, including 5 Stories, 1 Tasks, and 1 Bugs. Product movement was real, but the sprint was still noisy: 11 items entered after planning and 6 of them were closed. The main misses were concentrated in 5 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items13Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items8Items whose final outcome bucket is Done
Carry overs5Items not closed at sprint review
Delivered mix5 / 1 / 1Stories / Tasks / Bugs delivered
Entry kind mix2 / 11 / 0Planned / Added during sprint / Stretch visible
Readiness mix7 / 6 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended0/1Progress items were expected not to finish in this sprint

Stories done (5)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-7807 — [MOB] - Notificări modul admitereAdded
ADS-7976 — [MOB] BFF - newsfeedAdded
ADS-8098 — [MOB] - Filter school yearsAdded
ADS-8139 — [MOB] - Fix notification navigationAdded
ADS-8140 — [MOB] - Maarif Retake ExamPlanned

Tasks done (1)

Jira itemHow entered
ADS-8115 — [MOB] - Adauga suport pentru Dss NationalPlanned

Bugs done (1)

Jira itemHow entered
ADS-7219 — [MOB] - Fixes post release 06/04/2026Added

Carry overs / not delivered (5)

Jira itemWhy it carried
ADS-2456 — Bug — [Groups] - Rubrica Activitatea mea de la modul grupuri nu functioneaza pe android asa cum functioneaza pe IOS, pe Ios nu sunt trecute toate evenimentele
ADS-5808 — Bug — [MOB][Wellbeing] - Parintele nu poate vizualiza testele de autocunoastere pe mobNot started
ADS-7831 — Story — [Spike] - Mobile app cold startNot started
ADS-7884 — Story — [MOB] - Web bridge SDKPartial completion
ADS-8068 — Story — [MOB] - Încheiere situatieNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion0Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started3Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

0 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

One Done row (ADS-7219 — Bug — [MOB] - Fixes post release 06/04/2026) is still flagged as Priority Change in the outcome file. The report respects the outcome as Done and treats the flag as a data-quality anomaly.

One Done row (ADS-7976 — Story — [MOB] BFF - newsfeed) is still flagged as Partial completion in the outcome file. The report respects the outcome as Done and treats the flag as a data-quality anomaly.

One Done row (ADS-8139 — Story — [MOB] - Fix notification navigation) is still flagged as Late start / sequencing in the outcome file. The report respects the outcome as Done and treats the flag as a data-quality anomaly.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1111 issues in the planning snapshot
Sprint review / outcome snapshot raw list1414 issues in the Friday review snapshot
Normalized sprint fact base1313 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.