Sprint Pulse

Product Pulse — Mobile ADS Q3 W30 - 27-31 Jul

Planned sprint ADS Q3 W30 - 27-31 Jul • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 0 of 9 visible items, including 0 Stories, 0 Tasks, and 0 Bugs. Product movement was real, but the sprint was still noisy: 0 items entered after planning and all of them were closed. The main misses were concentrated in 9 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items9Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items0Items whose final outcome bucket is Done
Carry overs9Items not closed at sprint review
Delivered mix0 / 0 / 0Stories / Tasks / Bugs delivered
Entry kind mix9 / 0 / 0Planned / Added during sprint / Stretch visible
Readiness mix6 / 3 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended2/2Progress items were expected not to finish in this sprint

Stories done (0)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered

Tasks done (0)

Jira itemHow entered

Bugs done (0)

Jira itemHow entered

Carry overs / not delivered (9)

Jira itemWhy it carried
ADS-3527 — Bug — [Photos]- Primul videoclip dintr-un album video nu este redat corect în aplicația mobilă
ADS-4419 — Story — [Elev][Părinte] - Redesign - Noutati & Activitati
ADS-5808 — Bug — [MOB][Wellbeing] - Parintele nu poate vizualiza testele de autocunoastere pe mobNot started
ADS-6694 — Story — [MOB] - Test parentingPartial completion
ADS-8068 — Story — [MOB] - Încheiere situatiePartial completion
ADS-8237 — Bug — [MOB] - Problema la switch account de pe notif admission
ADS-8273 — Story — [MOB][Elev][Parinte] - Detalii elevPartial completion
ADS-8332 — Story — [MOB] Updates for "Module" & "Activity"
ADS-8334 — Story — [MOB] Fix issues reported by Google & flutter upgrade

Blocker / miss pattern

MetricValueHow to read it
Partial completion3Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started1Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

2 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list9Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list9Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base9Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline9Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot9Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review9planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning0planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review0planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows0Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Visible sprint items9all rows in the outcome snapshot9/9Open denominator JQL
Delivered items0rows whose Sprint Outcome is Done0/9Open denominator JQL
Carry overs9rows whose Sprint Outcome is Carry Over or remained open in review9/9Open denominator JQL
Stories done0done items where issue type = Story0/0Open denominator JQL
Tasks done0done items where issue type = Task0/0Open denominator JQL
Bugs done0done items where issue type = Bug0/0Open denominator JQL
Entry kind mix9 / 0 / 0Planned / Added / Stretch counts across all visible sprint items9/9Open denominator JQL
Readiness mix6 / 3 / 0Ready / At risk / Not Ready counts across all visible sprint items9/9Open denominator JQL
Progress items behaving as intended2/2progress-intent items that carried as intended ÷ all progress-intent committed items2/2Open denominator JQL
Partial completion misses3carryover items whose miss reason is Partial completion3/9Open denominator JQL
Dependency / competing work misses0carryover items whose miss reason is Dependency delay0/9Open denominator JQL
Not-started misses1carryover items whose miss reason is Not started1/9Open denominator JQL

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.