Sprint Pulse

Product Pulse — Org Adservio ADS Q1-26 W-14

Aggregated sprint ADS Q1-26 W-14 • deduplicated roll-up across included teams

This org roll-up aggregates deduplicated frozen issue facts across 1 team snapshots, then applies the same metric definitions and drill-down model. Counts in metric tables link to snapshot-exact JQL result pages.

Download DOCX

Executive summary

Yellow. The sprint closed 7 of 12 visible items, including 0 Stories, 3 Tasks, and 4 Bugs. Product movement was real, but the sprint was still noisy: 1 items entered after planning and 0 of them were closed. The main misses were concentrated in 5 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items12All rows in the outcome snapshot used for this retrospective
Delivered items7Items whose final outcome bucket is Done
Carry overs5Items not closed at sprint review
Delivered mix0 / 3 / 4Stories / Tasks / Bugs delivered
Entry kind mix11 / 1 / 0Planned / Added during sprint / Stretch visible
Readiness mix0 / 0 / 0Ready / At risk / Not Ready in the outcome snapshot
Progress items behaving as intended0/0Progress items were expected not to finish in this sprint

Stories done (0)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered

Tasks done (3)

Jira itemHow entered
ADS-7012 — [UNI][BE] Code Sanity: Deprecate and Remove Unused Endpoints, Services and DAO MethodsPlanned
ADS-7077 — [QA][Financiar] - E2E testing UMSPlanned
ADS-7193 — [BE][TUIASI] Migrarea notelor si absentelor de pe persoane cu intrări dublate in UMS, către conturile activePlanned

Bugs done (4)

Jira itemHow entered
ADS-6506 — [BUGS] -Plan de invatamant pe seriiPlanned
ADS-6933 — [BE][UPA] - Calcularea numarului de credite in 'Catalog' - 'Promovare studenți'Planned
ADS-7175 — [BE-JAva] - Media ECTS nu este calculata corect pentru anumiti studentiPlanned
ADS-7192 — [BE][Fisa disciplinei] - Ordinea continuturilor se modifica in UI in momentul editarii acestoraPlanned

Carry overs / not delivered (5)

Jira itemWhy it carried
ADS-6662 — Story — [Catalog][Situatie scolara] -US5 Download docPartial completion
ADS-6835 — Story — [Admitere v2] [US1.3] -Editare medie admitere singleMissing from outcome snapshot
ADS-6910 — Bug — [BE-PHP][Cazari] - Soldul de pe fisa studentului nu corespunde cu cel de pe studentPartial completion
ADS-7179 — Bug — [BE][Asachi] - Verificare note introduse in sesiunea 1Dependency delay
ADS-7234 — Bug — [BE][Asachi][Catalog-Situație școlara] - Nu se calculeaza media

Blocker / miss pattern

MetricValueHow to read it
Partial completion2Carryovers blocked by partial completion
Dependency / competing work1Delivery slipped because attention or dependency landed elsewhere
Not started0Committed item never really got underway

Data-quality caveats

This org roll-up is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

Included teams in this org pulse: University.

One Done row (ADS-7077 — Task — [QA][Financiar] - E2E testing UMS) is still flagged as Dependency delay in the outcome file. The report respects the outcome as Done and treats the flag as a data-quality anomaly.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Full snapshot list links

SnapshotIssue countLink
Planning snapshot full list1111 issues used for planning baseline
Sprint review / outcome snapshot full list1111 issues reviewed at sprint review

These links are snapshot-exact JQL lists, intended for drill-down and debugging.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.