Sprint Pulse

Product Pulse — Team 1 ADS Q3 W30 - 27-31 Jul

Planned sprint ADS Q3 W30 - 27-31 Jul • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 11 of 25 visible items, including 3 Stories, 2 Tasks, and 5 Bugs. Product movement was real, but the sprint was still noisy: 13 items entered after planning and 8 of them were closed. The main misses were concentrated in 14 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items25Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items11Items whose final outcome bucket is Done
Carry overs14Items not closed at sprint review
Delivered mix3 / 2 / 5Stories / Tasks / Bugs delivered
Entry kind mix12 / 13 / 0Planned / Added during sprint / Stretch visible
Readiness mix7 / 17 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended3/4Progress items were expected not to finish in this sprint

Stories done (3)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-5784 — [FE/BE] Refactor pagina de permisiuniPlanned
ADS-6638 — [Preferinte][Notificari] Refactor pagina de gestionare notificăriAdded
ADS-8376 — Stergere coduri vechiAdded

Tasks done (2)

Jira itemHow entered
ADS-7274 — [FQ] Implementare afisare numar matricol pentru rolurile de elev si parinteAdded
ADS-8281 — [QA]: Testat crearea de clase normal + bulkAdded

Bugs done (5)

Jira itemHow entered
ADS-7555 — Fix period selection for grades and absencesAdded
ADS-7638 — Close situation” option is incorrectly visible to teachers when the grading setting is set to “NeverAdded
ADS-8285 — [Medii] - Recalculare medii greșitePlanned
ADS-8373 — Student users can see the data from other studentsAdded
ADS-8374 — XSS vulnerability - student grades statisticsAdded

Carry overs / not delivered (14)

Jira itemWhy it carried
ADS-2590 — Bug — [Students] - Trebuie inlocuit articolul de la model import automat-date de completare si sa se deschida articolul din manualul de utilizare daca de da click pe linkul respectivPartial completion
ADS-3619 — Story — [Conduita] - View diriginte
ADS-6357 — Story — [Conduita] - Adaugarea materiei in conduita
ADS-7816 — Story — [SIIIR] - Import clasePartial completion
ADS-7907 — Task — [BE] Refactoring SQL_CALC_FOUND_ROWSPartial completion
ADS-8067 — Story — [Incadrare] Refactoring React & APILate start / sequencing
ADS-8105 — Story — Impartirea pe modulePartial completion
ADS-8168 — Task — [QA] - Testat Orarul
ADS-8209 — Bug — [Prod][AWS][legacy-web] GET /api/v2/fisiere/view returns HTTP 500 when M_fisiere.php calls query() on nullNot started
ADS-8306 — Bug — [FE] - Nefunctionalitate filtru "Elevi"
ADS-8310 — Bug — [Prod][AWS][legacy-web] Admin home reads missing school session context and renders warnings - 35 errors/72h
ADS-8331 — Task — [FE] - Student detailsPartial completion
ADS-8366 — Bug — [Prod][AWS][legacy-web] Tenantless API requests hit null school DB handle across timetable, grades, and portfolio
ADS-8375 — Story — Refactor temporary S3 buckets solution for files

Blocker / miss pattern

MetricValueHow to read it
Partial completion5Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started1Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

3 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list12Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list25Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base25Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline12Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot25Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review12planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning13planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review0planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows0Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Visible sprint items25all rows in the outcome snapshot25/25Open denominator JQL
Delivered items11rows whose Sprint Outcome is Done11/25Open denominator JQL
Carry overs14rows whose Sprint Outcome is Carry Over or remained open in review14/25Open denominator JQL
Stories done3done items where issue type = Story3/11Open denominator JQL
Tasks done2done items where issue type = Task2/11Open denominator JQL
Bugs done5done items where issue type = Bug5/11Open denominator JQL
Entry kind mix12 / 13 / 0Planned / Added / Stretch counts across all visible sprint items25/25Open denominator JQL
Readiness mix7 / 17 / 0Ready / At risk / Not Ready counts across all visible sprint items25/25Open denominator JQL
Progress items behaving as intended3/4progress-intent items that carried as intended ÷ all progress-intent committed items3/4Open denominator JQL
Partial completion misses5carryover items whose miss reason is Partial completion5/14Open denominator JQL
Dependency / competing work misses0carryover items whose miss reason is Dependency delay0/14Open denominator JQL
Not-started misses1carryover items whose miss reason is Not started1/14Open denominator JQL

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.