Sprint Pulse

Product Pulse — Team 1 ADS Q3 W34 - 24-28 Aug

Planned sprint ADS Q3 W34 - 24-28 Aug • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 14 of 30 visible items, including 2 Stories, 1 Tasks, and 9 Bugs. Product movement was real, but the sprint was still noisy: 12 items entered after planning and 6 of them were closed. The main misses were concentrated in 16 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items30Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items14Items whose final outcome bucket is Done
Carry overs16Items not closed at sprint review
Delivered mix2 / 1 / 9Stories / Tasks / Bugs delivered
Entry kind mix18 / 12 / 0Planned / Added during sprint / Stretch visible
Readiness mix11 / 16 / 3Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended2/2Progress items were expected not to finish in this sprint

Stories done (2)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-7111 — Conturi parinti active/inactivePlanned
ADS-8105 — Impartirea pe moduleAdded

Tasks done (1)

Jira itemHow entered
ADS-8516 — Routes calendar detailsPlanned

Bugs done (9)

Jira itemHow entered
ADS-7654 — Grades.php / AverageCalculator: POST /api/v2/grades accepts grade but skips average recomputation - 2 errors/24hPlanned
ADS-8324 — [BE] - Indicatori gresiti ID 5809Added
ADS-8455 — [AWS prod][Teacher school years] M_cadre omits pagination total after merge - 396 errors/6hPlanned
ADS-8474 — [Documente] - Indicatori gresiti ID 5809Planned
ADS-8508 — [Cont] - Nu se poate modifica genul și data nașteriiPlanned
ADS-8511 — [BE] ordinea claselor la adaugarePlanned
ADS-8542 — [FE] Materiile nu au elevi asociati dupa copierea incadrariiPlanned
ADS-8571 — [FE] La copierea încadrării de anul trecut, nu sunt bifați elevii în mod automatAdded
ADS-8582 — [FE] Nu se poate motiva o absenta atunci cand suntem pe tab-ul "toate"Added

Carry overs / not delivered (16)

Jira itemWhy it carried
ADS-2590 — Bug — [Students] - Trebuie inlocuit articolul de la model import automat-date de completare si sa se deschida articolul din manualul de utilizare daca de da click pe linkul respectivNot started
ADS-7816 — Story — [SIIIR] - Import clasePartial completion
ADS-7818 — Story — [SIIIR] - Import eleviPartial completion
ADS-7852 — Task — [BE]: Dezactivare actiuni noteaza (si bulk) daca media anuala si/sau media semestriala este incheiataDependency delay
ADS-8067 — Story — [Incadrare] Refactoring React & APIUnder Estimated
ADS-8209 — Bug — [Prod][AWS][legacy-web] GET /api/v2/fisiere/view returns HTTP 500 when M_fisiere.php calls query() on nullNot started
ADS-8366 — Bug — [Prod][AWS][legacy-web] Tenantless API requests hit null school DB handle across timetable, grades, and portfolioNot started
ADS-8400 — Story — [Incadrare] - Imparte clasaPartial completion
ADS-8462 — Task — [Localizare] Elemente netraduse în interfața English, grupate per rolPartial completion
ADS-8506 — Bug — [Prod][AWS][legacy-web] Student export binds an empty DATE value and silently returns no rows - 10 errors/72hNot started
ADS-8510 — Bug — [FE] diferenta numar elevi in raportul "promovabilitae elevi"Priority Change
ADS-8569 — Task — [BE] transfer date comasare scoliNot started
ADS-8570 — Task — [FE] inactivare conturi in urma comasariiNot started
ADS-8580 — Task — Recuperare date sterse elev ID 775987Dependency delay
ADS-8593 — Bug — [Prod][TUIASI][legacy-web] Admin edit reads missing suppressAdminEvent flag - 2 warnings/72hNot started
ADS-8598 — Task — [BE] aflare cine l-a sters pe elev ID 2372338Dependency delay

Blocker / miss pattern

MetricValueHow to read it
Partial completion3Carryovers blocked by partial completion
Dependency / competing work1Delivery slipped because attention or dependency landed elsewhere
Not started4Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

2 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list2626 issues in the planning snapshot
Sprint review / outcome snapshot raw list3838 issues in the Friday review snapshot
Normalized sprint fact base3030 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.