Executive summary

Yellow. The sprint closed 15 of 34 visible items, including 1 Stories, 5 Tasks, and 8 Bugs. Product movement was real, but the sprint was still noisy: 18 items entered after planning and 11 of them were closed. The main misses were concentrated in 19 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items34Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items15Items whose final outcome bucket is Done
Carry overs19Items not closed at sprint review
Delivered mix1 / 5 / 8Stories / Tasks / Bugs delivered
Entry kind mix16 / 18 / 0Planned / Added during sprint / Stretch visible
Readiness mix13 / 20 / 1Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended1/2Progress items were expected not to finish in this sprint

Stories done (1)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-7818 — [SIIIR] - Import eleviPlanned

Tasks done (5)

Jira itemHow entered
ADS-8486 — [Catalog] - Import note din VIVA (verificare format și date necesare)Added
ADS-8695 — [BE]: Adaugare nota tip corigenta pe MaarifPlanned
ADS-8755 — Stergerea bazei de date cu elevii incarcatiPlanned
ADS-8791 — [BE] stergere moduleAdded
ADS-8795 — nu se primesc codurile de inregistrare/ mail de confirmare pe adresa de e-mail domeniuAdded

Bugs done (8)

Jira itemHow entered
ADS-8724 — [FE/BE] Modal detalii elev ani trecuțiAdded
ADS-8742 — [FE] catalogul descarcat din arhiva nu contine numele/prenumele/nr telefon al parintilor la date personaleAdded
ADS-8750 — [Prod] service-fetgenerator crashes on unhandled TypeError when fet-cl reports a data validation errorAdded
ADS-8754 — [FE] intarziere la selectarea coordonatorului clasei si pierderea datelor completate la refreshPlanned
ADS-8784 — [FE] pentru un elev transferat, nu se gaseste transferul in modulul "transferuri"Added
ADS-8789 — [FE] eroare 400 la completare formular contactAdded
ADS-8797 — [FE] - Image CropperAdded
ADS-8799 — [FE] selectarea altui elev din catalog nu actualizeaza paginaAdded

Carry overs / not delivered (19)

Jira itemWhy it carried
ADS-2590 — Bug — [Students] - Trebuie inlocuit articolul de la model import automat-date de completare si sa se deschida articolul din manualul de utilizare daca de da click pe linkul respectivNot started
ADS-3757 — Story — [Site] - Actualizare website AdservioPartial completion
ADS-7803 — Task — [FE/BE/MOB/UNI] - TitulaturaPartial completion
ADS-7817 — Story — [SIIIR] - Import cadre didacticePartial completion
ADS-7852 — Task — [BE]: Dezactivare actiuni noteaza (si bulk) daca media anuala si/sau media semestriala este incheiataPartial completion
ADS-8569 — Task — [BE] transfer date comasare scoliPartial completion
ADS-8570 — Task — [FE] inactivare conturi in urma comasariiPartial completion
ADS-8580 — Task — Recuperare date sterse elev ID 775987Partial completion
ADS-8598 — Task — [BE] aflare cine l-a sters pe elev ID 2372338Partial completion
ADS-8713 — Bug — [FE] cod de inregistrare invalid la accesarea linkului din emailNot started
ADS-8721 — Bug — [FE] Butonul de semnare a condicii de prezenta nu e afisat pentru rolul de contabilNot started
ADS-8723 — Improvement — Posibilitate generare orar atunci cand exista 2 profesori principaliPartial completion
ADS-8758 — Task — de mutat elevii de clasa aVIII de pe scoala ID 6179 pe ID 6254Partial completion
ADS-8760 — Task — [FE]: Schimbari pe Suprascrieri si transferuriNot started
ADS-8766 — Bug — [Prod][AWS][legacy-web] Bulk class creation returns 500 when generated class name exceeds storage limit - 35 failures/72hNot started
ADS-8785 — Bug — [Prod][AWS][Auth] Password recovery silently skips missing parent profile - 28 requests/72hNot started
ADS-8792 — Task — Stergere elevi dublati la sincronizarea cu SIIRNot started
ADS-8802 — Bug — [FE] ordine absente gresita pentru elevii de gradinita- 2024-2025Not started
ADS-8806 — Improvement — [SIIIR] Improvments & bugsPartial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion9Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started5Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

1 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list2626 issues in the planning snapshot
Sprint review / outcome snapshot raw list3939 issues in the Friday review snapshot
Normalized sprint fact base3434 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.